Integrated Water Resources Management / Akhouryan River
Construction of Kaps Reservoir and Gravity Irrigation System
German Financial Cooperation with Armenia
Partners
• Government of the Republic of Armenia
- represented by the State Committee of Water Economy under the
Ministry of Territorial Administration
• Government of the Federal Republic of Germany
- represented by the Federal Ministry of Cooperation and Development,
administered through KfW Entwicklungsbank
• implemented by a consortium of consultants
- CES Consulting Engineers Salzgitter GmbH
- AHT GROUP AG Management & Engineering
- Yerevan State University of Architecture and Construction
12/12/2013
Presentation to National Water Policy Dialogue
2
Location
• within international / trans-boundary River Basin
EU-ENPI EPIRB
12/12/2013
Presentation to National Water Policy Dialogue
3
Location - national
• Kaps Reservoir within existing irrigation scheme
12/12/2013
Presentation to National Water Policy Dialogue
4
Kaps Dam and Reservoir
• existing infrastructure from abandoned works in late 1980s
Spillway
Alignment
Ջրհեռի
ճանապարհի
հարթեցում
Dam axis
Construction
Tunnel
Պատվարի առանցք
Շինարարական թունել
Irrigation
Tunnel
Ոռոգման թունել
Kaps Dam Site
2
12/12/2013
Kumayri Tunnel
Կումայրու թունել
Presentation to National Water Policy Dialogue
5
Rehabilitation Needs
Completed left
embankment
Central part of
embankment
Left abutment
Concrete cap
for grouting
View to downstream
Drilling of core material
12/12/2013
Presentation to National Water Policy Dialogue
6
Rehabilitation Needs
Construction tunnel
intake partly blocked
Construction tunnel outlet
Irrigation tunnel intake
Collapsed lining of
irrigation tunnel
Investigation of tunnel
lining and rock by Georadar
Outlet of irrigation tunnel /
Intake Kumayri tunnel
12/12/2013
Presentation to National Water Policy Dialogue
7
Envisaged Irrigation Areas
• Northern part:
Replacement of pumping
stations (some are
abandoned) by gravity
conveyance
• Southern part:
Conversion to irrigation of
dryland farming area along
disused conveyance
system of Kaps Irrigation
Project
12/12/2013
8
Presentation to National Water Policy Dialogue
8
Project ToR
• Task I
Analyse and Update of 2009 Feasibility Study “IWRM
/ Akhouryan River, Phase 1”
• Task II
Detailed design and assistance to tendering “IWRM /
Akhouryan River, Phase 1”
• Task III
Construction supervision for Phase 1 contracts
• Task IV
Feasibility Study for the Irrigation System of “IWRM /
Akhouryan River, Phase 2”
• Task V
Management Plan for the Akhouryan River Basin
Note:
• Phase 1 of the Project comprises the rehabilitation of the dam at a low level
providing about 6 Mm3 capacity and the gravity supply of 2,200 ha irrigation
currently supplied by pumps or are non-irrigated.
• Phase 2 comprises the improvement of the irrigation system of the 2,200 ha.
• Feasibility study under Task I covers also the raising of the dam to its final height.
12/12/2013
Presentation to National Water Policy Dialogue
9
Timeframe
• for Tasks I, IV and V the timeframe is from 1st of November 2013
through April 2014 (6 months)
• for optional Task II the timeframe would be from May 2014 through
April 2015 (12 months)
• for optional Task III the timeframe would be 24 months (mid 2015
to mid 2017)
12/12/2013
Presentation to National Water Policy Dialogue
10
Results to expect
• Stabilization of dam construction site (Stage 1) with improvement
of the conveyance system (replacement of pumps by gravity
system) under Phase 1 of the Project
• Initial creation of storage capacity to relieve Arpi and Bavra
Reservoirs from their buffering function
• Preparation of a feasibility study for the improvement of the
irrigation system under Phase 2 of the Project with significant
efficiency improvements
• Preparations for Stage 2 of Kaps Dam (elevating dam to final
height)
• Embedding the irrigation scheme of “Shirak” Water User
Association into the National and International River Basin
Management Plan
• Stabilization of agricultural production in Shirak Marz for benefits
such as food security and rural employment
12/12/2013
Presentation to National Water Policy Dialogue
11