E-Beam System Update

Download Report

Transcript E-Beam System Update

e-Beams Systems Update
David Schultz
People
ARR
Linac Installation
Undulator Production
MMF Operations
FAC, 4/16/07
D. Schultz
1
New responsibilities in Linac and Undulator
Jose Chan is the new Cost Account
Manager for LCLS Injector and Linac
Systems, taking over from Eric Bong.
Geoff Pile is the new Cost Account
Manager for Undulator Systems at
ANL, taking over from Steve Milton.
FAC, 4/16/07
D. Schultz
2
Injector Accelerator Readiness Review
FAC, 4/16/07
D. Schultz
3
Injector Accelerator Readiness Review
Safety Assessment Document
The LCLS SAD for Injector Commissioning was
approved Jan. 24th.
Accelerator Readiness Review (ARR)
The ARR for Injector Commissioning was held
October 31st.
The committee (in part) reconvened March 14th.
The four pre-start items were cleared when the ARR
report was released.
Four comments from the SSO were also addressed.
Approval to operate was given April 4th.
FAC, 4/16/07
D. Schultz
4
Injector Commissioning
Injector Commissioning is
underway.
Commissioning has been
impeded by faulty hardware
Problems with profile
monitors, toroids, FC
Working on improving
QA, in the shops, with
vendors and during
installation.
FAC, 4/16/07
D. Schultz
5
First electrons from the gun
4/5/07
Courtesy P. Emma
2007 Commissioning
Sector 21
Sector 20
Laser
stopper
BLM
BC1
L1
LX
Ins/SAB
Wall
FAC, 4/16/07
D. Schultz
See P. Emma’s talk
6
Installation Schedule
6 MeV
Linac-1
L 9 m
...existing
linac
21-1
b,c,d
13.6 GeV
X
Linac-2
L 330 m
Linac-3
L 550 m
21-3b
24-6d
25-1a
30-8c
BC1
L 6 m
‘Wall region’
BC2
L 22 m
2007 down
Now commissioning
SLAC linac tunnel
FAC, 4/16/07
D. Schultz
4.30 GeV
Linac-X
L =0.6 m
Linac-0
L =6 m
rf
gun
250 MeV
135 MeV
7
undulator
L =130 m
DL2
L =275 m
research yard
Draft LCLS Installation and Commissioning Time-Line
Drive-Laser
Commissioning
DriveControls
Laser
Checkout
Installed
LTU/Und/Dump
FEE/NEH Install
LTU/und.
hall “ready”
First Spont.
Light
’08 inst. sched.
under
CD-4a
development
PPS
A S O N D J F M AM J J A S O N D J F M AM J J A S O N D J F M
2006
2007
2008
2009
Gun/Inj./BC1 Gun/Inj/BC1
Install
Commissioning
April 12, 2007 rmb
FAC, 4/16/07
D. Schultz
Controls
Checkout
linac/BC2
Install
8
Checkouts
LTU/und.
Linac/BC2 Commissioning
Commissioning
’07 Downtime Installation
Sept., Oct., Nov. 2007, a very tight schedule.
Installation of BC2 and L3, not L2.
Installation to support BTH-West
Cable plant installation through the BSY
Coordinated through the AD downtime schedule
IRR held March 16th.
Kicker magnet design is still ongoing.
Cable plant inst. schedule is tight.
Scheduling and coordination between the
different disciplines will be vital.
See breakout talks
FAC, 4/16/07
D. Schultz
9
’08 Installation
LTU/Undulator/Dump
Readiness for early occupancy held at Nov. 1, 2007
Begin installation with:
Metrology
Beamline supports
Cable plant
Installation scheduling to be coordinated
by R. M. Boyce
Installation contracts need to go to bid this summer.
Need to complete designs to support these.
See breakout talk
FAC, 4/16/07
D. Schultz
10
Undulator Systems Components
Quadrupole magnets on order.
Beam Finder Wire going to procurement.
Wire card a SLAC responsibility, design underway.
Support/Mover system going to procurement.
RF Beam Position Monitor in development.
Prototype being brazed.
Vacuum Chamber – next slide
These systems are all near the critical path.
WPM/HLS FDR was held March 22nd
FAC, 4/16/07
D. Schultz
11
See G. Pile’s talk
Undulator vacuum chamber - 4-Weld Design
Early 4-Weld prototype
Two competing designs were
carried to the prototype stage.
Review of the Undulator Vacuum
Chamber Design Options, Feb. 22nd
The 4-Weld design was selected to
remain the baseline.
2 full size prototypes have been produced and tested.
Vacuum properties, mag. permeability,
surface coating process, look good.
Fabrication schedule identified as a problem.
Ordering materials now, preparing the fab. bid package
FAC, 4/16/07
D. Schultz
12
Undulator Magnetic Measurement
35 undulators have been accepted at the vendors.
20 undulators are at SLAC.
All undulators will be at SLAC by July.
The MMF is in a production mode, but behind schedule.
3 undulators finished magnetically, but not RFI.
1 undulator in fine tuning, 1 in rough tuning.
Production rate is approaching 1 per week.
Learning to deal with the exceptional cases.
See breakout talk
FAC, 4/16/07
D. Schultz
13
Issues
The ’07 downtime Linac installation schedule is very tight.
Hardware availability is being closely monitored
Kicker magnet, cable plant, are concerns
Controls checkout (last) is at risk.
The Undulator vacuum chamber is still on the critical path.
This schedule is being pushed.
RFBPM production schedule is close to critical.
The MMF is in production.
Need to solidly demonstrate throughput.
FAC, 4/16/07
D. Schultz
14
end