IT PROJECTS-UNDER CAO/FOIS

Download Report

Transcript IT PROJECTS-UNDER CAO/FOIS

IT PROJECTS
(UNDER CAO/FOIS)
PROGRESS AND CONCERNS
AUGUST 2006
1
STRUCTURE OF PRESENTATION
1.
OVERVIEW
2.
AREAS REQUIRING BOARD’S
INTERVENTION
3.
PROJECT SPECIFIC DETAILS
2
OUR TASK - THIS YEAR
Software
User/SRS specifications, interaction with field
officers and CRIS, testing and field trial.
Deployment of hardware
and connectivity
equipments
i) TSS equipment = 4600*
Humanware
9500 men to be trained
Connectivity and power
supply
Sites = 1151*
Terminals = 3984*
Site identification and
preparation
Sites = 1151*
Roll out
Hand holding and commissIoning
ii) Routers = 500* Modems = 1700* pairs
Lan Extenders = 1013* pairs V-SATs = 950*
*Plus issues related to 569 sites, 600 routers, 1200 pairs modems, 187
Lan Extenders, 235 VSATs, 616 terminals & 1400 TSS equipments that
were commissioned till last year.
3
GROWTH OF IT PROJECTS ON IR
IR’s capital budget for IT is Rs. 273 crore in
2006-07
It is projected to increase to about Rs. 900
crore to Rs. 1200 crore by 2010 – 2011
To make this scale of operation possible,
requirement of space and other facilities for
CRIS and FOIS organization needs to be
significantly increased
4
OUTLAY FOR PROJECTS UNDER
CAO/FOIS
YEAR
Last 5 years’ average
(2001-2006)
2006 – 2007
INVESTMENT
(Rs. in Crores)
26.30
100 (approx.)
5
IMPORTANT PROJECTS
1. COA (Control Charting)
2. FOIS (Freight Operations Information System)
3. CMS (Crew Management System)
4. ICMS (Integrated Coach Management System)
6
MAJOR ISSUES NEEDING BOARD’s INTERVENTION
CONTROL
CHARTING
DATA LOGGER - INTEGRATION WITH CONTROL CHARTING
(COA)
V-SAT – PERFORMANCE & EXPANSION
DISASTER RECOVERY SITE WITH STAND BY V-SAT HUB AT SC
POWER SUPPLY – CONNECTION FROM AT SUPPLY/STATION
GENERATOR
ALL
PROJECTS
POSTING OF OFFICERS - SUITABLE BACKGROUND, THEIR
EXCLUSIVE USE FOR PROJECTS, CONSULTAION WITH CAO
INTEGRATED BUILDING COMPLEX(CAO & CRIS) – SANCTION
ON OUT OF TURN BASIS
CMS
EDs COMMITTEE - TO RESOLVE DIFFERENCE IN PRACTICE
OVER ZONES
INTEGRATION OF LOBBIES – BY ZONES BEFORE NOV. ‘06
7
STATUS – CONTROL CHARTING
(COA)
Pilot project under trial at Madurai and Trivandrum
divisions of SR
DOMs/SrDOMs visiting TVC/MDU and their reports
being sent to CRIS continuously for necessary
changes/enhancements
Tender for customization of software for IR under
finalization in CRIS.
Tender for hardware and roll out to 23 divisions also
under finalization in CRIS (Phase I)
Strategy for roll out – In three phases
Phase I – SR, SCR, SWR, CR, ECOR, SECR
 Phase II – WR, WCR, NCR, NR, NWR
 Phase III – SER, ER, ECR, NER. NFR
(all detail at http://it.indianrail.gov.in)

8
CONTROL CHARTING (COA) – TYPICAL CHART
Chart and Advance Plotting
FOIS
COIS
NTES
CMS
9
ISSUES – CONTROL CHARTING
(COA)
Integration with dataloggers (1437
already installed & number growing)
Integration with FOIS, COIS, CMS and
other public interface systems like
NTES, Call centers etc
Record keeping of Control chart
information – policy for archival
10
IMPACT ON TARGET –
CONTROL CHARTING (COA)
Board’s target for IR (76 locations/ 284
boards) – Mar 2007
Latest review with CRIS indicates that
software and hardware may become available
by Dec 2006
Roll out @ 7 locations per month
Mar 2007
Jun 2007
Dec 2007
21 locations
42 locations
76 locations
11
DECISION/ASSITANCECOA
Telecom and C&IS directorates to
resolve the issue of supply of data by
datalogger vendors to enable
development of interface of COA with
networked dataloggers
Safety and C&IS directorates to help
freeze archival policy
12
ISSUES-FOIS
V-SAT INSTALLATION AT 214 TMS
SITES
EQUIPMENTS AVAILABILITY
RAILWAY’S INVOLVEMENT
CHANGED TRAFFIC PATTERN
13
FOIS TMS Module
524* locations on IR
(all details at http://it.indianrail.gov.in)
214 locations on VSAT
324 locations online covering 376 sites
126 locations printing RR online covering 176 sites
Around 1100 PCs and 400 printers supplied so far
668 PCs and 612 printers under supply (within 45 days)
*(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)
14
VSAT – BASIC FACTS
ON 21/12/04 BOARD (ML/MT/FC) APPROVED SETTING UP
OF RAILWAY HUB & PURCHASE OF VSATs BY IRPMU
WITH FOLLOWING FEATURES:
1.
2.
3.
4.
5.
6.
7.
8.
MASTER EARTH STATION IN KU BAND WITH AUTOTRACKING
200 VSAT TERMINALS WITH DATA & VOICE CAPABILITY
SETTING UP OF NMS NETWORK
PAYMENT TO DOT FOR COMMERCIAL/CAPTIVE VSAT SERVICES
WITH CUG CAPABILITY
HIRING OF QUARTER TRANSPONDER
AMC WITH OEM FOR MAINTENANCE SUPPORT FOR HUB &
TERMINAL
CAO/FOIS TO MONITOR PROJECT & IRPMU TO NOMINATE ONE DY.
CSTE EXCLUSIVELY
HIRE VSAT WITHIN 3 MONTHS & SETTING UP OF A HUB WITHOUT
AFFECTING FOIS TERMINAL
15
TMS VSAT locations
214 TMS locations have to be
commissioned on VSATs by IRPMU
Railway Board’s target was June 2006.
IRPMU’s revised target is Sept 2006
74 VSATs covered upto 17.8.06
16
IMPACT ON TARGETFOIS
V-SAT DEPENDENT TMS SITES(214)
WILL TAKE LONGER TO STABLISE
RESPONSE TIME ISSUES (1500 vs700
msecs)
 CHANGE IN HUB FROM VENDOR’S TO OUR
OWN
(Realignment of each dish)

17
Problems relating to the VSAT
Network
Response time excessive – timed out if data
packet size exceeds 1000 bytes
Voice communication yet to be provided
Video conferencing facility between CRIS,
Railway Board and zonal railway HQs
required
18
GENERAL ISSUES- V-SAT
HECL CONTRACT - 235 (± 25%)
Requirement as of now - 477
HUB CAPACITY-500 (CAN GO UPTO 1000)
TRANSPONDER HIRING ISSUE
19
DECISION/ASSITANCEFOIS
Board’s directive for AT/generator supply from
station to TMS site
Nomination of 2 Rates Inspectors by each
zone to CAO/FOIS for verification of
referential database and testing of software
changes due to rates circulars
20
STATUS-CMS
Detailed estimate of Rs 38.16 crores sanction
by Railway Board.
302 lobbies to be covered, out of which 259
are integrated lobbies (presently around
60%).
(all details at http://it.indianrail.gov.in)
Target for completion March 2007
21
STATUS-CMS
Application under development and testing for
 Freight module
 Coaching, shunting and pilot module
 Suburban module
Site Preparation
 Lump sum amount sanctioned @ Rs 1,31,728 for major and Rs
82,890 for minor lobbies
 Target for readiness Aug 2006
Terminal Equipment
 Under vetting
 Target of Phase I supply - Dec 2006
Datacom Equipment
 Under vetting. Will be procured through CRIS
Training
 Core group and core implementers will be trained at CRIS
 Core group identified on all 16 zonal railways
 Training labs being set up at 5 locations
22
ISSUES - CMS
Difference in interpretation of Board’s
circulars by zonal railways in calculation
of running allowance
Integration of lobbies
23
IMPACT ON TARGET-CMS
Board’s target – 302 sites by Mar 2007
Latest review with CRIS indicates
software and hardware will be available
only by Dec 2006.
Going by the FOIS and other roll out
experience, commissioning of 30 sites
per month would be a reasonable target
March 2007
100 sites (DLI MUMBAI routes - 3)
Dec 2007
202 sites
24
DECISION/ASSITANCECMS
Nomination of Committee of ED s of
Electrical, Mechanical, Personnel &
Finance for practice to be adopted for
computation of running allowance and
other issues / business reengineering
Details of sample issues
25
STATUS-ICMS
Enhanced scope

Punctuality Module


Coaching Stock Management Module




Module is being tested on NDLS & MAS
Being implemented in three phases
Software ready and under field trials at Nizamuddin &
Chennai
Ready for roll out
Timetabling Module

Time table simulation module’s system requirements
under discussion
26
STATUS-ICMS
Enhanced scope (contd)

Coaching Stock Maintenance Module




Scope of Mechanical module has been enhanced from
capturing of coaching depot maintenance related
activities to automation of C&W department
It covers 154 depots & 975 coaching locations.
It covers 331 depots & 973 electrical locations.
Scope of Electrical Maintenance module defines only 8
technical modules developed by NR under MIS projects.
It also does not give assessment of hardware & user
specifications.
27
ICMS – Coaching Stock
Management Module
Phase I – 114 terminals at 41 locations
Target for implementation 31st Aug 2006
Phase II - 78 terminals at 34 locations
Target for implementation 31st Oct 2006
Phase III - 128 terminals at 58 locations
Target for implementation 31st Dec 2006
(all details at http://it.indianrail.gov.in)
Training
 186 staff from 136 locations trained so far
 Training labs being set up to take care of additional training needs
Equipment
 Thin clients and printers supplied to all locations
 Datacom equipment- 57 LAN extenders supplied. Rest under
supply
 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1
 107 locations have been provided connectivity.
 Target likely to be met
28
ISSUES-ICMS
Freezing the scope of Mechanical &
Electrical Maintenance Modules –
Railway Board
Supply of datacom equipment by CRIS
& commissioning of 59 VSAT locations
450 pair modems PO placed. Supply in a month
144 pair LAN
extenders
112 routers
Supply completed
TC negotiation
29
IMPACT ON TARGETICMS
Three months delay due to supply of
UPS and datacom equipment
Mar 2007
Jun 2007
Phase I & II – 192
locations
All 320 locations
30
DECISION/ASSITANCEICMS
C&IS directorate to facilitate freezing of
scope for Mechanical & Electrical
Maintenance Modules in view of
dropping of work from MIS
C&IS directorate to sanction & release
funds for time tabling module.
31
GENERAL ISSUES INFRASTRUTURE
INVESTMENT
SPACE-BLDG
MANPOWER
DISASTER TOLERANCE – VSAT HUB
ISSUE
32
GENERAL ISSUES TRAINING
CURRICULAM IN TRAINING
INSTITUTESTRAFFIC,MECHANICAL,ELECTRICAL
-MPP DTE’S ROLE
ADDITIONALTRAINING CENTERS –5
(DLI,SC,BB,HWH,TPJ)
33
Increase in strength of FOIS and
space requirement
Year
Approx IT
budget
(Rs. Crore)
FOIS
manpower
(total)
Manpower
based in
HQ
Bare
seating
space
(sq m)
Support
space
Training
areas,
central
control
room
etc.
200607
300
264
140
420
420
210
1050
200708
360
317
160
480
480
240
1200
200809
450
396
200
600
600
300
1500
200910
540
475
240
720
720
360
1800
201011
650
572
290
870
870
435
2175
201112
800
704
360
1080
1080
540
2700
Total space
requirement
(sq m)
34
Projected growth of manpower in CRIS
1200
Trainees
1100
Procurement staff
1000
Support staff
900
IT/HW
800
Help Desk
700
N/W
600
DBA
500
Implementers (full-time)
400
Developers
300
Managers
200
100
0
2006
2007
2008
2009
2010
2011
Year
35
SPACE - CRIS location
36
SPACE – Area with Railways
37
Required facilities for
expansion
Secure areas in red
Restricted areas in orange
Open access in green
38
THANK YOU
39