E-Beam Systems Update

Download Report

Transcript E-Beam Systems Update

e-Beams Systems Update
David Schultz
Linac
Injector
Undulator Production
MMF commissioning
ARR
FAC, 10/12/06
D. Schultz
1
LCLS Diagnostics and Controls Physicist
Joe Frisch
Joining Paul Emma on the
LCLS Physics and
Commissioning Team
Brings extensive experience
with diagnostics, RFBPMs,
bunch length monitors, timing
systems, laser systems, …
FAC, 10/12/06
D. Schultz
2
2006 Installation
Sector 21
Sector 20
Laser
stopper
BLM
BC1
L1
Ins/SAB
Wall
FAC, 10/12/06
D. Schultz
3
LX
Linac Status
Downtime installation work is underway
Removal of accelerator structures is done.
Next few weeks - installing
Wall region components (this week)
L1 and LX accelerator regions (this week)
BC1 supports (next week)
Insertion region installation 11/6 (week 12)
Table due 10/16
BLM region installation 11/6 (week 12)
FAC, 10/12/06
D. Schultz
4
Linac Accelerator Section Removal
Before
After
Making room for
the Insertion, L-1
and L-X regions
FAC, 10/12/06
D. Schultz
5
The X-band accelerator section
Klystron, modulator being power
tested prior to installation.
FAC, 10/12/06
D. Schultz
6
Inj/Linac quad magnets ready for installation
FAC, 10/12/06
D. Schultz
7
Diagnostic devices ready to install.
Wire scanners
and profile
monitors
FAC, 10/12/06
D. Schultz
8
Linac Downtime Issues
BPM feed-through welding, many leak.
Leak at ceramic, need UHV QC before welding
Late components:
BC1 Instrument package
BLM 11 (BLM 12 will be in)
Toroids (in several locations)
Vacuum chambers in insertion region.
Spool pieces are being fabricated
to be installed temporarily.
Time will be needed to install these components
as they become available.
FAC, 10/12/06
D. Schultz
9
LCLS Injection
LCLS Insertion region
Critical vacuum
chambers which
may be late.
Linac beam
Linac integrity
needed for ESA
program in Jan.
FAC, 10/12/06
D. Schultz
10
Injector Installation Status
Injector installation has taken second priority to Linac
installation.
Injector vault:
Floor and cable plant installed
Injector beamline:
Accelerator structures, L0a ready, L0b to final bake
RF waveguide needs to go through bake
Gun is in hot test, RF on 10/5
2nd gun is in brazing
then final cold-test, final braze.
Support stands are in the vault ready
except for the GTL table
FAC, 10/12/06
D. Schultz
11
The LCLS Drive Laser
Drive Laser installed, operating
LSS installed in laser room
Now working on temporal
shaping,
Streak camera
Cross correlator
FAC, 10/12/06
D. Schultz
12
The Injector Vault
Cable plant, vault ready for
beamline components.
FAC, 10/12/06
D. Schultz
13
L0A on the MMF CMM
FAC, 10/12/06
D. Schultz
14
The LCLS photocathode electron gun
FAC, 10/12/06
D. Schultz
15
Injector Installation Issues
Water system needs to be installed,
installation reqs. out,
BPM feed-through welding, toroids
Late:
The GTL stand released to purchasing.
Estimate it will be here 11/16 for installation 11/20.
Laser table installation begins 11/27
The Gun will be ready by then, needed later.
GTL is late, now moving to machining. (next slide)
Working to advance the schedule. What is
competing? What can be sent out? Critical path.
FAC, 10/12/06
D. Schultz
16
Gun-to-Linac area
Laser
table
uv
Gun
L0a
Spectrometer
GTL
FAC, 10/12/06
D. Schultz
17
Controls
Magnet power supplies, vacuum controls, installed in
racks and tested. Racks now being installed.
Ethernet backbone to the Computer Center installed
and connected.
Wire scanners controls tested.
Linac cable plant phase 2 installation is underway.
Coordinating hardware installation schedule now with
Controls checkout.
FAC, 10/12/06
D. Schultz
18
Magnets power racks assembled, tested,
prior to installation
FAC, 10/12/06
D. Schultz
19
Vacuum system racks assembled, tested,
prior to installation
FAC, 10/12/06
D. Schultz
20
Controls - PPS
Personnel Protection System is in the review process with
the SLAC RSC.
PLC design conditionally approved!
The Committee wants to see the certification
procedure.
Beam loss and shielding design approved.
Beam Containment System, LCLS FDR 10/6,
RSC review 10/12.
FAC, 10/12/06
D. Schultz
21
Undulator Systems Design
Quadrupole Order placed, vendor designs, 1st article 2/07
Fixed Support/Mover Final Design Review - September 13/14
Go ahead given for production.
Beam Finder Wire Final Design Review - September 20, 2006
Go ahead given for production of BFW, except wire card.
RF Beam Position Monitor Final Design Review - October 4
Testing program has been interrupted by RF gun failure.
Vacuum Chamber Final Design Review - September 27/28
42" chamber welded, machined, to be coated.
2 other prototypes in hand for QC, permeability measurements.
Plan D design effort initiated at SLAC.
FAC, 10/12/06
D. Schultz
22
Undulator vacuum chamber 4-Weld Prototype
Issues: flatness, permeability,
vacuum, Al coating, surface finish
Vacuum Chamber Design Review September 27/28
FAC, 10/12/06
D. Schultz
23
MMF Status
Measurement benches installed and commissioned.
CMM installed and in use.
Quad measurement station operational.
Eight finished undulators are here at SLAC.
Six to eight more to be shipped to SLAC by October 20th
Issues:
Air cond. mixing valve (new) failed. Now repaired.
New breaker panel wiring needed to be worked on.
Compressed air system does not meet spec.
Looking for a work-around.
Need to move to production fine-tuning.
FAC, 10/12/06
D. Schultz
24
Undulator magnets at the MMF
Six undulator magnets in crates awaiting tuning at the MMF.
Six to eight more to arrive at SLAC by October 20th.
FAC, 10/12/06
D. Schultz
25
Injector Accelerator Readiness Review
Safety Assessment Document
Draft LCLS SAD for Injector Commissioning under
internal review.
Operating procedures are being written with AD Ops.
Commissioning
LCLS Commissioning Workshop October 9-11
Includes a Commissioning Readiness Review.
Accelerator Readiness Review (ARR)
LCLS ARR for Injector Commissioning scheduled for
October 31st.
Committee members, speakers on board.
FAC, 10/12/06
D. Schultz
26
Issues
The downtime schedule is very tight.
We got off to a good start.
Not all parts are in hand.
Injector installation will delay commissioning.
Controls checkout (last) is at risk.
The Undulator vacuum chamber is still in the
design/prototype stage.
On the critical path.
Adding engineering resources from SLAC.
The MMF is late and needs attention.
FAC, 10/12/06
D. Schultz
27