TI 8 installation and commissioning
Volker Mertens, LHC-TCC, 21. 9. 2001
Outline:
Layouts
- Extraction + TT40
- TI 8
- Injection zone
- Warm line to sector 8-7
Planning
- Framework
- Details
Summary
Thanks to:
S. Akhtar
P. Bonnal
C. Colloca
K. Foraz
R. Genand
J. M. Jimenez
R. Jones
G. Kouba
J. Kühnl-Kinel
M. Meddahi
P. Proudlock
J. P. Quesnel
G. R. Stevenson
J. Uythoven
K. Weiss
E. Weisse
...
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
TI 2 / TI 8 overall layout, main milestones
• combined length 5.6 km
• over 700 room-temperature magnets (74 recup’d)
http://proj-lti.web.cern.ch/proj-lti/
TI 8
04/2004
04/2006
TI 2
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
New fast extraction in SPS LSS4 towards TT40
QD419
5 kickers (MKE)
bumper 1
magnetic septa
(MSE)
bumper 4
bumper 3
bumper 2
TT40
SD 01/02 - MSE girder installation, incl. magnet supports,
plug-ins, motorisation, cooling & cooled cables
- MSE power supply installation
- MKE power + control cables + cooling
- bumper cabling & power supply installation (BA4)
- MKE infrastructure in ECA4
SD 02/03 - MSE magnet installation, diluter, controls, cabling
- MKE magnet installation
- alignment & survey
- system tests (vacuum, cooling, power)
2003
- MKE PFN + switches upgrade (faster rise time)
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
x
2002
TT40
link tunnel TA42
ECA4
PGC8
TED
TT40
chicane
STOP
TJ8
TT41
SPS
TI 8
SD 01/02 - TT40 services installation
SD 02/03 - TT40 magnet installation
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
Transfer line TI 8
TED
D(m)
STOP
s(m)
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
Injection elements + warm line for sector test
UX85 centre
IP8
~ 215 m to substitute
350
2.5
bx
by
Dx
300
250
2
1.5
200
1
150
0.5
100
0
50
0
480
530
580
630
680
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
730
-0.5
780
Status of main magnets
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
Working Summary Schedule
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
3 phase installation + commissioning approach
to disentangle potential problems + build upon previous experience
1. SPS extraction / TT40 (up to TED400353)
early
2003
test equipment + tune extraction
test extraction performance / check for SPS errors (p-to-p reproducibility, drifts ?)
access system must be capable to handle varying conditions safely + efficiently
time sharing with bulk installation(s) to be agreed (+ interlocks to be set up)
2. Transfer line TI 8 (up to TED87765)
late
2003
debug full-size installation
investigate behaviour of line (time-dependent effects ?)
basic ingredients of definitive control system must be available (conc. on line !)
for beam tests: beam instrumentation must be available
[set up trajectory correction
 certainly not a one-shot action !
measure optical characteristics]
3. LHC injection (up to TDI) (+ temporary warm line up to left of IP 8 !)
as from
04/2004
set up injection equipment, as for nominal injection
learn to work with new software (establish seamless link with main ring BI,
prepare for future integration with LHC first turns (inj. oscillations, orbit FB, ...)
access + safety systems fully functional
interlocks primordial (at least at higher intensities)
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
sector 8-7
2001
Overall planning: 2001 / 2002
2002
LHC
side
SPS
side
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
2003
2002
full platform
in UX85
“half” platform
in UX85
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
2002 / 2003
2003
Transfer of bulk of TI 8 material
platform
sector 8-7 >
< TI 8
UX85
PX84
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
2003
“half” platform
in UX85
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
2003 / 2004
2004
2003
2004
TI 8 installation and commissioning / V. Mertens / LHC-TCC / 21. 9. 2001
2004
Summary
•
An approach is proposed where installation and commissioning is split in 3 phases:
– SPS extraction / TT40
– TI 8
– injection elements + temporary warm line
•
•
•
•
Planning looks feasible,
although not yet achieved.
which should help to use subsequent test and beam times to their best,
i.e. to be best prepared for the sector test + injection milestone.
Many circumstances have to fit to translate this planning into reality
(extraction delivered, no CE delays, no crane breakdowns, …).
Main magnets incl. vacuum are already available, but many ingredients should arrive
just-in-time (MKI, MSI vacuum, transport system, …).
For certain elements surrogate solutions exist (e.g. MKI, if necessary).
Baseline planning is to have all injection elements (MKI, MSI, TDI/TCDD
+ associated vacuum + instrumentation) installed at their definitive
locations and the remainder to the triplet left of IP8 to be filled
temporarily by TI 2 and SPS material.
Progress + constraints need to be closely monitored.
2002 and even more 2003 are decisive.