Transcript 下載/瀏覽
Cogeneration System Design for a
High-Tech Science-Based Industrial Park
Cheng-Ting Hsu
Presenter: Cheng-Ting Hsu
Department of Electrical Engineering
Southern Taiwan University of Technology
Tainan, Taiwan
Outline
˙Introduction
˙System Configurations of Cogeneration Facility
˙Short Circuit Analysis
˙Mathematical Modeling of Cogeneration Units
˙Protective Relay Setting for Tie Line
˙Load Shedding Scheme
˙Computer Simulation by Transient Stability Analysis
˙Conclusion
Introduction
• With so many semiconductor manufacturers in the sciencebased industrial park, power quality and service reliability have
always been the critical issues for the industrial customers.
• This paper presents the proper design of protective relay
settings for tie line tripping and load shedding of a
cogeneration system in a high-tech science-based industrial
park.
System Configurations of Cogeneration Facility
Bus902
Bus903
Three Operation Modes of the Cogeneration System
Operation
Modes
GTG1
(MW)
GTG2
(MW)
GTG3
(MW)
STG Total Gen.
(MW)
(MW)
Total Load
(MW)
3G1S
45
45
45
26.9 161.9
151.9
2G1S
45
45
1G1S
45
OFF 26.9
116.9
151.9
OFF OFF 26.9
71.9
151.9
Short Circuit Analysis
The Short Circuit Current at Long-Song Substation
Cases
with 161/161 kV
transformers
without 161/161 kV
transformers
I"k
Iasym
Ipeak
Ib
I"k
Iasym
Ipeak
Ib
Total fault
current (kA)
Fault current supplied
by cogeneration (kA)
39.588
1.566
63.34
-
106.89
-
39.584
1.564
40.425
2.512
64.68
-
109.15
-
40.403
2.494
Mathematical Modeling of Cogeneration Units
• Generator Model
• Excitation System Model
• Governor System Model
Governor Model of Cogeneration Units
Gas Turbine
Steam Turbine
Protective Relay Setting for Tie Line
• 81L relay: 58.4 Hz with 0.1second time delay
• 27 relay: 0.65pu
Load Shedding Scheme
Pstep
2H d 2H
m0
0 dt
60
p.u.
where m0 is the initial frequency decay rate at the tie line tripping
H = 4.4pu for 3G1S
= 3.36pu for 2G1S
= 2.32pu for 1G1S
Computer Simulation by
Transient Stability Analysis
• Case A: A three-phase bolted fault is assumed to occur
at Long-Song substation and the relay 27 of
the cogeneration system is activated to trip the
tie line in 0.1 second after the fault.
• Case B: A short circuit contingency with fault impedance
of 6.22ohm occurs at Long-Song substation.
• Case C: A far distance fault at TPC system is assumed
and the relay 81L of the cogeneration is activated
to trip the tie line.
Case A
A three-phase bolted fault is occurred at Long-Song substation
and the under voltage relay of the cogeneration system
is activated to trip CB H1 and H2 in 0.1 second. .
F
H1
H2
Bus 903
Bus 932
Bus 903
Bus 932
Case B
A short circuit contingency with fault impedance occurs
at Long-Song substation. The cogeneration is operated
in 3G1S mode.
Bus 903
Case C
A far distance fault is assumed and the relay 81L of the
cogeneration is activated at 58.4Hz to trip the tie line. The
cogeneration system is operated in 3G1S, 2G1S and 1G1S modes.
Gas turbine
Steam turbine
Conclusions
• With the series 161/161 kV transformers, the short
circuit current provided by the cogeneration system
will be less than 2kA to meet the operational criterion.
• With the series 161/161 kV transformers, the critical
clearing time and the residual voltage at customer
load buses can be both enhanced.
• By applying the designed protective relay settings for
tie line tripping and load shedding, the isolated
cogeneration system will be restored to stable
operation after transient disturbances introduced by
utility faults.