Background
• Host Country:
• Project Proponent:
Egypt
Hydro-Power Plants
Executive Authority
Project Sponsors:
Ministry of Electricity
& Energy (MOEE)
•
Ministry of Irrigation
& Water Resource
Other Project Participants:
(KfW)
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Technical description of the
project activity
• The project’s purpose : it is the
generation of electrical energy. The
project would have a total investment
cost (excluding customs and duties) of
approximately € 28.6 to 29.8 million,
depending on foundation conditions.
Construction would take about two
and a half years (30 months).
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Technical description of the
project activity (contd.)
• The project involves construction of a
power plant within the river channel
immediately downstream of the
existing Damietta Barrage
• The installed capacity would be 13.0
MW, with actual hydropower
generation rising from 81 GWh in 2010
to 84 GWh in 2017, as river flows
increase.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Technical description of the
project activity (contd.)
• The power generated would be
supplied to the local grid by a 66 kV
double circuit overhead transmission
line running for about 450 m to a new
66 kV substation north of the WRC
campus, and from there by a new 66
kV overhead line for some 300 m to an
existing overhead 66 kV transmission
line.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Estimated Annual Generation
(year 2017)
Project
Damietta (Delta)
Min Hydro-Egypt
Plant Capacity
Installed Dependable*
MW
MW
13.0
7.6
‹#›
Annual Generation
Firm
Average
GWh
GWh
66
84
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Cost of Damietta Barrage Small
Hydropower Project
Hydropower Plant
Regular Foundation
FC
LC
106€
106LE
Damietta
23.0
39.1
Unfavorable Foundation
FC
LC
106€
106LE
23.6
42.8
(1) Cost level 1st quarter 2003
(2) Excluding customs and duties
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Technical description of the
project activity (contd.)
• The construction time for the project is
about 2.5 years, and the earliest year of
construction is expected to be 2005. The
earliest year of commissioning and
operation of the project will be 2007.
• The environmental assessment carried our
during the study considers that the project is
regarded as addition to the existing barrage
and its head pond, and no re-location of
people is involved.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Location of the project activity:
• Host country party(ies) : Egypt
• Region:
Qalyoubia Governorate
• City:
Al-Qanater Al-Khairyy
• The Damietta Barrage small
hydropower project is located on the
Nile river branche namely: Damitta
branch at Qalyoubia Governorate
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Min Hydro-Egypt
Jerba-CDM-Investment-Forum
‹#›
UNEP RISOE / APEX
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
• Category:
“Renewable electricity generation
in grid connected applications”.
• Technology:
Bulb, directly coupled generator.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
How GHGs are reduced :
• Applying the methodology described
in section B.2, the project will generate
an annual reduction of 47,058 tCO2
and a total reduction of 988,218 tCO2
over 21 years.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Damietta Barrage Small Hydro-Power
Project ERs
Crediting Period
tCO2
Year 1
Year 1-7
Year 1-14
Year 1-21
47,058
329,406
658,812
988,218
Public funding of the project activity
No public funding is provided for this Project.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Baseline methodology
• Methodology for ex post monitoring of
electricity generation from the project
and its impacts on emission from the
operation and expansion of electric
sector”.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Justification of Baseline Scenario
• The project type is not a common
practice.
• The project type lacks priority within
the planning scheme of the country.
• Perceived technology risk.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
The outline of the method to calculate the ERs is as follows:
Determination of baseline emission rate (as per section B3)
(tCO2/MWh)
Monitoring generation output from the Project
(MWh)
Calculation of ERs generated by the Project using the formula:
Periodic annual electricity dispatched to the grid X baseline emission rate for this period
(tCO2)
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
• The net annual generation is estimated to
be: 86,663 MWh
• The baseline emission rate is: 0.543
tCO2/MWh
• The net annual reductions are estimated to
be: 47,058 tCO2
• The net reductions over a 21-year crediting
lifetime are estimated to be: 988,218 tCO2
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Environmental impacts
• The environmental assessment has
concentrated on identifying environmental
and social factors which might affect the
project layout, design and cost.
• A limited consultation process was carried
out, appropriate to the level of detail of the
study. Persons and organizations consulted
are listed in the main documents.
• The screening process carried out in this IEE
has not identified any significant negative
environmental impacts likely to be caused
by the project.
Min Hydro-Egypt
‹#›
Tunis, Sept 22-24, 2004
TIMS/EEAA
Jerba-CDM-Investment-Forum
UNEP RISOE / APEX
Stakeholders comments
• There have been consultations with the
farmers downstream from the irrigation
district who use the water stored in the
Barrage. There have also been consultations
with affected landowners along the route of
the transmission line.
• Most of the comments appreciate and
welcome the project.
Min Hydro-Egypt
‹#›