NYSERDA and Data Center Efficiency

Download Report

Transcript NYSERDA and Data Center Efficiency

1

NYSERDA Data Center Efficiency Program

Columbia University Green Data Center Winter Workshop January 7

th

, 2011

2

NYSERDA

Mission:

To advance innovative energy solutions in ways that improve New York’s economy and environment

Vision:

To serve as a catalyst – advancing energy innovation and technology, transforming New York’s economy, empowering people to choose clean and efficient energy as part of their everyday lives.

3

Importance of Data Centers in NYS

• • New York has the 2 nd the US largest concentration of data centers in Energy efficient growth of data center load is key to maintaining sustainability of the NYS economy and IT delivery infrastructure

Studies found:

– NYS data centers consume ~4.5 billion kWh/yr at a cost of ~$600 million – Energy consumption by data centers is forecasted to double in 3-5 years

4

Challenges Facing Data Centers Today

• • • • Growing IT Demand Constrained space and power availability Increasing energy and operating costs Common themes – Over-provisioned IT infrastructure – Ineffective/inefficient cooling – IT and Facilities coordination – Reliability is the priority

5

NYSERDA’s Data Center and IT Efficiency Program

Goal:

To maximize energy efficiency and computing performance in data centers by addressing all steps in the technology innovation chain, through:

Market Development

• • • • Research & Development Market Transformation Education and Training

Demonstration Projects Product/Process Development

Deployment Initiatives

Technology R&D Market Adoption Codes & Standards Commercial Applications

6

Research & Development

• • Research program developed in 2008 to support development and/or demonstration of energy efficient data center and computing technologies Innovation supported through R&D’s NextGen Technologies

Demonstration Projects

(PON 1105, 1772) and Data Center and Server

Product/Process Development

Efficiency (PON 1206) programs

Technology R&D Market Development Market Adoption Codes & Standards Commercial Applications

7

NextGen - Current R&D Opportunity

• • • • The NextGen Program (PON 1772) supports the development and/or demonstration of efficient energy end-uses in buildings; including data center hardware and space conditioning technologies Program provides support for feasibility studies, product development, demonstration, and commercialization of innovative technologies Max award is $300k per project. Round 3 (final) is due January 27 th

8

Research & Development

• • • • • • • • • • • NYSERDA R&D have supported 15 projects with over $3M in funding. Topics have included: Desktop, Server, and Storage Virtualization Energy Monitoring and Management Advanced Energy Efficient Servers Efficient File/Operating Systems Airflow Management

Demonstration Projects

Free Cooling Advanced UPS DC Power Distribution Cryo-Computing

Product/Process Development

Solid-State Drives

Technology R&D Market Development Market Adoption Codes & Standards Commercial Applications

9

Market Transformation

• • • • • NYSERDA supports market analysis, training and information dissemination for the purpose of increasing awareness and to help motivate wider adoption of efficient technologies and practices NYSERDA/ASHRAE Data Center Best Practices Workshops (2009, 2010) NYSERDA University Data Center Conference (2010) Market Research – “Barriers to

Demonstration Projects Product/Process Development

Adoption”

Market Development Market Adoption Codes & Standards

Data Center energy efficiency framework (DCEEF) – On-going

Technology R&D Commercial Applications

10

Deployment - Industrial and Process Efficiency

• • • NYSERDA’s IPE Program is investing ~$115 Million over three years to widen the deployment of commercially available energy efficient practices at manufacturing sites and data centers Reduction Goal: • 840,000 MWh • 1,000,000 MMBtu Directly rewards data centers for sustainable, efficient load growth

Demonstration Projects Product/Process Development Technology R&D Market Development Market Adoption Codes & Standards Commercial Applications

11 • • • •

FlexTech Program

FlexTech is a technical assistance program that provides cost-shared engineering studies and energy audits for the purpose of identifying problem areas and energy efficiency opportunities Includes but not limited to: • • • • • Feasibility Studies CFD Modeling Facility Systems IT Systems Benchmarking/Commissioning Provides 50% Cost Share Up to $1 million

12 • • • • • •

Industrial and Process Efficiency Incentives

Incentive is paid based on verified energy savings ($0.12/kWh upstate, up to $0.16/kWh in Con Edison) Incentives for energy saving improvements – IT: Next Generation Servers, Virtualization, Storage Consolidation, Server Load Prioritization and Optimization – Facilities: Air Flow Management, Cooling, Use of Waste Heat, UPS System Upgrades New construction or existing assets Detailed engineering analysis to determine savings Large projects require M&V 50% of project costs up to $5 million per project

13 • • • •

Joint Data Center Program

Westchester Launch Date: January 27, 2011

Technical Assistance Studies for data centers interested in identifying their energy efficiency options.

Energy Efficiency Incentives for retrofit and new construction projects to off-set the cost of energy efficiency improvements.

Customer Installation Support to provide participating data centers with a complete package that addresses all energy related issues critical to their facilities’ operation. Outreach, Education, and Marketing to recruit data centers into the initiative.

Contact Info: 212.701.7222 or [email protected]

14

Efficient Data Center Program Future Focus

• • • R&D – Continued emphasis on the development of innovative energy efficient – technologies Larger scale demonstrations of advanced concepts Market Transformation – Additional training and industry events to inform data center owners and operators of best practices Deployment – Energy productivity master planning – Development of customer/site specific energy per workload productivity metrics – – Bringing critical teams together; CxO, IT, Facilities, Business Development Long-term strategies for improving and measuring productivity

15

NYSERDA Data Center Efficiency Program

Questions?

16

NYSERDA Data Center Efficiency Program

Contact Information R&D Bryan Berry [email protected]

518-862-1090 x3537 Joseph Borowiec [email protected]

518-862-1090 x3318 Deployment Chris Stump [email protected]

518-862-1090 x3537 Sandy Hwang (NYC Office) [email protected]

518-862-1090 x3009 Diane Foy – Willdan Energy Solutions [email protected]