Transcript Document
MINISTRY OF POWER ACTION PLAN FOR N.E. REGION BASED ON NER VISION 2020 Presented by: JOINT SECRETARY MINISTRY OF POWER GOVT. OF INDIA Before: 60th Plenary of North Eastern Council Dated : 16th June, 2011. INSTALLED CAPACITY AS ON 31.03.2011 (All figures in MW) STATE Assam HYDRO THERMAL RENEWABLE ENERGY SOURCES TOTAL 429.72 522.01 27.11 978.84 97.57 36.93 78.86 213.36 230.58 28.01 31.03 289.62 Tripura 62.37 186.69 16.01 265.07 Manipur 80.98 71.37 5.45 157.80 Nagaland 53.32 21.19 28.67 103.18 Mizoram 34.31 68.14 36.47 138.92 1116.00 989.74 223.60 2329.34 75.27 73.10 47.11 195.48 1191.27 1062.84 270.71 2524.82 Arunachal Pradesh Meghalaya Total (NER) Sikkim TOTAL (NER+SIKKIM) 2 ACTUAL POWER SUPPLY POSITION as on 31.03.2011 (April-10 to March-11) Peak Shortage(-)/Surplus(+) State Energy Shortage(-)/Surplus(+) Peak Demand Peak Met MW % Energy Requirement Availability MW % Assam 971 937 -34 -3.50 5414 5075 -339 -6.3 Ar.Pradesh 101 85 -16 -15.8 507 432 -75 -14.4 Meghalaya 294 284 -10 -3.4 1153 1359 -194 -12.5 Tripura 220 197 -23 -10.5 883 802 -81 -9.2 Manipur 118 115 -3 -2.5 568 504 -64 -11.3 Nagaland 118 110 -8 -6.8 588 524 -64 -10.9 Mizoram 76 70 -06 -7.9 366 313 -53 -14.5 1913 1560 -353 -18.5 9879 9009 -870 -8.8 106 104 -2 -1.9 402 402 0 0 Total(NER) Sikkim 3 DISTRIBUTION IN THE NER – STATUS The AT&C losses (%) during the last three years in NER States. Sl. No. State 2006-07 2007-08 2008-09 1. Arunachal Pradesh 57.96 61.59 60.15 2. Assam 36.64 35.18 20.32 3. Manipur 79.69 79.39 81.01 4. Meghalaya 39.08 39.45 43.37 5. Mizoram 31.71 28.31 41.01 6. Nagaland 48.01 44.08 48.69 7. Sikkim 61.43 51.32 56.86 8. Tripura 29.19 30.16 31.98 135 projects under Part-A of R-APDRP at the estimated cost of Rs. 408.16 Crs. sanctioned in NER States to control AT&C losses. 4 HYDROPOWER POTENTIAL AND IT’S DEVELOPMENT IN NORTH EASTERN REGION • Total hydro-power potential in the NER including Sikkim is 63,257. • Presently, only 3% of the assessed potential has been developed in N.E. Region. 5 HYDRO POWER PROJECTS IDENTIFIED/ALLOTTED IN N.E. REGION AND SIKKIM • 143 HE projects with capacity of 57,167 MW identified by CEA/States in NER for implementation and monitoring. • Out of these, 79 projects have been allotted in Arunachal Pradesh as on date: 75 projects allotted to private sector with capacity of 29512 MW, 4 projects for a capacity of 5870 MW are allotted to CPSUs. Sector-wise, State-wise HE Schemes allotment 6 STATUS OF DEVELOPMENT OF H.E. POTENTIAL IN NER AND SIKKIM Identified Capacity as per reassessment study above 25 MW Capacity Developed Capacity under development Capacity Developed + Under Development (MW) (MW) (MW (MW) Capacity yet to be developed. % NORTH EASTERN REGION (other than Sikkim) MEGHALAYA 2298 156 166 322 1976 85.99 TRIPURA 0 0 0 0 0 0.00 MANIPUR 1761 105 0 105 1656 94.04 ASSAM 650 375 0 375 275 42.31 NAGALAND 1452 75 0 75 1377 94.83 AR. PRADESH 50064 405 4460 4865 45199 90.28 MIZORAM 2131 0 60 60 2071 97.18 SIKKIM 4248 570 2162 2732 1516 35.69 62,604 1686 6848 8534 54,070 86.36 TOTAL (NER) 7 UNDER CONSTRUCTION HYDRO ELECTRIC PROJECTS IN NER INCLUDING SIKKIM Sl. No. Name of Project I.C. (MW) State/ Implementing Agency Likely Commissioning 1. Subansiri Lower 2000 Arunachal Pradesh/ Assam/NHPC 2013-15 2. Kameng 600 Arunachal Pradesh/ NEEPCO 2016-17 3. Pare 110 Arunachal Pradesh/ NEEPCO 2013-14 4. Demwe Lower Ar. Pr./M/s. Athena Demwe Power Ltd. 2016-17 5. Tuirial 60 Mizoram / NEEPCO 2014-15 6. Myntdu 126 Meghalaya/ MeSEB 2011-12 7. New Umtru 40 Meghalaya/ MeSEB 2012-13 Sikkim/ M/s. Gati Infrastructure Ltd. 2011-12 Sub-total (NER) 1750 4692 8. Chujachen 99 9. Teesta- III 1200 Sikkim/ M/s. Teesta Urja Ltd. 2012-13 10. Teesta- VI 500 Sikkim/ M/s. Lanco Energy Pvt. Ltd. 2012-13 11. Rangit-IV 120 Sikkim/ M/s. Jal Power corp. Ltd. 2013-14 12. Jorethang Loop 96 Sikkim/ M/s DANS Energy Ltd. 2012-13 13. Bhasmey 51 Sikkim/ M/s Gati Infrastructure Ltd. 2012-13 Sub-total (Sikkim) Total (NER + Sikkim) 2066 6758 Under Construction Thermal Projects 8 MAJOR ISSUES IN THE DEVELOPMENT OF H.E. POTENTIAL • Delay in Environment & Forest clearances. • Problem in Land Acquisition. • Downstream impact Assessment. • Development of Infrastructure (Roads & Bridges). • Power Evacuation & Sequencing of Projects. • Long Term Financing. Measures for expeditious Hydro Power Development 9 MAJOR INITIATIVES IN TRANSMISSION AND SUB TRANSMISSION SYSTEM IN THE NER 1. Comprehensive scheme for strengthening of transmission and distribution system in NER and Sikkim: Power Grid has prepared DPR. The estimated cost of the schemes is about ` 11348.5 Crs. The schemes are to be funded by GOI/World Bank. The schemes are to be implemented in 2 phases by 2015-16. 2. Transmission system for evacuation of power from Pallatana GBPP: The power from the Pallatana GBPP (726.6 MW) being implemented by OTPC would be evacuated over Pallatana-Silchar-Bongaigaon 400kV D/C line being implemented by NETC. 3. North East-Northern/Western Interconnector-I : Biswanath Chariyalli-Agara + 800kV, 6000 MW HDVC bipolar line to evacuate power from Lower Subansiri HEP (2000 MW) and Kameng HEP (600 MW) being implemented by Power Grid. Will be utilized for evacuation from Hydro Projects in Bhutan namely Punatsanchu-I (1200 MW), Punatsanchu-II (990 MW) and Mangdechu (720 MW). Existing and Under Construction Transmission System 10 DEVELOPMENT OF TR. SYSTEM THROUGH CHICKEN NECK • • • • • About 45000 MW of power to be evacuated from NER through chicken neck area in north of West Bengal A very narrow patch of land (22 km. width X 18 km length) near Siliguri having borders of Nepal on one side & Bangladesh on the other side and is largely habited. All transmission lines, railway lines, gas pipe-lines, telecommunication lines etc. have to pass through the chicken neck area. About 8 nos. of HVDC/EHVAC corridors may be required with a total width of about 1.5-2 Kms. For this, 4 corridors of + 800kV HVDC of 6000MW each (Total : 24,000 MW) is under implementation. 11 COMPREHENSIVE STRENGTHENING IN NER The scheme mainly covers : Intra-state transmission & subtransmission system (132kV & above) to strengthen the grid to deliver power to states with security and reliability. 5700 km line 87 nos. substations (7600MVA) Distribution System (upto 33kV) 8450 km line 332 nos. substations (2255MVA) to disperse power to the ultimate consumer The total scheme has been programmed in two phases; Phase-I and II, to be completed progressively by 2015-16. Estimated Total Cost : Rs. 11,411.00 Crs. Details of State-wise Estimated Cost and scope of work 12 FUTURE TRANSMISSION SYSTEM CHALLENGES • Huge potential for future hydro generation projects • Need to transfer power over to load centre over long distance • Difficult Terrain – Hilly, Forest, River Crossing • Development of high capacity transmission corridor through Chicken Neck Area • High cost of transmission system due to High Capacity Transmission line through difficult corridor Phased development of the generation projects Low PLF of hydro projects 13 FUNDING OF COMPREHENSIVE STRENGTHENING SCHEMES MoP has recommended the scheme to DEA in June, 2009. During Nov.,2010, DEA has posed the scheme to World Bank in three transces of USD 500 million each. The World Bank is deliberating upon the scheme. World Bank preliminary mission is visiting the states of NER. 14 RAJIV GANDHI GRAMIN VIDYUTIKARAN YOJANA (RGGVY) IN N.E. STATES • RGGVY projects for all districts have been sanctioned • Project coverage/targets and achievements are: Target of Village Electrification (nos.) Villages Electrified (nos.) % achievement Target of BPL Connections (no. in Lakh) 13906 7826 56.3% 15.60 State-wise details Connections Released (no. in Lakh) % achievement 7.74 49.6% 15 MINISTRY OF POWER 16 SUMMARY OF HE SCHEMES ALLOTTED IN NER & SIKKIM (YET TO BE TAKEN UP FOR IMPLEMENTATION) Central Name of State Private Total No. I.C. (MW) No. I.C. (MW) No. Ar. Pradesh 3 4400 86 31375.5 89 Assam - - - - - - Manipur 2 1566 - - 2 1566 Meghalaya 1 85 5 1124 6 1209 Mizoram 5 2196 - - 5 2196 Nagaland - - 1 165 1 165 Total (NER) 11 8247 92 32664.5 103 40911.5 Sikkim 2 730 20 2532 22 3262 Total (NER+Sikkim) 13 8977 112 35196.5 125 44173.5 BACK I.C. (MW) 35775.5 17 UNDER CONSTRUCTION THERMAL PROJECTS IN THE NER Name of Project Agency State Capacity (MW) Bongaigaon TPP (3x250 MW) NTPC Assam 750 Commissioning Schedule – 8/2012, 7/2013, 10/2013 Monarchak Gas Based Power Project NEEPCO Tripura 100 Commissioning Schedule - 01/214 OTPC CCPP (Palatana) (2x363.3 MW) JV of ONGC & Govt. of Tripura Tripura 726.6 Namrup CCGT APGCL Assam 100 Commissioning Schedule – Early 12th Plan Lakwa WHRU Project/Steam Turbine APGCL Assam 37.2 Commissioning Schedule – 3rd Quarter of 2011-12. BACK Remarks Commissioning Schedule – 03/2012 18 ACTION PLAN FOR EXPEDITIOUS HYDRO DEVELOPMENT Sheet 1 of 3 • To obviate the problems of levels being encountered during DPR formulation; a ‘Basin Approach’ could be adopted for planning the projects in the entire basin. Such an approach would help in optimizing the features and the benefits from individual schemes. State Government to facilitate availability of hydrological data/details and topo-sheets/bench-marks for development. Creation of a Data Bank in certain central agency like CWC could also be considered so that developers have access to the already available hydrological data. BACK Contd….. 19 ACTION PLAN FOR EXPEDITIOUS HYDRO DEVELOPMENT Sheet 2 of 3 Development of infrastructure facilities like roads in the basin jointly by the State/NEC/DoNER and Developers. Facilitate environmental clearance at the State level. Law & Order Problems to be suitably addressed by the State. State Government to facilitate in Land acquisition. Adoption of it is around the project area by the developers well in advance for developing skilled manpower required. Strict monitoring of the progress and quality of investigations by the State for time bound formulation of DPRs and implementation of schemes. BACK Contd….. 20 ACTION PLAN FOR EXPEDITIOUS HYDRO DEVELOPMENT Sheet 3 of 3 Firming up the beneficiaries/buyers well in time in order to obtain LTOA for evacuation of power and so that completion of transmission system matches with the commissioning schedule. Storage projects could be given more thrust by the States due to the ever growing threat of changes in flow pattern due to Climate Change especially in Himalayan Region. BACK 21 Sheet 1 of 3 POWER MAP OF NORTH EASTERN REGION ARUNACHAL PRADESH Existing and under Construction ROING ALONG PASIGHAT DAPORIJO ZIRO TEZU NAMSAI SUBANSIRI(LOWER) TINSUKIA DIBRUGARH RANGANADI MIAO JONAI KAMENG SEPPA LHAO SILAPATHAR KATHALGURI KHUPI ITANAGAR TENGA BHUTAN CHUKHA DHEMAJI BISHWANATH CHARIALI GOHPUR BALIPARA AGRA(NR) TEJPUR ROWTA TO SILIGURI BIRPARA DHALIGAON RANGIA BORNAGAR 0K MARIANI(NEW) V MOKOKCHUNG(PG) MOKOKCHUNG DOYANG NAGALAND ASSAM DIMAPUR DIMAPUR KIPHIRE DIPHU LANKA UMTRU KOHIMA KYRDEMKULAI MEGHALAYA TURA 22 MARIANI MISA CHANDRAPUR UMIAM-4 AT BOKAJAN JAGIROAD GUWAHATI D LAKWA GOLAGHAT AMINGAON BTPS AGIA GE AR CH BOKAGHAT SAMAGURI AZARA TO NEW SILIGURI H AT AN LI HW IYA) BISHAR CL C EG (A BONGAIGAON NANGAL BIBRA SHILLONG BYRNIHAT UMIAM KHLIEHRIAT KOPILI KHANDONG KHLIEHRIAT(PG) CHERRAPUNJI LOWER SUBANSIRI-KAMNEG SYSTEM CHARGED AT 132K 3 D DHARMNAGAR H'KANDI KOLASIB CHURACHANDPUR 2KV D AT 13 2K SJ'NAGAR V PALLATANA AGARTALA AGARTALA GPP ROKHIA LEGEND MELRIAT(NEW) KV D GE AR CH TRIPURA PALLATANA BONGAIGAON SYSTEM THOUBAL KAKCHING JIRIBAM AT 13 KHOWAI AMBASSA AR GE NING V IMPHAL(NEW) LOKTAK GED CHAR GE AR CH 1 AT KAILASHAHAR KUMARGHAT PK BARI KAMALPUR CH MANIPUR SRIKONA BADARPUR SILCHAR B'PUR(PG) DULLABCHERA2KV AT 2 13 AIZWAL AIZWAL (ZEMABAWK) W.PHAILENG MELRIAT THERMAL/GAS GENERATION MIZORAM HYDRO GENERATION SAITUAL KHAWZAWL SERCHIP MARPARA UNDER CONSTRUCTION/ APPROVED EXISTING LUNGDARE BACK DEOMALI NAMRUP NORTH LAKHIMPUR NECHIPHU 400 KV LUNGLEI 220 KV 132 KV 440 KV 220 KV 132 KV POWERGRID LUNGSEN LUWNGTLAI SEB 22 Sheet 2 of 3 POWER MAP OF NORTH EASTERN REGION Lower Subansiri ARUNACHAL PRADESH Kameng Bishwanath Chariali Balipara ROING ALONG PASIGHAT DAPORIJO ZIRO NAMSAI SUBANSIRI(LOWER) TINSUKIA DIBRUGARH RANGANADI Bongaigaon TEZU MIAO JONAI KAMENG SEPPA LHAO SILAPATHAR KATHALGURI KHUPI ITANAGAR TENGA BHUTAN CHUKHA DHEMAJI BISHWANATH CHARIALI GOHPUR BALIPARA BONGAIGAON AGRA(NR) TEJPUR ROWTA TO SILIGURI BIRPARA DHALIGAON RANGIA BORNAGAR Misa DIMAPUR KIPHIRE DIPHU LANKA KOHIMA KYRDEMKULAI MEGHALAYA NANGAL BIBRA SHILLONG BYRNIHAT UMIAM KHLIEHRIAT KOPILI KHANDONG KHLIEHRIAT(PG) CHERRAPUNJI Silchar LOWER SUBANSIRI-KAMNEG SYSTEM BADARPUR SILCHAR B'PUR(PG) DULLABCHERA2KV CHARGED AT 132K D DHARMNAGAR H'KANDI KOLASIB CHURACHANDPUR Imphal 2KV D AT 13 2K SJ'NAGAR V PALLATANA AGARTALA AGARTALA GPP ROKHIA LEGEND MELRIAT(NEW) KV D GE AR CH TRIPURA PALLATANA BONGAIGAON SYSTEM THOUBAL KAKCHING JIRIBAM AT 13 KHOWAI AMBASSA AR GE NING V IMPHAL(NEW) LOKTAK GED CHAR GE AR CH 1 AT KAILASHAHAR KUMARGHAT PK BARI KAMALPUR CH MANIPUR SRIKONA 3 P.K. Bari AT 2 13 AIZWAL AIZWAL (ZEMABAWK) W.PHAILENG MELRIAT HYDRO GENERATION SAITUAL KHAWZAWL LUNGDARE MARPARA Surajmaninagar THERMAL/GAS GENERATION MIZORAM SERCHIP BACK MOKOKCHUNG(PG) DOYANG DIMAPUR UMTRU Pallatana Kathalguri MOKOKCHUNG NAGALAND ASSAM TURA MARIANI(NEW) V MARIANI MISA CHANDRAPUR UMIAM-4 0K BOKAJAN JAGIROAD GUWAHATI D 22 LAKWA GOLAGHAT AMINGAON BTPS AGIA GE AR CH BOKAGHAT SAMAGURI AZARA TO NEW SILIGURI H AT AN LI HW IYA) BISHAR CL C EG (A Agra Siliguri AT DEOMALI NAMRUP NORTH LAKHIMPUR NECHIPHU Melriat 400 KV LUNGLEI POWERGRID LUNGSEN LUWNGTLAI SEB UNDER CONSTRUCTION/ APPROVED EXISTING 220 KV 132 KV 440 KV 220 KV 132 KV MAJOR TRANSMISSION SYSTEM Sheet 3 of 3 Existing Tr. System for Major project like Kathalguri (Gas : 291 MW), Ranganadi(Hydro : 405MW) (Black Color) Kathalguri – Misa 400kV D/c line (operated at 220kV) Misa– Balipara – Bongaigaon – Siliguri 400kV D/c line Ranganadi – Balipara 400kV D/c line On-going Tr. System for Lower Subansiri(2000MW) / Kameng(600MW) Hydro Projects (Red Color) Kameng-Balipara-Bongaigaon 400kV D/c Lower Subansiri – Biswanath Chariyali 400 kV 2 x D/C Line Biswanath Chariyali – Agra ± 800 kV, 6000 MW HVDC Bi pole line On-going Tr. System for Pallatana(726 MW)/Bongaigaon(750 MW) Thermal Projects (Blue Color) Pallatana-Silchar-Bongaigaon(PG) 400kV D/c line (twin moose) Pallatana - Surajmaninagar (Tripura) 400kV D/c line (op. at 132kV) Silchar – PK Bari (Tripura) 400kV D/c line (op. at 132kV) Silchar (Assam)– Melriat (Mizoram) 400kV D/c line (op. at 132kV) Silchar(Assam) - Imphal(Manipur) 400kV D/c line (op. at 132kV) BACK 24 COMPREHENSIVE SCHEME – ESTIMATED COST Sheet 1 of 2 State Transmission & Subtransmission (132kV and above) Phase-I Phase-II Distribution (33 kV) SubTotal Consultancy Total Total incl IDC 1 Inter - State 44.5 250.2 0.00 294.7 39.0 333.7 336.2 2 Ar. Pradesh 959.2 466.8 217.1 1643.1 217.5 1860.6 1860.6 3 Assam 711.7 940.6 741.7 2394.0 316.9 2710.9 2731.2 4 Manipur 196.9 185.5 260.2 642.6 85.1 727.7 733.1 5 Meghalaya 920.5 0.00 283.9 1204.4 159.4 1363.8 1374.0 6 Mizoram 263.4 222.2 145.0 630.6 83.5 714.0 719.4 7 Nagaland 915.8 0.00 152.1 1067.9 141.3 1209.2 1218.3 8 Tripura 612.7 229.2 284.6 1126.5 149.1 1275.6 1285.1 9 Sikkim 730.7 0.00 1018.3 134.8 1153.1 1153.1 TOTAL 5355.4 2294.4 10022.0 1326.5 11348.5 11411.0 287.6 2372.2 BACK 25 COMPREHENSIVE SCHEME – SCOPE OF WORK Sheet 2 of 2 Distribution (upto 33kV) Transmission/ Subtransmission (132kV & above) Line (Km) New S/s (No) Total MVA (New & Aug.) Line (km) New S/s (No) Total MVA (New & Aug.) Interstate 270 4 715 - - - Manipur 495 4 185 2291 54 244 Ar. Pradesh 1354 19 705 1380 36 169 Meghalaya 589 6 1072.5 869 54 535 Mizoram 569 6 225 1210 63 399 Assam 809 27 2836 1066 31 98 Nagaland 810 6 585 496 32 222 Tripura 645 9 730 855 46 381 Sikkim 164 6 360 291 16 207 Total 5705 87 7413.5 8458 332 2255 BACK 26 RAJIV GANDHI GRAMIN VIDYUTIKARAN YOJANA (RGGVY) IN N.E. STATES Project Coverage Sl. State Connections Electrification of to BPL H/Hs Village (no.) (nos.) Project Cost (Rs. Crore) Achievements (31-05- 2011) Village Electrification (no.) % of Target BPL connection( no.) % of Target 36.1% 1 Arunachal Pr. 2129 40810 537.68 717 33.7% 14744 2 Assam 8525 991656 1660.00 6430 75.4% 615268 62.0% 3 Manipur 882 107369 357.79 293 33.2% 10822 10.1% 4 Meghalaya 1943 116447 290.41 151 7.8% 34669 29.8% 5 Mizoram 137 27417 104.25 57 41.6% 9849 35.9% 6 Nagaland 105 69900 111.17 60 57.1% 19000 27.2% 7 Sikkim 25 11458 57.11 20 80.0% 7187 62.7% 8 Tripura 160 194730 131.47 98 61.3% 62256 32.0% 13906 1559787 3249.88 7826 56.3% 773795 49.6% Total BACK 27