Installation plans from mid 2005
ATLAS overview week
Miikka Kotamäki
Freiburg, 7th October 2004
ATLAS Overview Week, Freiburg,
7th Oct '04
General
 In the July EB it was decided to start an informal task force to look at in
details what can be done to accelerate the schedule in the first 6
months following the insertion of the barrel calorimeter.
 The task force had its first meeting 27th of July and since then has met
roughly once a week.
 The following is a summary of a possible installation sequence worked
out in the task force meetings. The sequence covers the period from
completion of the BT in July ’05 to the end of the Calorimeter A
assembly on the Truck in the beg of ’06.
 The sequence has also been implemented in a working schedule.
 All the working documents of the task force (including the working
version of the schedule) are available on EDMS at:
https://edms.cern.ch/document/490947
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
2
Starting point
 Our starting point is the mechanical completion of the Barrel Toroid in
July ’05. By this time:
 Barrel Calorimeter is ready, tested with all possible services we can
install.
 Toroid installation platforms are still in place.
 Jacks supporting the BT are still in place.
 Some Muon chambers (especially in bottom sectors 12, 13 and 14)
are installed.
 Some cable trays, Muon rails and brackets of the access gangways
have been installed on the coils/warm structure.
 Muon access gangways in sector 13 installed.
 Cryogenic lines installed in the bottom sector.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
3
Barrel Toroid Installation Structures
BT status in July ’05.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
4
Status of barrel muons when BT mechanically completed
4
Muon Barrel status in
July ’05.
5
6
3
Sectors 12, 14:
- BMF (all)
- BOG(6+)
- BOF (4)
7
2
8
1
Sector 13:
- BOL(6?)
- BML(6?)
9
Sectors 2, 8, 10, 16: 16
- BMS (all)
10
15
11
US
14
ATLAS Overview Week,
Freiburg, 7th Oct '04
13
M. Kotamäki -Installation plans from mid 2005
USA
12
5
From mid July onwards
 When the BT is mechanically assembled we move on to a hectic
installation period which consists of parallel work almost all over the
detector and the cavern.
 To simplify the planning of this period we have divided the next ~4
months (from mid July) in 5 short phases that are easier to manage.
The length of the phases are from 2 to 4 weeks and they are marked
with letters A-E.
 For this presentation I have also added 5th phase (F) which was
discussed in the last two task force meetings and which covers the
period from end Oct ’05 to Jan ’06.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
6
Phase A: From mid July to mid August
Sep '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Endcap Calorimeter A
LAr
Muon Barrel A
Platforms
removal
Barrel Toroid services
Barrel Cryo lines
Half Barrel services
Lar Cryostat
BOF, BOG, BMF
chambers
Side C
Endcap cryo lines.
Barrel Calo services
Chimney
Check rails
HS
arches
Barrel Toroid Coils 5-8
Release of
jacks
Barrel
Barrel Toroid Coils 1-4
Preparations for
Barrel Toroid
assembly
BT testing
Barrel Calo testing and commissioning
ID services along
ID services through Muons
Barrel
Platf.
Cable chains
Remov
Muon rails, gangways & services
Endcap Cal. C services
Muon Barrel C
Barrel Tile upper half
assembly
Field mapping
Barrel Toroid
Endcap Calorimeter C
Barrel Calorimeter services, 1st fix on truck
LAr
Big Wheels (TGC1)
Solenoid
Preparations for
BT assembly
JN C
Side A
HS
arches
preparati
on
JN A
BT full power
B
ig
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Sep '04
ATLAS Overview Week,
Freiburg, 7th Oct '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
M. Kotamäki -Installation plans from mid 2005
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
7
Phase A: From mid July to mid August
During this
PHASE :
Q1
U5
Q2
-Jacks released
6 zones (in phi):
-Central
platforms
dismounted
- 4 quadrants
- 2 vertical sec.
-Part of the
extended
platforms
r
-BT final survey
Q4
ATLAS Overview Week,
Freiburg, 7th Oct '04
D13
M. Kotamäki -Installation plans from mid 2005
Q3
8
Release of jacks and partial removal of platforms
Release jacks and
remove top pilars
Remove central
platform and part
of extended
platforms to give
space for the Barrel
Cal and to create a
gap for services
installation at z=0.
Release jacks
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
9
Phase A: What else can be done during this phase?
 Mount cable trays on the warm structure, if not yet done.
 HS arches during the evening.
 Install some cryogenic transfer lines in Q1 and Q2.
 Install temporary new scaffolding to access bolting critical positions in
Q1, U5, Q2
 Prepare minivans on side A.
 Bring in the Solenoid Chimney before we push the Calorimeter in and
fix it temporary
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
10
HS Arches
The top part of the
arches will be preassembled into 3
large sections, and
equipped with
platforms and cable
trays if possible,
already on surface.
Already installed.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
11
Barrel cryogenic lines in top sectors
LAr fill line from expansion
vessel and N2 lines from
the valve box (located next
to the expansion vessel) to
z=0 will be placed asap.
Manual welds at z=0 when
calorimeter moved in.
LAr fill line
LN2 lines (2 per
side) each
containing
internally three
lines
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
12
Phase B = Insertion of Barrel Calorimeter, end Aug ‘05
3 zones (in Z):
A
C
I
During this PHASE :
- Move Barrel Calo
inside
A
C
Prepare and move in
Minivans side C
Access
scaffolding
Minivans
-Side C lower and start
Calo end-cap C
Barrel Calo
inside, working
platforms in place
(4x2 minivans)
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
13
What else can be done during phase B
 Finish fixation of Solenoid Chimney & Control Dewar
 Remove truck A and install muon elevating platform A
 Install phi scaffolding on the surface of the barrel calorimeter
 Finish installation of the cable trays
 Start connecting up the cooling and vacuum pipes.
 Start connecting up the cryogenic lines
 Install the muon elevating platform on side C between the Truck and
BT. This is a new idea and makes it possible to assemble end-cap
calorimeter and install muon chambers in parallel on the same side.
The platform has to be installed, operated and accessed above the rail
line.
 Start installing BT busbars under the HS arches.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
14
Muon installation platform
On side C the
platform is installed
between the BT and
Truck C. The platform
cannot go below the
rail level because of
the bridge and rail
extensions between
the BT and Truck.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
15
Phase C: From end Aug till mid Sep.
Sep '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Endcap Calorimeter A
LAr
Muon Barrel A
Platforms
removal
Barrel Toroid services
Barrel Cryo lines
Half Barrel services
Lar Cryostat
BOF, BOG, BMF
chambers
Side C
Endcap cryo lines.
Barrel Calo services
Chimney
Check rails
HS
arches
Barrel Toroid Coils 5-8
Release of
jacks
Barrel
Barrel Toroid Coils 1-4
Preparations for
Barrel Toroid
assembly
BT testing
Barrel Calo testing and commissioning
ID services along
ID services through Muons
Barrel
Platf.
Cable chains
Remov
Muon rails, gangways & services
Endcap Cal. C services
Muon Barrel C
Barrel Tile upper half
assembly
Field mapping
Barrel Toroid
Endcap Calorimeter C
Barrel Calorimeter services, 1st fix on truck
LAr
Big Wheels (TGC1)
Solenoid
Preparations for
BT assembly
JN C
Side A
HS
arches
preparati
on
JN A
BT full power
B
ig
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Sep '04
ATLAS Overview Week,
Freiburg, 7th Oct '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
M. Kotamäki -Installation plans from mid 2005
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
16
Phase C: From end Aug till mid Sep ’05.

We can now start 4 main activities in parallel:
1. Calo and ID services installation along the Barrel and exit at z=0

Start first putting in place the radial cable supports at z=0
2. Muon Barrel installation

In the present scenario we can install chambers from both ends. Side
A platform has access to the full face. Side C platform is put in
between the BT and Truck C and has access only to sections above the
rail height. Access gangways are installed where possible.
3. Cryo lines connections + cryo services installation
4. End-cap Calorimeter C assembly on the Truck
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
17
Services along the Barrel and exit at z=0

Cable trays z=0 : First operation. Install all the support structures and
z=0 cable trays at z=0 sector by sector in the order 5, 13, 3, 7, 9, 1

Install pipes from z=0 to cooling units (cal) and distribution racks (ID)
on HS and make connections at z=0.

LAr Services: in the order 5,13,3,7,9,1,15,11

Tile Cal Services: in the order 13,3,7,9,5,1,15,11

ID Services: in the order 5,13,3,7,9,1,15,11

Muon Services: install services in top sectors
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
18
Services along the Barrel and exit at z=0
-All sectors
install cable
tray supports
- Install pipes
and connect
them at z=0
-Install calo
cables followed
by ID cables
sector by sector
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
19
ID services on cryostat flange and along the barrel
Total 160 shifts
estimated for the
installation.
Assuming 4 teams
and 2 shifts per day
on each side -> 1
week per sector, total
8 weeks.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
20
Muon Barrel installation, step 1
Chambers before removal of the BT top platforms
Must wait for 1 month before re-tightening the BT bolts and removing
the platforms. Cannot start installing BMS chambers in sectors 4 and 6
before the platforms are removed -> try to do something else in
between.
BOS chambers: all on normal rails (If simpler install all from side A)
BIS & BIL: If possible, insert first 3 chambers per side and park at large Z
till services are in place. Can now be inserted from both sides no need
to jump over at Z=0. The chambers can be later moved into their final
positions without using elevating platform.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
21
Muon Barrel installation, step 1 (cont.)
Chambers before removal of the BT top platforms
Inner layers:
- Insert BIL &
BIS 3/sect and
keep them in
parking position
(sectors 4 & 6
full)
Sectors 2,4,6,8:
- BOS
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
22
Muon gangways in BT



The brackets for the access gangways in the BT coil will be installed where
possible as the coil is assembled.
After removing the BT coil jacks, and the barrel calorimeter put into
position, the gangways and barrel muons will be installed as the BT
assembly platforms are removed.
Prototype platform received from Pakistan.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
23
Gangways, platforms and ladders inside BT
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
24
Connection of Barrel Cryogenic lines
 All the cryogenic lines inside BT are already installed while building it up
or in phase A. In the same way all the lines along the Barrel
Calorimeter up to z=0 are installed already on the Truck.
 As soon as the calorimeter is moved inside to its final position we can
start connecting up the lines at z=0:
-
LAr and LN2 lines on top of the cryostat
FT vacuum lines on top
LAr dump line on bottom
Insulation vacuum lines on bottom
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
25
Goals for phase C
At the end of phase C :
 All barrel calorimeter cables are installed (but in many sectors still
not connected up)
 Installation of the ID cables from PP1 to PP3 has started.
All possible BIL,BIS chambers are either in the parking position or
in the final position. All BOS chambers in top sectors installed.
The cryo-ring is being connected in sector 5 at Z=0.
Final servicing of BT bolts done.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
26
Phase D: From mid Sep till end Sep
Sep '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Endcap Calorimeter A
LAr
Muon Barrel A
Platforms
removal
Barrel Toroid services
Barrel Cryo lines
Half Barrel services
Lar Cryostat
BOF, BOG, BMF
chambers
Side C
Endcap cryo lines.
Barrel Calo services
Chimney
Check rails
HS
arches
Barrel Toroid Coils 5-8
Release of
jacks
Barrel
Barrel Toroid Coils 1-4
Preparations for
Barrel Toroid
assembly
BT testing
Barrel Calo testing and commissioning
ID services along
ID services through Muons
Barrel
Platf.
Cable chains
Remov
Muon rails, gangways & services
Endcap Cal. C services
Muon Barrel C
Barrel Tile upper half
assembly
Field mapping
Barrel Toroid
Endcap Calorimeter C
Barrel Calorimeter services, 1st fix on truck
LAr
Big Wheels (TGC1)
Solenoid
Preparations for
BT assembly
JN C
Side A
HS
arches
preparati
on
JN A
BT full power
B
ig
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Sep '04
ATLAS Overview Week,
Freiburg, 7th Oct '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
M. Kotamäki -Installation plans from mid 2005
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
27
Muon Barrel installation, step 2
Chambers after removal of BT top platforms
First step: remove BT top platforms. Then, install BMS chambers in sectors
4 and 6 first after which aim at completing sector 5 asap.
BMS chambers in sectors 4 & 6:
Will be brought in from Sector 5.
Sector 5: As soon as calo & ID services installed at z=0 finish BIL. When
BMS in sectors 4 & 6 done install all BML, EIL4 and BOL. Might still
need to leave a gap for services at Z=0.
Sectors 3 & 7: Install all BOL (possibly on extended rails to leave a gap
for services). The first 3 BML chambers could also be installed at this
stage but it seems better to wait and install full sectors at one go once
the ID services through Muons are done and all BIL chambers installed.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
28
Muon Barrel installation, step 2
Chambers after removal of the BT top platforms
Sectors 4, 6:
- BMS installed
from 5
Sector 5:
-As soon as Calo &
ID services installed
finish BIL. When
BMS in sectors 4 &
6 done, install all
BML, EIL4 and
BOL
- install gangways
4
5
6
3
7
Sectors 3, 7:
- BOL
- install gangways
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
29
Endcap flexible cryogenic lines
The contractor will
continue installing
Endcap cryogenic
lines as soon as the
Barrel cryo lines are
installed and
connected.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
30
Goals for phase D
At the end of phase D :
In top sectors 4, 5, and 6 all chambers are installed with their
services.
50% of the ID cables from PP1 to PP3 installed. Probably sectors 5,
13, 3, 7 done
The first 3 BIL chambers in final positions in sectors 5, 13, 3, 7
+ the BIS chambers in the neighbouring sectors (full sectors?)
Phi scaffolding removed where possible
ID cabling from PP2 to PP3 done
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
31
Phase E: ~ October ‘05
Sep '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Endcap Calorimeter A
LAr
Muon Barrel A
Platforms
removal
Barrel Toroid services
Barrel Cryo lines
Half Barrel services
Lar Cryostat
BOF, BOG, BMF
chambers
Side C
Endcap cryo lines.
Barrel Calo services
Chimney
Check rails
HS
arches
Barrel Toroid Coils 5-8
Release of
jacks
Barrel
Barrel Toroid Coils 1-4
Preparations for
Barrel Toroid
assembly
BT testing
Barrel Calo testing and commissioning
ID services along
ID services through Muons
Barrel
Platf.
Cable chains
Remov
Muon rails, gangways & services
Endcap Cal. C services
Muon Barrel C
Barrel Tile upper half
assembly
Field mapping
Barrel Toroid
Endcap Calorimeter C
Barrel Calorimeter services, 1st fix on truck
LAr
Big Wheels (TGC1)
Solenoid
Preparations for
BT assembly
JN C
Side A
HS
arches
preparati
on
JN A
BT full power
B
ig
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Sep '04
ATLAS Overview Week,
Freiburg, 7th Oct '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
M. Kotamäki -Installation plans from mid 2005
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
32
Removal of lateral platforms & Muon installation
 Lateral platforms provide good access in many areas and should
therefore kept in place as long as possible. However, they need to be
gradually removed to:
give space for the gangways and chamber installation in lower
sectors
give space for the installation of the last BOF/BOG chambers
between the feet after which we can put back the HS extensions
which the flexible chains in sectors 11 and 15 will be supported
from. The chains in turn must be installed before the Muon chamber
installation in these sectors can be completed (access still to be
sorted out).
 After removal of the lateral platforms all the rest of the BOS and BOL
chambers can be installed on side A, BOS chambers possibly also on
side C.
 Chambers in the inner layers are still dependent on the ID services
installation and must wait for the installation of the ID services through
the gaps in Muons to PP2s.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
33
Muon Barrel installation, step 3
Chambers after removal of lateral platforms
Sectors 10,16:
- all BOS from side
A
Sectors 1 and 9:
- BOL
Sectors 12 and 14
- Rest of the BOF,
BOG
Sectors 11 and 15
- BOL side A only
- access to install
BIR and BIM
chambers still to be
sorted out.
ATLAS Overview Week,
Freiburg, 7th Oct '04
1
9
16
10
15
11
14
12
M. Kotamäki -Installation plans from mid 2005
34
Cable chains in sector 9
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
35
Cable chains sectors 11 & 15
The last BT platforms must be
removed and the last BOF/BOG
chambers installed before the
supports on the HS and the
cable chains can be installed.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
36
Goals for the phase E
At the end of phase E :
 all the ID cables from PP1 to PP3 installed.
 all calorimeter cables connected and tested -> Ready for Barrel
cooldown
 all BT supports & platforms dismounted
 all muon services installed
~2/3 of the barrel chambers mechanically installed on rails.
 endcap flexible chains installation started.
 we are ready to move in the end-cap calorimeter C for connection
of the services
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
37
Phase F: from end Oct ’05 to Jan ’06.
Sep '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Endcap Calorimeter A
LAr
Muon Barrel A
Platforms
removal
Barrel Toroid services
Barrel Cryo lines
Half Barrel services
Lar Cryostat
BOF, BOG, BMF
chambers
Side C
Endcap cryo lines.
Barrel Calo services
Chimney
Check rails
HS
arches
Barrel Toroid Coils 5-8
Release of
jacks
Barrel
Barrel Toroid Coils 1-4
Preparations for
Barrel Toroid
assembly
BT testing
Barrel Calo testing and commissioning
ID services along
ID services through Muons
Barrel
Platf.
Cable chains
Remov
Muon rails, gangways & services
Endcap Cal. C services
Muon Barrel C
Barrel Tile upper half
assembly
Field mapping
Barrel Toroid
Endcap Calorimeter C
Barrel Calorimeter services, 1st fix on truck
LAr
Big Wheels (TGC1)
Solenoid
Preparations for
BT assembly
JN C
Side A
HS
arches
preparati
on
JN A
BT full power
B
ig
36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 1 2 3 4 5 6 7 8 9
Sep '04
ATLAS Overview Week,
Freiburg, 7th Oct '04
Oct '04
Nov '04
Dec '04
Jan '05
Feb '05
Mar '05
Apr '05
May '05
Jun '05
Jul '05
M. Kotamäki -Installation plans from mid 2005
Aug '05
Sep '05
Oct '05
Nov '05
Dec '05
Jan '06
Feb '06
38
Phase F: From end Oct ’05 to Jan ‘06
Side A:
Assembly of the calorimeter endcap A
Using muon platform A install chambers where possible
Center:
 ID cabling through Muons to PP2.
 Complete flexible chains installation, first side C then side A
 Continue connection of services on muon barrel
 Get ready for the testing of the BT.
Side C:
 Start connecting up Calorimeter C
 Push all remaining side C chambers in place (interlinked with PP2
ID cabling)
 Insert Monoblock and washers
 Start Big Wheels (TGC1) assembly!
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
39
ID services through Muons to PP2
Six PP2s per side.
Current estimate for
the workload is 20
shifts per PP2!?
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
40
TGC1 assembly on side A
Muon barrel
installation continues
in parallel. Elevating
platform in front of
the Toroid not shown.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
41
TGC1 assembly
By the completion of
the TGC1 assembly
the Muon Barrel
installation should
also be finished, and
the elevating
platform removed.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
42
Feb ’06: Close for Solenoid field mapping
• Move endcap
calorimeters to run
position and bring
down the shield
discs.
• After field mapping
re-open and start
connecting
calorimeter A and
continue with 2nd Big
Wheel on side C.
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
43
From Jan ’06 onwards
Installation schedule version 6.24 summary
ATLAS Overview Week,
Freiburg, 7th Oct '04
M. Kotamäki -Installation plans from mid 2005
Detailed version available on EDMS at:
https://edms.cern.ch/document/380587
44
Summary

“Installation Summer 2004 task force” has worked out a schedule proposal for
the 6 months following the completion of the BT.

The schedule is now much more detailed than before, especially on the
installation of services.

The main difference in the sequence w.r.t previous version is that on both sides,
A and C, the installation of the Muon barrel chambers is done partially in
parallel with the End-cap Calorimeter assembly, and on side C the assembly of
the first Big Wheel is started when the barrel chambers installation is still going
on.

The rest of the schedule has not been discussed in the task force, but I have
now scheduled the assembly of all four Big Wheels on side C before lowering
End-cap Toroid C. On side A the sequence is in reverse order.

In the schedule all the Big Wheels on side A are assembled before closing the
beam pipe (March ’07). However, in case of problems and delays we must be
able to assemble the Big Wheels also with the beam pipe closed.