ASHRAE Guideline 0-2005
The Commissioning Process
Building Commissioning Association
Northeast Chapter
Thomas Anderson, CCP
Purpose of Guideline 0-2005

Describe the Cx Process to verify a
facility meets the Owner’s Project
Requirements
Utilization


Guideline Describes the “Process”
Technical Guidelines Detail Technical
Requirements
Guideline 0-2005 The Cx Process

ASHRAE Guideline 1-200X


HVACR Cx Process (Tech Requirements)
NIBS Guidelines



2-200X through 14-200X Requirements
Other Technical Cx Volumes
Roofing, Lighting, Plumbing, Life
Safety, Etc.
Pre Design Phase



Develop Owner’s Project
Requirements (OPR)
Cx Scope & Budget
Develop Initial Cx Plan
Owner’s Project Requirements

Forms the basis from which all
decisions are made…




Design
Construction
Acceptance
Operational Decisions
Owner’s Project Requirements

Primary Tool for Benchmarking
Success and Quality


At all Phases of Project Delivery
Throughout the Life of Facility
Owner’s Project Requirements


Owner’s Objectives for a New Facility
Guidance for Design Team & Others

Not developed by Design Team
OPR Should Include…






Schedule & Budget
Cx Scope & Budget
User Requirements
Energy Efficiency Goals
Applicable Codes & Standards
Etc.
An OPR is Dynamic…


Evolves through each Phase
Updated to Reflect Current Project
Requirements


Feasibility
Budget Limitations
Design Phase Cx Tasks




Verify Basis of Design (BoD) with OPR
Update Cx Plan
Defining Training Requirements
Perform Focused Design Reviews



Developed by Design Team
CxA Verifies BoD Conforms to OPR
Systems Manual
Basis of Design

Basis of Design (BoD)



Conveys Design Assumptions that Fulfill
OPR Intent
Developed by Design Team
Updated throughout Design Phase
Basis of Design Includes


System Selection Reasoning
Assumptions





Narrative of System Selection &
Reasoning
Environmental Conditions
Load Calcs & Sizing
Codes
Operations
Systems Manual

Information Needed to…



Understand Systems
Operate
Maintain
Systems Manual Includes






Index of Systems Manual
Executive Summary
OPR
BoD
O&M Manuals
Cx Process Report
Construction Phase






Verify Systems & Assemblies Conform
to OPR
Submittal Review (Spot Check)
Develop Test Docs
Witness Tests
Verify Training
Update Systems Manual (OPR, BoD,
Etc.)
Occupancy & Operations Phase



Begins at Substantial Completion
Continue through end of
Contractual/Warranty Period
Ideally, Continues through Life of the
Facility
Occupancy & Operations Phase






CxA Assists in Problem Solving
Guidance on O&M to Achieve OPR
Seasonal Testing
Verify Training
Systems Manual Update
Cx Report