06-Mitigation Update and Uncertainty Scenarios 2012-2013 Updated:2013-07-25 12:54 CS
Download
Report
Transcript 06-Mitigation Update and Uncertainty Scenarios 2012-2013 Updated:2013-07-25 12:54 CS
Local Area Study
Mitigation Plan Update
and
Uncertainty Scenarios
2012 - 2013
Mitigation Plans Updates
East Helena bus fault or transformer outage
» Ranked # 7 - Outages result in complete loss of the Helena 69 kV
system
» Construct 100 kV loop to radial fed Helena area 100 kV
distribution substation
» Tie proposed distribution substation needed for continued
growth in the Helena area to new 100 kV facilities
» Construct and tie new 100 MVA 100/69 kV auto substation to
new 100 kV facilities
» Add breakers to East Helena 69 kV bus to complete breaker-anda-half scheme
2
Mitigation Plans Updates
Broadview to Billings Area 230 kV double contingency
» Ranked # 8 - Outage results in low to very low voltage in the
Billings Area
♦ Problem worsens after loss of Corette and continued Billings area growth
» Build a new 230 kV line from Broadview into Billings
♦ Assumes slightly diverse route from existing Broadview to Billings 230 kV
lines
Clyde Park bus fault or transformer outage
» Ranked # 13 - Outages result in loss of Livingston and Big
Timber Loads
» Upgrade Big Timber Auto to a 50 MVA transformer
» Reconductor weak 50 kV line near Big Timber
» Add capacitors to Big Timber and Livingston area distribution
substations
3
Uncertainty Scenarios
Scenarios Considered:
Extreme Winter
Low Thermal, Heavy Import
High Wind System Wide
High Generation North of Great Falls (NOGF)
» Similar to stakeholder suggestion
Study Assumptions:
N-0 and N-1 conditions considered
All existing Special Protection Schemes considered
4
Extreme Winter
Scenario Details
2017 Extreme Winter load profile (1:50 forecast)
Hydro plants significantly reduced
» Rivers/reservoirs partially frozen
Thermal plants dispatched at max
» Corette assumed to be mothballed
Wind dispatched at 5%
Scenario Findings
230 kV and 161 kV systems more heavily relied on to supply the
underlying 100 kV systems
Loss of Butte area 161/100 kV tie overloads remaining 161/100 kV tie
100 kV system in Judith Gap area overloads from loss of major 230
kV line in Great Falls area
5
Low Thermal, Heavy Import
Scenario Details
2017 Heavy Summer load profile
All major thermal plants are offline
Wind dispatched at 5%
Path 8 heavily importing
Scenario Findings
Kalispell 115 kV tie line overloads (within emergency limits) for the
loss of Rattlesnake 230/161 kV auto transformer
Loss of Butte area 161/100 kV tie overloads remaining 161/100 kV tie
Steamplant bus outage causes additional overloads on Billings area
100 kV ties to the higher voltage BES
6
High Wind System Wide
Scenario Details
2017 Heavy Summer and Light Autumn load profiles
Existing wind projects dispatched at capacity
All other generation dispatched same as original case
MATL has little to no flow at Great Falls
Scenario Findings
No new thermal issues
Minor high voltage under outage conditions identified in Two Dot
area
7
High Generation NOGF
Scenario Details
2017 Light Spring load profile
Great Falls and NOGF area hydro generation at max
Other Montana hydro dispatched same as original case
Great Falls and NOGF area wind generation at max
Remaining wind generation dispatched at moderate
levels
MATL importing at Great Falls near 300 MW
Path 8, 18, 80 transfers similar to original case
8
High Generation NOGF
Scenario Findings
Butte area 100 kV line heavily loaded under N-0
conditions
Loss of Great Falls – Ovando 230 kV line overloads 100
kV lines in Helena area
Loss of Great Falls – Judith Gap – Broadview 230 kV line
overloads 100 kV lines in Harlowton, Judith Gap, and
Broadview areas
9
Conclusions
System still robust in most areas, few new potential
problems found.
Benefits of widely dispersed generation are
demonstrated.
Potential weaknesses in the 100 kV system were
identified.
» Line or transformer upgrades and/or new facilities could be
required to mitigate problems observed.
This analysis is “Informational” and not the primary
driver for mitigation.
» Because of the uncertain nature of these scenarios, formal
mitigation plans have not been developed.
» In some cases, new generation or TSR requests would drive
mitigation for problems observed.
10