4.0 AMDS Installation

Download Report

Transcript 4.0 AMDS Installation

MDS Installation
Page 1
Contents
 Introduction
 Outdoor Unit Installation
 Indoor Unit Installation
 Refrigerant Pipe Work
 Gas Charge
 Wiring
 Summary
Page 2
Introduction
Page 3
INSTALLATION
Bad installation – System will not
operate as per design
 Waste of Money
 Waste of Time
 Bad Image
3 Major Categories
 Unit Installation
 Piping Installation
 Wiring Installation
Page 4
Outdoor Unit Installation
Page 5
Outdoor Unit Installation
Outdoor Unit Installation
 Sufficient area around the unit. No barrier for supply
air and discharge air.
 Avoid discharge air return to the unit (Hot Air shortcircuiting)
 Strong foundation for the unit
Page 6
Outdoor Unit Installation
Handling Outdoor Unit
Correct
Page 7
Outdoor Unit Installation
Handling Outdoor Unit
Wrong
Page 8
Outdoor Unit Installation
Correct
Page 9
Wrong
Outdoor Unit Installation
Page 10
Outdoor Unit Installation
Outdoor Unit Spacing (Single Unit)
Wall / Barrier
lower than unit
Wall / Barrier
higher than unit
Side View
Page 11
Outdoor Unit Installation
Outdoor Unit Spacing (Single Unit)
Top View (Barrier higher than unit)
Page 12
Outdoor Unit Installation
Outdoor Unit Spacing (Single Unit)
Top View (Barrier lower than unit)
Page 13
Outdoor Unit Installation
Outdoor Unit Spacing (More than 1 unit)
Top View
(Wall / Barrier restriction same as 1 outdoor unit)
Page 14
Outdoor Unit Installation
Outdoor Unit Spacing (More than 1 unit)
Top View
(Wall / Barrier restriction same as 1 outdoor unit)
Page 15
Outdoor Unit Installation
Outdoor Unit Spacing (More than 1 unit)
Top View
(Wall / Barrier restriction same as 1 outdoor unit)
Page 16
Outdoor Unit Installation
Outdoor Unit Foundation
 Floor location strength
- Able to withstand the unit weight and vibration
Page 17
Outdoor Unit Installation
Outdoor Unit Foundation
 Layout for drainage, piping & cables
- Different level, avoid blocking
(Remove the panel before
piping connection)
Piping connection position
Main and slave units must be
installed in the same level
A
To units
To units
Bala
nce
pipe
id p
ipe
B
A >10mm
B >200mm
C >500mm
D>100mm
Liqu
Gas
Access valve for
balance piping (φ9.52)
Base panel hole
pipe
Tri-jiont
Elbow
For φ28.6mm gas pipe,
directly connect to Tri-joint;
For φ34.9mm gas pipe, add a
reducer and a transition pipe
C
Conn
e
indo ct pipe
or u
nits to
D
Screw join
t
Balance pi
pe
φ28.6mm a transiton pipe
(only for φ34.9mm gas pipe)
Gas and liquid piping connection
Page 18
Side panel hole
Balance piping connection
Outdoor Unit Installation
Outdoor Unit Foundation
 Screw bolt required to further tighten the unit
- Avoid the unit from falling due to earthquake
Page 19
Indoor Unit Installation
Page 20
Indoor Unit Installation
Drainage Pipe Work
 Adjust the downward gradient
Gradient of 1:100
or more
Page 21
Indoor Unit Installation
Drainage Pipe Work
 Group drain pipe
Vent opening
Clamp of drain pipe
Gradient ≥ 1/100
≥100mm
Converged drain pipe
Page 22
Indoor Unit Installation
EXV Box Installation
 MUST install vertically upward
Page 23
Unit and EXV Selection - 2006
Indoor Mode
WMD 09G
WMD 10G
WMD 15G
WMD 20G
WMD 25G
Page 24
Liquid Pipe Diamter (Inch)
R22
R410A
1/4
1/4
1/4
1/4
1/4
1/4
1/4
1/4
3/8
1/4
MEX Model
R22
R410A
MEX-16-2SAP-B
MEX-16-2SAP-B
MEX-16-2SAP-B
MEX-20-2SAP-B
MEX-20-3SAP-B
MEX-20-2SAP-B
CKD 10C
CKD 15C
CKD 20C
1/4
1/4
1/4
1/4
1/4
1/4
MEX-16-2SAP-A
MEX-16-2SAP-A
MEX-20-2SAP-A
CKD 20A
CKD 25A
CKD 30A
CKD 40A
CKD 50A
1/4
3/8
3/8
3/8
3/8
1/4
1/4
3/8
3/8
3/8
MEX-20-2SAP-A
MEX-20-3SAP-A
MEX-20-2SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
Unit and EXV Selection - 2006
Indoor Mode
CCD 10C
CCD 15C
CCD 20C
CCD 25C
CCD 28C
CCD 30C
CCD 38C
CCD 40C
CCD 50C
CCD 60C
Page 25
Liquid Pipe Diamter (Inch)
R22
R410A
1/4
1/4
1/4
1/4
1/4
1/4
3/8
1/4
3/8
3/8
3/8
3/8
3/8
3/8
3/8
3/8
1/2
3/8
MEX Model
R22
R410A
MEX-16-2SAP-A
MEX-16-2SAP-A
MEX-20-2SAP-A
MEX-20-3SAP-A
MEX-20-2SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
MEX-25-3SAP-A
CED 15E
CED 20E
CED 25E
CED 28E
1/4
3/8
3/8
1/4
1/4
1/4
3/8
MEX-20-2SAP-A
MEX-20-3SAP-A
MEX-20-3SAP-A
MEX-16-2SAP-A
MEX-16-2SAP-A
MEX-16-2SAP-A
MEX-20-3SAP-A
CED 40D
CED 50D
CED 62C
3/8
3/8
1/2
3/8
3/8
3/8
MEX-25-3SAP-A
MEX-25-3SAP-A
MEX-25-3SAP-A
MEX-20-3SAP-A
MEX-20-3SAP-A
MEX-25-3SAP-A
Unit and EXV Selection - New
Indoor Mode
WMD 09G
WMD 10G
WMD 15G
WMD 20G
WMD 25G
Liquid Pipe Diamter (Inch)
R22
R410A
1/4
1/4
1/4
1/4
1/4
1/4
1/4
1/4
3/8
1/4
R22
R410A
MEX-15-2SAP-D
MEX-15-2SAP-D
MEX-15-2SAP-D
MEX-18-2SAP-D
MEX-18-2SAP-D
MEX-18-3SAP-D
MEX-22-2SAP-D
CKD 10C
CKD 15C
CKD 20C
1/4
1/4
1/4
1/4
1/4
1/4
MEX-15-2SAP-C
MEX-15-2SAP-C
MEX-18-2SAP-C
MEX-18-2SAP-C
CKD 20A
CKD 25A
CKD 30A
CKD 40A
CKD 50A
1/4
3/8
3/8
3/8
3/8
1/4
1/4
3/8
3/8
3/8
MEX-18-2SAP-C
MEX-18-3SAP-C
MEX-24-3SAP-C
MEX-24-3SAP-C
MEX-24-3SAP-C
Marketing Bulletin: MBA001-0801
Page 26
MEX Model
MEX-22-2SAP-C
MEX-22-2SAP-C
MEX-22-3SAP-C
MEX-22-3SAP-C
MEX-22-3SAP-C
Unit and EXV Selection - New
Indoor Mode
CCD 10C
CCD 15C
CCD 20C
CCD 25C
CCD 28C
CCD 30C
CCD 38C
CCD 40C
CCD 50C
CCD 60C
Page 27
Liquid Pipe Diamter (Inch)
R22
R410A
1/4
1/4
1/4
1/4
1/4
1/4
3/8
1/4
3/8
3/8
3/8
3/8
3/8
3/8
3/8
3/8
1/2
3/8
MEX Model
R22
R410A
MEX-15-2SAP-C
MEX-15-2SAP-C
MEX-18-2SAP-C
MEX-18-2SAP-C
MEX-18-3SAP-C
MEX-22-2SAP-C
MEX-22-3SAP-C
MEX-24-3SAP-C
MEX-22-3SAP-C
MEX-22-3SAP-C
MEX-24-3SAP-C
MEX-22-3SAP-C
MEX-24-3SAP-C
MEX-22-3SAP-C
MEX-24-4SAP-C
MEX-24-3SAP-C
CED 15E
CED 20E
CED 25E
CED 28E
1/4
3/8
3/8
1/4
1/4
1/4
3/8
MEX-18-2SAP-C
MEX-18-3SAP-C
MEX-18-3SAP-C
MEX-15-2SAP-C
MEX-18-2SAP-C
MEX-22-2SAP-C
MEX-22-3SAP-C
CED 40D
CED 50D
CED 62C
3/8
3/8
1/2
3/8
3/8
3/8
MEX-24-3SAP-C
MEX-24-3SAP-C
MEX-24-4SAP-C
MEX-22-3SAP-C
MEX-22-3SAP-C
MEX-24-3SAP-C
Marketing Bulletin: MBA001-0801
Indoor Unit Installation
EXV Box Installation
 3 types of mounting methods
1
3
Page 28
2
Indoor Unit Installation
EXV Box Installation
Page 29
Indoor Unit Installation
EXV Box Installation
Page 30
Refrigeration Pipe Work
Page 31
Refrigerant Pipe Work
Piping Installation
 Ensure piping is dry, clean and no air leakage
Page 32
Refrigerant Pipe Work
Piping Installation
 Nitrogen gas replacement
Nitrogen gas pressure: about 0.02 MPa (0.2 kg/cm2, 2.8 psi)
Page 33
Refrigerant Pipe Work
Piping Installation
 Covering of refrigerant pipes
- Prevent water, dirt or dust from getting into the pipes
Pinching
Taping
Method
Page 34
Refrigerant Pipe Work
Piping Installation
 Covering of refrigerant pipes
The spare pipe is also
needed to cap the
end
cap the pipe end
Indoor
Outdoor
Page 35
Refrigerant Pipe Work
Piping Installation
 Covering of refrigerant pipes
Page 36
Refrigerant Pipe Work
Piping Installation

Page 37
Connection
Refrigerant Pipe Work
Piping Installation
 Refnet & distributors joints to be install horizontally
In ±15°
In ±15°
Page 38
Refrigerant Pipe Work
Piping Installation
 Refnet & distributors joints to be install horizontally
Page 39
Refrigerant Pipe Work
Connection Type of Refnet Joint/Distributors
Refnet
Joint
Page 40
Refrigerant Pipe Work
Connection Type of Refnet Joint/Distributor
Distributor
Page 41
Refrigerant Pipe Work
Connection Type of Refnet Joint/Distributors
Page 42
Refnet
Joint
Distributor
Refrigerant Pipe Work
Connection Type of Refnet Joint/Distributors
Refnet
Joint
Page 43
Distributor
Refrigerant Pipe Work
Thermal Insulation Work
 Insulation material must be able to withstand the
pipe heat
- Heat pump unit – heat resistance polyethylene foamed
(> 120°C)
- Cooling only unit – polyethylene (> 100°C)
 Insulation method
 Thickness of insulation
Page 44
Refrigerant Pipe Work
Thermal Insulation Work
 Both liquid and gas pipe MUST be insulated
Insulation
Finishing tape
Liquid pipe
Control wire
Gas pipe
Page 45
Refrigerant Pipe Work
Thermal Insulation Work
Wrong Method
Page 46
Correct Method
Refrigerant Pipe Work
Thermal Insulation Work
 Insulation thickness
Notes:
•
Page 47
Hot and wet environment, increase then thickness of the insulation
Refrigerant Pipe Work
Thermal Insulation Work
 Connection pipes should be properly fix
Page 48
Gas Charge
Page 49
Gas Charge
Additional Refrigerant Charge
 The amount of additional charge must be
determined by the equation with the total length of
liquid pipe.
 After calculation, the amount of additional charge
should be recorded to the reverse side of the of the
outdoor unit control box cover.
 Put in liquid state refrigerant from the liquid port to
connect the cylinder by using weight scale.
Page 50
Gas Charge
Additional Refrigerant Charge (R22)
 The equation of additional refrigerant charge
Pipe Diamater (mm)
Additional Charge (g/m)
6.35
9.52
12.70
15.88
19.05
50
80
120
180
290
Additional Charge Amount
= (Ø15.88 liquid pipe length x 180g/m) + (Ø12.7 liquid pipe length x 120g/m) +
(Ø9.52 liquid pipe length x 80g/m) + (Ø6.35 liquid pipe length x 50g/m)
Page 51
Gas Charge
Additional Refrigerant Charge (R410A)
 The equation of additional refrigerant charge
Pipe Diamater (mm)
Additional Charge (g/m)
6.35
9.52
12.70
15.88
19.05
45
70
120
180
260
Additional Charge Amount
= (Ø15.88 liquid pipe length x 180g/m) + (Ø12.7 liquid pipe length x 120g/m) +
(Ø9.52 liquid pipe length x 80g/m) + (Ø6.35 liquid pipe length x 50g/m)
Page 52
Wiring
Page 53
Wiring
Standard length 10 meter
ID PCB
MC301 controller
Connection between ID PCB & MC301
Page 54
Credit Card controller
Wiring
RECEIVER
Page 55
Wiring
Wiring Design
 All wires and accessories must be tested
beforehand
 All electric work must be done by licensed
electrician
 Wiring connection should be referred to the
installation manual
 Breaker and fuse should be set on each outdoor
unit
Page 56
Wiring
Communication Wires
 Twisted pair wired with shielding (20AWG)
- Shield wire to be earth on 1 end of the network
- Connected serially to the adjacent unit (Daisy Chain
Connection)
- Same polarity between units (A-A, B-B)
Wire Limitation (Units in meter)
• PC to Gateway – 2m (RS232)
• 1st Outdoor to Last Outdoor < 1000m (RS485)
• Outdoor to Last Indoor < 1000m (RS485)
Page 57
Wiring
Communication Wires
Outdoor unit
Indoor unit
Wired R.C
Page 58
Wiring
Communication Wires
 System wiring
Page 59
Jumper JP7 need to be shorted
for the final indoor unit
Wiring
Communication Wires
 System wiring
Ain = Terminal 30
Bin = Terminal 31
APC = Terminal 32
Page 60
BPC = Terminal 33
Wiring
MDS080~240
Ain Bin Apc Bpc
OD PCB
B
A
Page 61
ID PCB
Wiring
Communication Wires
 System wiring
Page 62
Jumper JP7 need to be shorted
for the final indoor unit
Wiring
MDS260/280/300/320
Ain Bin Apc Bpc
+
MDS120/150/160BRM
Ain Bin Apc Bpc
MDS130/150/160BRS
Indoor Units
Page 63
Wiring
Central Controller
(For R410A MDS Indoor only)
PCB: MC200-C & MC201-C
Page 64
Wiring
Central Wired Controller
• Group control for 32 unit.
• Group Control setting: On/Off, Temperature, Operating mode, Fan speed,
sleep mode and timer On/Off
• Single unit operation setting: On/Off, Temperature, Operating
Mode, Fan speed and sleep mode.
• Timer setting: timer on/off all units.
• Display Circularly: display each unit temperature, mode, fan
speed, running and fault code one by one.
• Real time clock: Required battery to maintain the time if no power
supply.
Page 65
Wiring
Central Wired Controller
MC200-C – M5WMD20/25G
MC201-C - Others
220-240V
/ 1P /
50Hz
MC200-C /
MC201-C
Page 66
MC200-C /
MC201-C
MC200-C /
MC201-C
Wiring
Central Wired Controller
Installation
Dimension
Page 67
Wiring
RS485
Gateway
Ain Bin Apc Bpc
RS232
Computer
1. Display ID status & error history
2. Monitor & Control
3. Daily, Weekly & Holiday timer setting
Outdoor units
Page 68
Indoor units
Wiring
Communication Wires
 Necessary distance from communication wires to
the power supply cable
Current of power supply
≥ 100V
Parallel distance (d)
≤ 10A
300mm
50A
500mm
100A
1,000mm
≥ 100A
1,500mm
Problem may happen due the electromagnetic
interference if the communication line is too close with
the power cable.
Page 69
Summary
Page 70
Summary
 3 basic rules of refrigerant pipe work :
- Dry, Clean and air tight
 Both liquid and gas pipe should be insulate
separately
 The communication wires must be in the same
polarity
 DO NOT wrap the power cable and communication
wire together
Page 71
The End
Page 72