IT PROJECTS-UNDER CAO/FOIS

Download Report

Transcript IT PROJECTS-UNDER CAO/FOIS

IT PROJECTS

(UNDER CAO/FOIS)

FIRST QUARTER REVIEW ********

PROGRESS AND CONCERNS

APPROACH

1.

PRESENT PROJECT SPECIFIC DETAILS WITH AREAS REQUIRING BOARD’S INTERVENTION 2.

SHARE OUR VISION ON GENERAL ISSUES INFRASTRUCTURE,TRAINING AND INSTITUTIONALISION

IMPORTANT PROJECTS

1. FOIS 2. COA 3. ICMS 4. CMS

GENERAL ISSUES

V-SAT EXPANSION INFRASTRUTURE -BLDGS TRAINING SETTING UP OF CONTROLS

ISSUES-FOIS

V-SAT INSTALLATION AT 203 TMS SITES EQUIPMENTS AVAILABILITY RAILWAY’S INVOLVEMENT CHANGED TRAFFIC PATTERN

FOIS TMS Module 524* locations on IR 212 locations on VSAT 324 locations online covering 376 sites 126 locations printing RR online covering 176 sites Around 1100 PCs and 400 printers supplied so far 668 PCs and 612 printers under supply *(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)

TMS VSAT locations 212 TMS locations have to be commissioned on VSATs by IRPMU Railway Board’s target was June 2006. IRPMU’s revised target is Sept 2006 53 VSATs have been installed upto 30.06.06

37 of these were commissioned upto June 2006 The target for July 2006 is for commissioning 64 locations on VSAT Target for 118 (64+53) locations is 15 th Aug 2006 72 locations have been commissioned upto 10.08.06

IMPACT ON TARGET FOIS

V-SAT DEPENDENT TMS SITES(212) WILL TAKE LONGER TO STABLISE  RESPONSE TIME ISSUES (1500 vs700 msecs)  CHANGE IN HUB FROM VENDOR’S TO OUR OWN (Realignment of each dish)

DECISION/ASSITANCE FOIS

Nomination of 2 Rates Inspectors by each zone to CAO/FOIS for verification of referential database and testing of software changes due to rates circulars Board’s directive for AT/generator supply from station to TMS site

STATUS-COA

Pilot project under trial at Madurai and Trivandrum divisions of SR DOMs/SrDOMs visiting TVC/MDU and their reports being sent to CRIS continuously for necessary changes/enhancements Tender for customization of software for IR under finalization in CRIS. Tender for hardware and roll out to 23 divisions also under finalization in CRIS (Phase I) Strategy for roll out – In three phases    Phase I – SR, SCR, SWR, CR, ECOR, SECR Phase II – WR, WCR, NCR, NR, NWR Phase III – SER, ER, ECR, NER. NFR

ISSUES-COA

Integration with dataloggers Links with RFID/GPS based tracking systems Integration with FOIS, COIS, CMS and other public interface systems like NTES, Call centers etc Record keeping of Control chart information – policy for archival

IMPACT ON TARGET COA

Board’s target for IR (76 locations) – Mar 2007 Latest review with CRIS indicates that software and hardware may become available by Dec 2006 Roll out @ 7 divisions per month Mar 2007 Jun 2007 Dec 2007 21 divisions 42 divisions 76 divisions

DECISION/ASSITANCE COA

Telecom and C&IS directorates to decide terms and conditions for acquisition of interface software from Datalogger suppliers Safety and C&IS directorates to help freeze archival policy

STATUS-ICMS

Enhanced scope  Punctuality Module  Implemented on IR. Migrated module will be given for testing by the end of July 2006  Coaching Stock Management Module    Being implemented in three phases Software ready and under field trials at Nizamuddin & Chennai Ready for roll out  Timetabling Module  Time table simulation module’s system requirements under discussion

STATUS-ICMS

Enhanced scope (contd)  Coaching Stock Maintenance Module    Scope of Mechanical module has been enhanced from capturing of coaching depot maintenance related activities to automation of C&W department It covers 154 depots & 975 coaching locations. Scope of Electrical Maintenance module defines only 8 technical modules developed by NR under MIS projects. It also does not give assessment of hardware & user specifications.

ICMS – Coaching Stock Management Module

Phase I – 114 terminals at 41 locations Target for implementation 31 st Phase II - 78 terminals at 34 locations Target for implementation 31 st Aug 2006 Phase III - 128 terminals at58 locations Target for implementation 31 st Oct 2006 Dec 2006

Training

 186 staff from 136 locations trained so far  Training labs being set up to take care of additional training needs

Equipment

  Thin clients and printers supplied to all locations Datacom equipment- 57 LAN extenders supplied. Rest under supply    UPSs to be procured by zonal railways – implementation held up for want of UPSs 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1 107 locations have been provided connectivity.

ISSUES-ICMS

Purchase of UPS – zonal railways Supply of datacom equipment by CRIS 450 pair modems PO placed. Supply in a month 144 pair LAN extenders 112 routers Supply completed TC negotiation Freezing the scope of Mechanical & Electrical Maintenance Modules – Railway Board

IMPACT ON TARGET ICMS

Three months delay due to supply of UPS and datacom equipment Mar 2007 Jun 2007 Phase I & II – 192 locations All 320 locations

DECISION/ASSITANCE ICMS

C&IS directorate to facilitate freezing of scope for Mechanical & Electrical Maintenance Modules in view of dropping of work from MIS C&IS directorate to sanction & release funds for time tabling module.

STATUS-CMS

Detailed estimate of Rs 38.16 crores sanction by Railway Board. 302 lobbies to be covered, out of which 261 are integrated lobbies.

Target for completion 7.3.2007

STATUS-CMS

Application under development and testing for

 Freight module   Coaching, shunting and pilot module Suburban module

Site Preparation

  Lump sum sanctioned @ Rs 1,31,728 for major and Rs 82,890 for minor lobbies Target for readiness Aug 2006

Terminal Equipment

  Under vetting Target of Phase I supply - Dec 2006

Datacom Equipment

 Under vetting. Will be procured through CRIS

Training

   Core group and core implementers will be trained at CRIS Core group identified on all 16 zonal railways Training labs being set up at 5 locations

ISSUES - CMS

Difference in interpretation of Board’s circulars by zonal railways in calculation of running allowance

IMPACT ON TARGET CMS

Board’s target – 302 sites by Mar 2007 Latest review with CRIS indicates software and hardware will be available only by Dec 2006. Going by the FOIS and other roll out experience, commissioning of 30 sites per month would be a reasonable target March 2007 100 sites Dec 2007 202 sites

DECISION/ASSITANCE CMS

Nomination of Committee of ED s of Electrical, Mechanical, Personnel & Finance for practice to be adapted for computation of running allowance and other issues / business reengineering

GENERAL ISSUES- V-SAT

HECL CONTRACT-235(+ OR- 25%) TOTAL NEED 477 HUB CAPACITY-500 (CAN GO UPTO 1000) TRANSPONDER HIRING ISSUE

Problems relating to the VSAT Network

•Poor Application Response Time owing to High Round Trip Time (RTT) •RTT varies between 1600 – 2400 ms for a 1000 Byte Packet Size vis à-vis the desirable value of 1200-1400 ms.

•High Delay Variation i.e. Jitter leading to inconsistency in the Application Response Time.

VSAT Issues Contd..

•Voice communication facility not yet provided at the VSAT sites.

•Video Conference requirement between CRIS & zonal Rly. Hqrs. not addressed.

•Requirement of providing connectivity to a FOIS location using a terrestrial link from the VSAT based location not met.

•Backhaul Link Failure leads to total outage of all VSAT based locations. For instance, complete failure from 14:00 hrs on 26.06.06 to 10:20 hrs of 27.06.06

VSAT Service Levels

•VSAT Network to operate using Shared Hub Services from HECL till Railway owned Hub is commissioned.

•Service Level Agreement w.r.t. Quality of Service (QoS) not available with the user •Bandwidth Allocations/ Channel Access Mechanism on the Outbound & Inbound channels not known •Status report of Captive Hub Project not available.

VSAT Migration to our own HUB

•Migration Plan for shifting the Remote VSATs to our own HUB needs to be worked out while specifying the following parameters: Service disruption due to re-alignment of Antenna/Tx-Rx Frequency at each remote site. Time required for establishing end-to-end connectivity between remote site and the FOIS datacentre Overall Stabilization of the VSAT Network

GENERAL ISSUES INFRASTRUTURE

INVESTMENT SPACE-BLDG MANPOWER DISASTER TOLERANCE

GENERAL ISSUES TRAINING

CURRICULAM IN TRAINING INSTITUTES TRAFFIC,MECHANICAL,ELECTRICAL MPP DTE’S ROLE ADDITIONALTRAINING CENTERS –5 (DLI,SC,BB,HWH,TPJ)

Growth of IT projects in IR

IR’s capital budget for IT is Rs. 273 crore in 2006-07 It is projected to increase to about Rs. 900 crore to Rs. 1200 crore by 2010 – 2011 To make this scale of operation possible, requirement of space and other facilities for CRIS and FOIS organization needs to be significantly increased

Statement of Expenditure of the Projects under CAO/FOIS

YEAR 2000 – 2001 2001 – 2002 2002 – 2003 2003 – 2004 2004 – 2005 2005 – 2006 EXPENDITURE (Rs. in Crores) 22.8

30.4

17.4

17.0

30.4

40.0

2006 07 2007 08 2008 09 Year

Anticipated increase in strength of FOIS and space requirement

Approx IT budget (Rs. Crore) FOIS manpower (total)

Manpower based in HQ

Bare seating space (sq m) Support space Training areas, central control room etc.

Total space requirement (sq m)

300 360 450 264 317 396

140 160 200

420 480 600 420 480 600 210 240 300

1050 1200 1500

2009-10 2010-11 2011-12 540 650 800 475 572 704

240 290 360

720 870 1080 720 870 1080 360 435 540

1800 2175 2700

Projected growth of manpower in CRIS

1200 1100 1000 900 800 700 600 500 400 300 200 100 0 2006 2007 2008

Year

2009 2010 2011 Trainees Procurement staff Support staff IT/HW Help Desk N/W DBA Implementers (full-time) Developers Managers

SPACE - CRIS location

SPACE – Area with Railways

Required facilities for expansion

Secure areas in red Restricted areas in orange Open access in green