NYSERDA - Metering.com

Download Report

Transcript NYSERDA - Metering.com

NYSERDA’s Peak Load Reduction Program PON 835

Embassy Suites Hotel New York, NY October 7, 2004

Program Objective

• • • • • Increase grid reliability by reducing/curtailing demand (NYISO DR programs) Base load reductions and enable demand response Demand reductions for the period of May through October – 11:00 AM-7:00 PM Open to end users and third party aggregators, etc. (LSE, CSP, utilities, etc.) PON 835 application deadline 11/1/04, I&O by 3/31/05

NYISO

"Hub of the Northeast" Hydro Quebec 19,410 MW* IMO 23,857 MW* PJM / PJM West 64,300 MW* New York ISO 30,983 MW*

* = Peak Load in Megawatts

ISO New England 25,158 MW*

NYSERDA/NYISO Relationship

• NYISO administers three demand response programs that pay for demand response • NYSERDA supports participation in these programs by reimbursing a portion of costs associated with technology installation that enables demand response/reduction

NYISO

s Demand Response Programs

• EDRP • Low Risk • Low/Moderate Return • DADRP • Moderate Risk • Moderate/High Return Return

EDRP SCR DADRP

• ICAP/SCR • Moderate/High Risk • Moderate/High Return Risk

NYSERDA/NYISO Relationship

ICAP/SCR EDRP DADRP NYISO Customer Permanent Demand Reduction NYSERDA Load Shifting/ Curtailment Dispatchable Emergency Generator Interval Meter

NYSERDA’s Peak Load Reduction Program

PDRE LC/S DEGI IM Con Edison Service Territory Non Con Edison Service Territory $475/kW $225/kW Con Edison Service Territory $175/kW Non Con Edison Service Territory $45/kW Con Edison Service Territory only $125/kW Statewide PSC Approved $2,500 per meter Statewide NYISO Compliant $1,200 per meter

NOTE: Contractors will be reimbursed the lesser of 70% of the Eligible Project Costs or the incentive caps set forth in Table 1. The Facility owner/operator must contribute no less than 30% of Eligible Project Costs.

Permanent Demand Reduction Efforts

• • • • Implement projects that result in long term demand reduction 20 kW minimum demand reduction (can be aggregated) Common measures include lighting, motors, cooling system upgrades, etc 70% of eligible costs up to $475/kW by 3/31/05

• • • • •

Permanent Demand Reduction

41 story commercial property in Manhattan The Durst Organization 28-tank ice storage system Ice Slurry is created at night, and circulated through cooling coils during daytime Shifted 4,000 ton-hours of cooling off-peak $300,000 in incentives

• • • • • Upgraded Lighting from T12 to T8 technology 39 Locations retrofitted Demand Reduction – 379 kW Energy Savings – 1.9 Million kWh NYSERDA incentive - $142,000

Load Curtailment/Shifting

• • • • • • Identify and control discretionary loads Supports Utility/NYISO Demand Response Programs Common measures include duty cycling, process shifting, lighting reductions, etc 100 kW minimum (may be aggregated) 70% of eligible costs up to $175/kW by 3/31/05 Direct load control encouraged (100% reimbursement up to $175/kW in Con Edison)

Load Curtailment/Shifting

• Direct Load Control – Load centrally controlled from a single source through bldg EMS, which activates pre-programmed curtailment settings – – – 21 BJ’s Wholesale Club locations (1 MW) 16 Stop & Shop Supermarkets (0.8 MW) 36 Home Depot locations (4.4 MW)

600 500 400 300 200 100 0

Home Depot Demand Curtailment (2002)

30-Jul

Time of Day

29-Jul curtailed load

• • • • •

Dispatchable Emergency Generator Initiatives

Energy & environmental controls & enhancements to improve operations and reliability Supports NYISO EDRP & SCR, or TO DRP Eligibility limited to facilities in Con-Edison service territory and machines with NOx emissions less than 35 lbs/MWh (18 lbs/MWh for new installations) Common measures include switchgear, controls, test & tunes, dual fuel conversions, etc 70% of eligible costs up to $125/kW by 3/31/05

AT&T Generator

• • • • AT&T could not run generators due to high emissions (opacity of 80%) Faulty fuel injectors, allowing unburned fuel in the exhaust New fuel injectors and turbo chargers were installed, allowing 7 MW of generation to run significantly cleaner (less than 20% opacity) NYSERDA provided over $400,000

Interval Meters

• • • • Interval metering intended for primary electric service Required registration in NYISO and/or Utility Demand Response Programs $2,500 for “socket meters”, or $1,200 for “shadow meters” 70% of eligible costs up to $2,500 or $1,200 by 3/31/05

3-D Metered Data

NYSERDA’s Interval Meter (8/15/03)

PON 835 Participation

• • • • • • • • Apply NYSERDA sends PO Submit a Technical Assessment (TA) NYSERDA reviews TA and issues notice to proceed Complete the job and notify NYSERDA NYSERDA does site visit to verify installation Invoice NYSERDA NYSERDA provides payment

Program Funding/Timeframe

• • • • $10.5 million available, program year nearly over Applications accepted through November 1, 2004, or until funds committed Applications accepted on a first come, first serve basis Projects must be completed and field verified by March 31, 2005

• • • •

PLRP for Summer 2005 PON 903

Similar to PON 835 – 4 components Retro-active back to projects contracted for after 11/01/04 Funding amount could be less – end of program Planned release December 2004

Questions?

• • • Albany 1-866-NYSERDA (697-3732) – – – Pete Savio ext 3334 Chris Smith ext 3360 Lee Smith ext 3313 New York City 212-971-5342 – Elizabeth Perry ext 3017 http://www.nyserda.org/835pon.pdf