Transcript BPM Update

Beam Position Monitors
Facility Advisory Committee
October 12, 2006
Action Items from previous review
Requirements / Specifications
System overview
Status
Schedule
October 12, 2006
LCLS Facility Advisory Committee
1
S. Smith
[email protected]
Action Items from Previous FAC
Decide on a Digitizer
Echotek glitches, lockups, lack of progress
Plan B  Plan A:
Select 4 channel PAD digitizer.
Fix schedule
Still schedule trouble
Plan barely finishes on time
No schedule contingency
October 12, 2006
LCLS Facility Advisory Committee
2
S. Smith
[email protected]
PRD 1.1-314
Full document:
October 12, 2006
LCLS Facility Advisory Committee
3
S. Smith
[email protected]
Beam Position Monitor System
Analog Frontend Version Three
Switchable Attenuators
Band
pass
Low Noise
Amplifier
Amp
Pad
Band
pass
Amp
Input
To ADC
Fc=140MHz 0dB NF=2.8dB 0dB NF=3.3dB
BW=14MHz to Gain=20dB to
Gain=15dB
(was 20 MHz) 15dB IP3=40dBm 15dB IP3=40dBm
October 12, 2006
LCLS Facility Advisory Committee
4
6 dB Fc=140MHz NF=3.3dB
BW=6 MHz Gain=15dB
IP3=40dBm
S. Smith
[email protected]
Beam Test
100 machine pulses
Effective beam charge 0.35 nC
sy = 2.5 microns
October 12, 2006
LCLS Facility Advisory Committee
5
S. Smith
[email protected]
Resolution vs. Charge
5mm @
200pC
Measured with beam in machine
Tightest machine requirement:
5 micron resolution @ 200 pC
Achieve 4 micron resolution @
200 pC
Resolution scales like 1/Q for the
three measured bunch charges,
as expected
October 12, 2006
LCLS Facility Advisory Committee
30
6
400
S. Smith
[email protected]
Linearity
Measured IP3 of BPM signal path
found IP3 within a few dB of calculation
Bench test of apparent position vs. amplitude looks good
Test consists of 15 kHz AM of 140 MHz signal
Results impeccable.
But beam test shows big amplitude  position modulation
Discovered prototype not built to schematic
Gain distribution wrong  Fixed
Took further steps:
Raise amp idle current 90 mA  140 mA
Reduce bandwidth of first filter, raise that of second filter
Narrowband filter before 2nd gain stage
October 12, 2006
LCLS Facility Advisory Committee
7
S. Smith
[email protected]
Status
Prototype meets resolution requirement
Stability not well established
Long weekend test looks great
But doesn’t apply controlled temperature cycles
Attempt to resurrect CPE environmental
chambers not successful
Thermal cycle tests yet to be performed
Proceeding with first article production
October 12, 2006
LCLS Facility Advisory Committee
8
S. Smith
[email protected]
Calibration
Calibrate through BPM
Via stripline-stripline coupling
Not prototyped
October 12, 2006
LCLS Facility Advisory Committee
9
S. Smith
[email protected]
Schedule
What should be done: (E.M. 9/20/2006)
PCB layout – end of September - 29 ?
PCB fabrication – one week – October 9 ?
PCB assembling – one board here – October 13
Chassis layout – September 28
Panels punching and painting - early October
buy the rest of the components – connectors, resistors, capacitors,
etc.
buy 23 chassis
Write detailed test procedure
October 12, 2006
LCLS Facility Advisory Committee
10
S. Smith
[email protected]
Software & Interface
VME IOC
EPICS PVs
SLC - Aware
EVR
Archive FIFO
Timing
X,Y,TMIT
Calib.
Waveform->U,V,S
Dedicated
Ethernet
PAD IOC
AFE CTL
Timing +
Cal Data
ADC
Acq.
diagnostic
EPICS PVs
AFE
October 12, 2006
LCLS Facility Advisory Committee
11
S. Smith
[email protected]
BPM Controls Description
User Interface Layer (EPICS, SLC-aware)
VME IOC
Converts raw waveforms into X,Y,TMIT and feeds
them (timestamped) to SLC.
Conversion parameters are Pvs
Controls calibration
PAD IOC
Sends raw data upstream (dedicated ethernet)
Diagnostic EPICS PVs
October 12, 2006
LCLS Facility Advisory Committee
12
S. Smith
[email protected]
Software Functionality (Day 1)
From SLC-aware IOC
averaged BPM readings
buffered acquisition
EPICS
raw waveforms
conversion params. (raw position -> x,y)
attenuator settings
diagnostics
October 12, 2006
LCLS Facility Advisory Committee
13
S. Smith
[email protected]
Functionality (Near Future)
Calibration [some features may be present at
day one; untested].
More sophisticated history buffers [other than
SLC 'buffered acq']
Filtering of beam codes in EPICS
Adjusting to beam charge in 'real-time'
October 12, 2006
LCLS Facility Advisory Committee
14
S. Smith
[email protected]
Conclusions
Good performance demonstrated
Schedule critical
October 12, 2006
LCLS Facility Advisory Committee
15
S. Smith
[email protected]