H5 Wet Weather Pump Station - North Hudson Sewerage Authority
Download
Report
Transcript H5 Wet Weather Pump Station - North Hudson Sewerage Authority
Presentation to Maxwell Place Homeowners
Association
1
Agenda
Project Needs/Benefits
Site Plan
Construction Process
Access at the Site
Noise Reduction
Effect on Businesses
Communications with Residents
Restoration of the Site
On-going Maintenance
Schedule
Questions
2
Project Needs/Benefits
Reduce and Protect Against
Flooding
Pump Station Minimizes /Eliminates
Street Flooding in Northern Hoboken
Integral Part of Overall Plan (“Rebuild by
Design”) to Guard Against Rising Sea
Levels/Superstorm Sandy Event
3
Project Needs/Benefits
Provides Maxwell Place Infrastructure
with Greater Resiliency
Pump Station Reduces Potential for Backups
in Long-Term for Maxwell Place Private
System
New Emergency Generator for Backup Power
at 11th Street Pump Station
Protects the PSE&G Substation that provides
power to Maxwell Place
4
Project Site Plan
5
Construction Process: Noise Reduction
Noise Reduction
Hours of Construction Limited to Reduce Community
Disruption:
Monday through Friday Only
Between Hours of 8 am to 5 pm
No Weekend or Off-Hour Construction Activity
No Pile Driving East of Hudson Street
Substantially Less Noise without Need for Piles
Limited Truck Traffic
Concentrated During Excavation and Concrete Placement
No Need for Constant Trucks In and Out of Site
6
Construction Process: Access
Access at the Site
Sidewalks
South Sidewalk: Open at All Times
South Sidewalk: Maintain Drop-Offs for School
North Sidewalk: Brief Intervals of Closure Between Sinatra
Drive North and Hudson Street
Traffic
Uninterrupted Access to Parking Garage
East-Bound Traffic Lanes (Between Sinatra Drive North and
Hudson Street): Open at All Times
West-Bound Traffic Lanes: Temporary Closures
Parking
No Street Parking During Construction Hours
Parking During Non-Construction Hours & on Weekends
7
Construction Process: Businesses
Effect on Local Businesses
Sidewalk Access Permits Unimpeded Foot Traffic to Local
Businesses
Traffic Controls at Site Should Not Impact Businesses
Drop-off Point Will Be Maintained During Construction
Parking Access May Have Limited Effect
Parking Garage Access Remains In Place
Restrictions on Street Parking May Have Limited Impact
8
Construction Process: Communications
Keeping Residents Informed
Monthly Progress Report Posted on North Hudson
Sewerage Authority Website
http://www.nhudsonsa.com/
Onsite Construction Field Office
Executive Director and Authority Engineer Available for
Update Meetings
24/7 Community Outreach Hotline
9
Restoration of Site
Street
Complete repaving of 11th Street
Both Sides Between Sinatra Drive North &
Hudson Street
Restoration of Island Landscaping
Blend Covers into Landscape Plan
10
H5 Wet Weather Pump Station
Control Vault View
H5 Wet Weather Pump Station View
th
11 Street from Sinatra Drive North
On-Going Maintenance
Pump Station
2 Hours Monthly Maintenance Visits
Safety Checks
Equipment Inspection & Preventative
Maintenance
Control Vault
2 Hours Weekly Maintenance Visits
Controls Check
Preventative Maintenance
13
Schedule
November/December 2014 – Public Advertisement
January/February 2015 – Contract Award
April 2015 – Commence Construction
February 2016 – Construction Completed
March 2016- Ribbon Cutting
14
Questions?
North Hudson Sewerage Authority
1600 Adams Street
Hoboken, NJ 07030
Phone: (201)-963-4685
http://www.nhudsonsa.com/
15