Cx Guideline 0-2005
Download
Report
Transcript Cx Guideline 0-2005
ASHRAE Guideline 0-2005
The Commissioning Process
Building Commissioning Association
Northeast Chapter
Thomas Anderson, CCP
Purpose of Guideline 0-2005
Describe the Cx Process to verify a
facility meets the Owner’s Project
Requirements
Utilization
Guideline Describes the “Process”
Technical Guidelines Detail Technical
Requirements
Guideline 0-2005 The Cx Process
ASHRAE Guideline 1-200X
HVACR Cx Process (Tech Requirements)
NIBS Guidelines
2-200X through 14-200X Requirements
Other Technical Cx Volumes
Roofing, Lighting, Plumbing, Life
Safety, Etc.
Pre Design Phase
Develop Owner’s Project
Requirements (OPR)
Cx Scope & Budget
Develop Initial Cx Plan
Owner’s Project Requirements
Forms the basis from which all
decisions are made…
Design
Construction
Acceptance
Operational Decisions
Owner’s Project Requirements
Primary Tool for Benchmarking
Success and Quality
At all Phases of Project Delivery
Throughout the Life of Facility
Owner’s Project Requirements
Owner’s Objectives for a New Facility
Guidance for Design Team & Others
Not developed by Design Team
OPR Should Include…
Schedule & Budget
Cx Scope & Budget
User Requirements
Energy Efficiency Goals
Applicable Codes & Standards
Etc.
An OPR is Dynamic…
Evolves through each Phase
Updated to Reflect Current Project
Requirements
Feasibility
Budget Limitations
Design Phase Cx Tasks
Verify Basis of Design (BoD) with OPR
Update Cx Plan
Defining Training Requirements
Perform Focused Design Reviews
Developed by Design Team
CxA Verifies BoD Conforms to OPR
Systems Manual
Basis of Design
Basis of Design (BoD)
Conveys Design Assumptions that Fulfill
OPR Intent
Developed by Design Team
Updated throughout Design Phase
Basis of Design Includes
System Selection Reasoning
Assumptions
Narrative of System Selection &
Reasoning
Environmental Conditions
Load Calcs & Sizing
Codes
Operations
Systems Manual
Information Needed to…
Understand Systems
Operate
Maintain
Systems Manual Includes
Index of Systems Manual
Executive Summary
OPR
BoD
O&M Manuals
Cx Process Report
Construction Phase
Verify Systems & Assemblies Conform
to OPR
Submittal Review (Spot Check)
Develop Test Docs
Witness Tests
Verify Training
Update Systems Manual (OPR, BoD,
Etc.)
Occupancy & Operations Phase
Begins at Substantial Completion
Continue through end of
Contractual/Warranty Period
Ideally, Continues through Life of the
Facility
Occupancy & Operations Phase
CxA Assists in Problem Solving
Guidance on O&M to Achieve OPR
Seasonal Testing
Verify Training
Systems Manual Update
Cx Report