A Vision for Transmission: COMPETITION Massachusetts Restructuring Roundtable Boston, MA

Download Report

Transcript A Vision for Transmission: COMPETITION Massachusetts Restructuring Roundtable Boston, MA

A Vision for Transmission:
COMPETITION
Massachusetts Restructuring Roundtable
Boston, MA
November 16, 2001
José A. Rotger
Manager, Regulatory Strategy
Is Transmission a Competitive Business?
• Historically, not treated as a business at all
– Generation and transmission planned together
– New transmission driven by generation plans
– Inter-area links for reliability ONLY, not economic
efficiency & trade – “must maintain self-sufficiency”
• But, industry restructuring has changed role
for transmission => economic trade
• New transmission competes against new
generation, demand-side measures,
distributed generation, etc.
Massachusetts Restructuring Roundtable
November 16, 2001
Page 2
Problems with Conventional Wisdom
• Undermined by new technology
– More modular, less “lumpy” => changes economics
– Far less environmental/community impact => affects siting
• Undermined by new regulatory structure
– Allows incentives inherent in restructured electricity markets
to be applied to transmission investment
– Recognize that transmission competes with other solutions
(G, DG, DSM) to meet customer needs
– Owners bear risks, rewards of investments => No stranded
cost risk
Massachusetts Restructuring Roundtable
November 16, 2001
Page 3
Framework for Market-Based Transmission
• Bid-based markets
• Security-Constrained Economic Dispatch
• Locational Wholesale Prices
– Preferably nodal
• Tradeable Financial Transmission Rights
– Supporters of transmission expansions receive FTRs
– Term of FTRs should be as long as possible
• PJM, NYISO have this framework in place
– ISO-NE, Ontario IMO to follow
Massachusetts Restructuring Roundtable
November 16, 2001
Page 4
Benefits of Market-Based Transmission
• Benefits to the environment
– More transmission => more markets for cleaner energy
– Deployment of advanced technologies with much lower impacts
• Benefits to the community
– More underground transmission (faster permitting)
– Eminent domain not needed by market providers
• Benefits to consumers
– The right investments in the right place at the right time
– Protection from stranded costs
– Efficient competition among all sources of delivered energy will
lower costs to consumers
Massachusetts Restructuring Roundtable
November 16, 2001
Page 5
Current Issues in Transmission
• Does a monopoly transco serve the best
interests of consumers?
– Transco will be a market participant because it will
affect market outcomes
– How will merchant transmission fit in?
• How will the RTO conduct transmission
planning?
– Will the transmission planning & expansion
process focus on reliability or economic needs?
– Will the incumbents control the process?
• Do we need a regional/national approach to
siting?
Massachusetts Restructuring Roundtable
November 16, 2001
Page 6
RTOs & Market-Based Transmission –
What is needed?
• Defined & marketable property rights
– Supporters of transmission expansions receive Financial
Transmission Rights (FTRs) that can then be monetized via RTO
• Free entry by entrepreneurial transmission companies
– No de jure or de facto monopoly over new transmission
• Level competition between new entrants & incumbents
– Equal opportunity for new entrants to compete for new transmission
investments – regulated or market-driven
• RTO planning function: Maintain reliability
– Planning serves as “backstop” for market failure, not preempt it
– Threat of “socialized” investments undermines market alternatives
– Allow greatest competition among all alternatives
Massachusetts Restructuring Roundtable
November 16, 2001
Page 7
The Alternatives
• Status quo: Gridlock in grid investment
– Endless debate about “net benefits” of project & who will pay
– No mechanism to address links between markets
• Monopoly transmission company (ITC)
– One transmission company:
• Operates under incentive rates
• Responsible for all congestion, losses, & reliability
• Makes unilateral investment & operating decisions to
maximize profit
– But, regulator must guess at correct incentive rates
• Why not let market set marginal transmission rates?
• Strong central planning by RTO
– Requires crystal ball, and consumers bear risk of imperfect
planning foresight
Massachusetts Restructuring Roundtable
November 16, 2001
Page 8
So, how do we get there?
• Don’t fall prey to commonly held myths
regarding transmission expansion:
“Our Top 10 myths”
Massachusetts Restructuring Roundtable
November 16, 2001
Page 9
Top 10 Myths About Grid Expansion
No. 10 Transmission is and will remain a
natural monopoly
Fact:
 True for grid operation, but NOT for additions and
expansions
 With LMP and tradeable property rights, G, T,
DSM, etc. all compete to meet new energy needs
 Free rider problems, economies of scale
arguments are being resolved by technology
Massachusetts Restructuring Roundtable
November 16, 2001
Page 10
Top 10 Myths About Grid Expansion
No. 9 Free riders restrict market-based
transmission investment
Fact:
 New controllable technologies address free riders –
only users pay (HVDC, FACTS)
 FTRs discourage free riders and provide vehicle for
investment recovery – only users pay
 The combination of risk aversion (bankruptcy) and
well-designed energy markets (with volatility) prevents
or eliminates free riders (woe to the unhedged)
Massachusetts Restructuring Roundtable
November 16, 2001
Page 11
Top 10 Myths About Grid Expansion
No. 8 Economies of scale (“lumpiness”)
restrict market-based transmission investment
Fact:
 New controllable technologies are smaller and more
modular (HVDC, FACTS)
 Modularity preserves options
 Grid capacity can match market demand
 Generation has residual economies of scale (even
with GTs), but few worries of market failures
Massachusetts Restructuring Roundtable
November 16, 2001
Page 12
Top 10 Myths About Grid Expansion
No. 7 Need eminent domain and other
state police powers to site transmission
Fact:
 New cables are smaller and easier to place
underground (HVDC Light) in existing ROWs (railroads,
highways, pipelines, etc., just like fiber optic cables)
 New point source and converter devices allow
capacity to be increased in existing substations
 Siting regulations/statutes changed to reflect
merchant generation – why not transmission?
Massachusetts Restructuring Roundtable
November 16, 2001
Page 13
Top 10 Myths About Grid Expansion
No. 6 Transmission takes too long to build
– need to “pre-approve” projects
Fact:
 New transmission technologies can approximate
project schedule for generation (e.g. 2-3 years)
 If RTO-sponsored transmission is pre-approved,
generators will locate at sending end of planned
upgrades (and what is the future of distributed
generation?)
Massachusetts Restructuring Roundtable
November 16, 2001
Page 14
Top 10 Myths About Grid Expansion
No. 5 Transmission is only 5-6% of total
cost – why bother?
Fact:
 Marginal cost of transmission much higher than
average cost (10x? 20x?)
 Congestion charges visible under LMP/FTR
frameworks – N.E. Mass & Boston congestion costs
5/99-7/00 = $80+ million
 To achieve efficiency, get prices right at the margin
 or generators in remote locations will push RTO to expand
grid
Massachusetts Restructuring Roundtable
November 16, 2001
Page 15
Top 10 Myths About Grid Expansion
No. 4 Why not over-build transmission – the
benefits outweigh any efficiency losses
Fact:
 “Must build to eliminate congestion” (at any cost) –
why bother with LMPs and FTRs? Let this market
structure work!
 Why saddle captive customers with uneconomic
transmission investments? (think nuclear)
 “Must build to mitigate market power” – there are
cheaper and better ways (behavioral solutions)
 “Must build to improve liquidity” – at what price?
Massachusetts Restructuring Roundtable
November 16, 2001
Page 16
Top 10 Myths About Grid Expansion
No. 3 Only a central planning process can
efficiently reduce congestion
Fact:
 Backstop role for reliability-driven upgrades, but NOT
for economic upgrades
 Why forfeit the competition benefits of new entrants?
 Central planners are destined to be wrong – and the
burden is on captive customers, NOT shareholders
 Central planners may be biased and may NOT be
sufficiently independent
 Any residual central planning requires complete
independence and a competitive solicitation process
Massachusetts Restructuring Roundtable
November 16, 2001
Page 17
Top 10 Myths About Grid Expansion
No. 2 We need incentive rates (PBR) to
build new transmission
Fact:
 Why not rely on market-based CMS -- LMPs and
FTRs? Let this market structure work!
 Why do we need incentive rates for the existing wires
in order to build new ones?
 Price caps (RPI – X): With LMPs & FTRs in place,
why pre-determine and lock in productivity
improvements (X)? Why not let the market set X?
Massachusetts Restructuring Roundtable
November 16, 2001
Page 18
and the Number One
Myth about Grid
Expansion is…
Massachusetts Restructuring Roundtable
November 16, 2001
Page 19
Top 10 Myths About Grid Expansion
No. 1 Market-based transmission cannot be
financed or built on basis of market rights
Fact:
 The US (and other nations) have implemented the
market structure (LBMPs & FTRs) necessary for marketbased transmission investments
 Let the markets work!
 TEUS is actively building transmission in USA and
Australia on a fully market basis – over 1,200 MW of in
service and proposed projects (& more to come)
Massachusetts Restructuring Roundtable
November 16, 2001
Page 20
Our Solution
• Over $500 million in market-driven projects
• Australia
– Directlink
– Murraylink
– Southernlink
180 MW, 65 km u/g DC
Operation
220 MW, 180 km u/g DC
Construction
150 MW existing lines upgrade Permitting
• United States
– Cross Sound
330 MW, 40 km subsea DC
Permitting
• Final permit may be issued by December => operational by summer 2002
– Lake Erie Link
– Harbor Cable
325-975 MW, 120 km DC
330-990 MW u/g & subsea
Permitting
Development
• Other competitors: NU (CLIC), Neptune, GenPower
Massachusetts Restructuring Roundtable
November 16, 2001
Page 21
Final Thoughts
• Market-based solutions are a reality
• Technology is changing the industry
• Trust, but verify
– Markets can and do work!
– But, ensure that the right structures are in place to
allow full and fair competition
Massachusetts Restructuring Roundtable
November 16, 2001
Page 22
For more information
• Our web sites:
– US
– CSC
– Australia
www.transenergieus.com
www.crosssoundcable.com
www.transenergie.com.au
• Contact information:
– Jeff Donahue
– Ray Coxe
– José Rotger
(508) 870-9900 x105 [email protected]
(508) 870-9900 x106 [email protected]
(508) 870-9900 x108 [email protected]
Massachusetts Restructuring Roundtable
November 16, 2001
Page 23