PEDDAGEDDA PROJECT

Download Report

Transcript PEDDAGEDDA PROJECT

PEDDAGEDDA PROJECT
Project cost : 73.19 Crores
Earth Dam 500.00Mt to 200.00 Mt
Ayacut
: 12000 Acres
RESERVOIR
Existing Karri valasa Anicut Irrigating 5594 Acres
VEGAVATHI RIVER
18Km
RIGHT MAIN CANAL
Earth Dam 96.25 Mt to 500.00 Mt
SPILLWAY ( 0.00 to 96.25)
Non EPC Package
Works under progress
Distributory system
EPC Package Works
under progress
Category II EPC Package :The balance Earth Dam from 500 to 2200 Mt, Gates, Right
Main canal including distributories, CM&CD works, Field channels and improvements
to existing Vegavathi system are Grounded with agreement amount of 38.80 Crores.
PEDDAGEDDA PROJECT PROFILE
1
PROJECT PROFILE : Across river Vegavati river. Formation of earth dam, construction of
spillway excavation of right main canal, distributaries to irrigate 12000
acres.
2
: 1.
Administrative Sanction
G. O. Ms. No. 91, I & CAD, Dt: 19-062003 for Rs. 26.52 Crores
2.
G.O.Ms.No.5, I&CAD, Dt.11-1-2005 for
Rs.46.67 Crores
Total: 73.19 Crores
3
4
No. of EPC Packages
: 1 Nos
Non EPC Packages
: 2 Nos.
Agreement value of 3 packages
: Rs. 52.73 Crs.
(EPC Rs.38.80 Crs. + Non EPC Rs.13.93
Crs.)
5
Budget provision for 200607
6
Expenditure of the project
: Rs.60.00 Crs.
2004 – 05 : Rs. 12.98 Crs.
2005 – 06 : Rs. 19.94 Crs.
Cum. Exp.
7
Utilisation
: Rs. 32.82 Crs
: 1.05 TMC
9
Land Acquisition
Required
: 1045 acres
Requisitioned
: 870 acres
Acquired
: 773 acres
10
Forest Land
: An extent of 95.00 hectares is acquired.
An amount of Rs. 3.269 Lakhs was
deposited with DFO/Vizianagaram
11
Estimated cost of L.A.
: Rs.1.5 Crs
12
Estimated cost of R & R
: Under preparation
13
Clearances
: All CWC clearances including
investment clearance obtained
14
Mob. Advance (Rs. in Crores)
Paid
Recovered
2004-05 :
3.34
--
2005-06 :
1.90
0.83
Total : Rs. 5.24
Rs. 0.83
PEDDAGEDDA RESERVOIR
Non-EPC-1 : Formation of Earth Dam from Name of the Contractor
Ch. 96.25m to Ch.500m including construction Agreement Amount
of head sluices
: Mr. R. Subbaraju,
: Rs. 5.68 Crs.
Agreement Date
: 21-04-2004
Period of Completion
: 16 Months

Investigation
: Completed

Designs
: Completed

Execution
: Completed earth dam length 365 mt. against 403.75 mt.

Structures
: Completed

Qty. of earth work done
: 9,39,000 cum against 11,07,000 cum.

Qty. of concrete work done : 973 cum.

Expenditure
:
2004-2005
- Rs. 6.37 Crs.
2005-2006
-
Cum. Mob. Adv. only
- Rs. 6.37 Crs.

Land Acquisition
: Required - 1045 acres, Acquired - 773 acres

Forest Land
: 95 Hectares acquired
--
PEDDAGEDDA RESERVOIR
Non-EPC-2 : Construction of spill way
regulator form Ch.0.00m to Ch.96.25
including NOF Dam River Sluice,
Surplus Course etc.
Name of the Contractor : M/s. Deepika Constructions
Agreement Amount
: Rs. 8.25 Crs.
Agreement Date
: 04-11-2004
Period of Completion
: 18 Months

Investigation
: Completed

Designs
: Completed

Execution
: 96.25 Mts against 96.25 Mts length.

Structures
: Completed

Qty. of earth work done
: 85,281 cum against 1,64,420 cum.

Qty. of concrete work done : 26100 cum against 31,316 cum.

Expenditure
Crs.
Crs.
Crs.

Land Acquisition
:
2004-2005
- Rs. 4.67
2005-2006
- Rs. 6.24
Cum. Mob. Adv. only
- Rs. 10.91
: Required 796.78 Acres, Acquired 290.76
PEDDAGEDDA RESERVOIR
Pkg.No.3/EPC/Cat-II : Formation of Earth
Dam from Km.0.50 to Km.2.20 and
excavation of Right Main Canal, CM&CD
works, distributories, field channels etc.
Name of the Contractor
: M/s. GHRA-KKRC(JV)
Agreement Amount
: Rs. 38.80 Crs.
Agreement Date
: 26-02-2005
Period of Completion
: 24 Months

Investigation
: Completed for a length 8.2Km against 18 Km.

Designs
: approved 1.930 Km against 1.930 (Earth work)

Designs (structures)
: 22 Nos against 39 Nos.

Execution
: Work is in progress

Qty. of earth work done : 51,000 cum against 4,21,000 cum.

No. of Machinery
: Deployed 26 Nos. (Excavation -4, Tippers-9, JCB-1 etc)

Expenditure
Crs.
:
2004-2005
2005-2006
Cum. Mob. Adv. only

Land Acquisition
- Rs. 1.94
- Rs. 12.25 Crs.
- Rs. 14.19 Crs.
: Required 232.12 Acres, Acquired 164.53 Acres.