MBO Inc. Commissioning Presentation

Download Report

Transcript MBO Inc. Commissioning Presentation

LEED®-NC Commissioning
Presented by MBO Inc.
Your Speakers for Today
Jorge Torres Coto, LEED AP
Building Systems Commissioning Engineer
MBO, Inc.
[email protected]
Brought to you by
MBO, Inc.
Outline



What is commissioning?
Benefits and cost of Cx
LEED Requirements and tips





EAp1
EAc3
Examples and experience on LEED Cx
Who can be the Cx Provider?
Going beyond the LEED requirements and
expectations
What is Commissioning (Cx)?


Technical systematic process of verifying
and testing Building Systems
TOTAL QUALITY ASSURANCE!
–
–
–
It applies to the Building Design
It applies to the Construction of the Building
It applies to the turnover of the building
What Cx is NOT






Peer Review
Contractor’s Q & A program
Paper only process
Testing, Adjusting & Balancing
System Troubleshooting process
Inspection Process only
Cx Process
What are the Benefits of Cx








Systems perform as intended
Lower energy use and cost
Early detection of potential problems
Better building documentation (Systems Manual)
Trained building operators
Lower Operations & Maintenance (O&M) cost
Enhanced Indoor Environmental Quality (IEQ)
Reduced construction costs (<Change Orders)
What can and will be Commissioned

Whole Building Commissioning NIBS
– Guideline 0
ASHRAE/NIBS The Cx Process
– Guideline 1
ASHRAE, HVAC&R System
– Guideline 2
ASCE, Structural System
– Guideline 3
BETEC, Exterior Envelope System
– Guideline 4
NRCA, Roofing System
– Guideline 5
AWCI, Interior System
– Guideline 6
NEII, Elevator System
– Guideline 7
ASPE, Plumbing System
– Guideline 8
IES, Lighting System
– Guideline 9
IEEE, Electrical System
– Guideline 10
NFPA, Fire Protection System
– Guideline 11
TIA, Telecommunications System
Economics of Cx

The operating costs of a commissioned
building are 8 – 20% lower than a
comparable non-commissioned building
(GSA Building Commissioning Guideline)
Other benefits of Cx

Reduced change orders.
–

Reduce RFI’s
–

0.5% - 10% of total MEP change orders
RFI’s turn into change orders $$$
Improved occupant comfort = Productivity
–
$0.10/ft2/year
Cost associated with Cx
Commissioning cost ($/Gft2)
Gft2
$0.50
$1.00
$1.50
300,000+
200,000
100,000
50,000
15,000
Simple
Complex
Commissioning cost can
vary considerably from
project to project.
Actual cost depend on:

Project size

Project complexity

Rigor of Cx effort
The question is not
whether you can
afford to Cx? But,
can you afford not
to?
Cx – The Bottom Line

Cx adds value.
–
–
–
Helps maintain and prove the Green excitement
Ensures IEQ benefits
ROI
ASHRAE Cx Process
The 4 phases of the Cx Process
1. PREDESIGN
4. OCCUPANCY
OPERATIONS
Cx PROCESS
3. CONSTRUCTION
2. DESIGN
LEED Rating System

Sustainable Sites
Water Efficiency

Energy & Atmosphere

–
–



Pre-1
Cre-3
Fundamental Systems Cx
Enhanced Cx
Materials & Resources
Indoor Environmental Quality
Innovation & Design Process
Energy & Atmosphere EAp1
Pre-1Fundamental Systems Cx
1.
2.
3.
4.
5.
6.
Designate a Cx Authority
Document OPR and develop BOD
Incorporate Cx requirements into CD
Develop and implement Cx plan
Verify the installation and
performance of the Commissioned
systems
Complete a summary of the Cx
Report
1.Designate the Cx Authority
Part of the owner’s team (ideally)
Third party in preferred but can be part of
the design team
CxA shall be independent of the project’s design
and construction management, though they
may be employees of the firms providing
those services.
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
2.Document OPR & BOD

–
Completed by Owner, CxA and Project Team







1.Designate a Cx Authority
OPR
Owner and user requirements
Environmental and sustainable goals
Energy efficiency goals
IEQ requirements
Equipment and System expectations
Building occupant and O&M personnel requirements
BOD
–
Completed by the design team



Primary design assumptions
Standards
Narrative descriptions
2.Document OPR and
develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
3.Incorporate Cx into CD’s
 Project
–
–
Typically the Cx requirements are in
the specs.
US DOE / PECI Guide

–
Specifications
http://peci.org/library/mcpgs.htm
Whole Building Design Guide

http://www.wbdg.org/ccb/browse_org.php?
o=70
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx
requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
5.Develop & Implement Cx Plan

Start early
–

Preferably during DD
It is not a rigid document
–
changes with planning, scheduling,
etc.
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx
plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
7.Verify the installation &
performance of the systems



Installation inspection
System performance testing
Evaluation of results compared to
OPR/BOD
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and
performance of the
Commissioned
systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
10.Complete Cx Report



Executive summary on the
process & results
Deficiency list with resolutions
Performance test results
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of
the Cx Report
11.Review building operation within 10
months after substantial
completion
Certification Submittals

LEED Letter template
–
–
–
–
–
Completed OPR and BOD
Incorporated Cx into specifications
Cx plan
Verified installation and performance of systems
Completed Cx Report
Energy & Atmosphere EAc3
Cre-3 Enhanced Commissioning
3.
Designate a Cx Authority
Document OPR and develop BOD
Incorporate Cx requirements into CD
4.
Conduct Cx design review prior to CD
5.
Develop and implement Cx plan
6.
Review contractor submittals applicable to Cx scope
7.
Verify the installation and performance of the commissioned systems
8.
9.
Develop Systems Manual
Verify requirements for training are complete
10.
Complete a summary of the Cx Report
11.
Review building operation within 10 months after
substantial completion
1.
2.
Cre-3

Enhanced Cx
Cx Authority must be an independent party
–
The CxA shall perform at least:



Design review prior to CD’s
Review contractor submittals
Review building operation (post-occupancy)
4.Design Review

Minimum one Cx design review of:
–
–
–

OPR
BOD
Design documents prior to mid-CD
phase
Back check review comments in
subsequent submission
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx
Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
6.Review Contractor Submittals

Only review submittals
applicable to systems being
commissioned for compliance
with OPR and BOD.
–
–
–
Do they meet OPR and BOD
O & M requirements
Facilitating performance testing
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s
Approved Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
8.Develop Systems Manual



In addition to the O&M manual that is provided
to the staff by the contractor.
Focuses on operations rather than
maintenance.
Specifics of interactions between equipment
–
–
–
–
–
–
–
Final version of BOD
Single line diagrams
As-built sequences of operation
Operating instruction for integrated systems
Recommended maintenance schedules
Recommended retesting schedules with blank
test forms
Recommended recalibration schedules for
sensors and actuators
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual
for the Cx Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
9.Verify Requirements for Training



Document training expectations
and needs with the owner
Ensure staff and occupants
receive training and orientation
Special attention should target
new or uncommon design
features that have a potential of
being over-ridden or removed
due to lack of understanding.
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for
Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building operation within 10
months after substantial
completion
11.Review Building Operations



After handover ( 6 – 10 months)
review performance of
building/facility with owner and O&M
staff.
Create a deficiencies list (prior to
manufacturer / contractors warranty
expiration)
Any items listed on the deficiencies
list that will not be corrected shall be
documented in the Systems Manual
1.Designate a Cx Authority
2.Document OPR and develop BOD
3.Incorporate Cx requirements into CD
4.Conduct Design phase Cx Review
5.Develop and implement Cx plan
6.Review Contractor’s Approved
Submittals
7.Verify the installation and performance
of the Commissioned systems
8.Develop Systems Manual for the Cx
Systems
9.Verify the requirements for Training are
completed.
10.Complete a summary of the Cx
Report
11.Review building
operation within 10
months after
substantial
completion
Certification Submittals

LEED Letter template
–
–
–
–
–
CxA conducted design review
CxA reviewed submittals
Systems Manual
O&M staff and occupants have been trained
CxA review of building operation post-occupancy
USGBC’s CxA inerpretations


CxA for Cre-3 has to be independent, cannot be
hired by design or construction team
Late in the game.
–

If owner commits to LEED late it is acceptable to provide
two reviews during and after CD’s in lieu of reviews at SD
and CD
For prototype buildings:
–
–
Reviews are acceptable after SD
2 reviews are to be performed on latter stages of design.
Open Forum
 Questions?
Comments?
Complaints?
Praises?
Cx References





www.peci.org
http://www.wbdg.org/ccb/NIBS/nibs_gl3.pdf
www.ashrae.org
www.bcxa.org
www.cacx.org/library
THANK YOU