Global R&D Board Bill Willis For the ILC GDE R&D Board Board Members and Areas • • • • • • Chris Damerell Eckhard Elsen Terry Garvey Hitoshi Hayano Toshiyasu Higo Tom Himel __________________ AREAS SC CAVITIES,
Download ReportTranscript Global R&D Board Bill Willis For the ILC GDE R&D Board Board Members and Areas • • • • • • Chris Damerell Eckhard Elsen Terry Garvey Hitoshi Hayano Toshiyasu Higo Tom Himel __________________ AREAS SC CAVITIES,
Global R&D Board Bill Willis For the ILC GDE R&D Board Board Members and Areas • • • • • • Chris Damerell Eckhard Elsen Terry Garvey Hitoshi Hayano Toshiyasu Higo Tom Himel __________________ AREAS SC CAVITIES, CRYOGENICS, BEAM DELIVERY, INJECTOR, LINAC PERFORMANCE, CONTROLS, INSTRUMENTATION DETECTORS 11/7/2015 • • • • • Lutz Lilje Hasan Padamsee Marc Ross Andy Wolski Bill Willis, Chairman ____________________ CRYOMODULES, DAMPING RINGS, POWER SOURCE, CONTROLS, HIGH AVAILABILTY What we are doing • We have developed an “Ideal R&D Program” by area with a multi-level Work Breakdown structure • This is being prioritized on an international basis, and has been used to identify gaps • Priorities of short-term fund distribution are asked by some Funding Agencies and will influence future proposals • Our Board Member Eckhard Elsen is RDB Data Integrator. We are taking the data from Proposals and Programs and putting them in a Common Format - with support from the CERN Project tools team: J.DeJonghe et al. • First deadline was for this meeting, examples in next slides. • This will be evolved to include schedules and resources. The resources will be broad categories: small, medium, and large, so that we may estimate wide categories with sensible weights. We see already that there are many schedule links, requiring rough timelines to see how the linkages work out. 11/7/2015 What the RDB is asked to do • • Take a Global View Structured R&D Projects, “Projectized” • • Proposal Driven Accelerator + Detector What we can do quickly: • We created a Structured “Ideal R&D Program” for the accelerator to compare with the actual proposals and programs, to ensure that the R&D needed for an early construction start gets done without Gaps. • We evaluated Priorities (1-4, 1=very high) based on risk and complexity of critical R&D to get the work done on time - this will need follow-up 11/7/2015 Segment of a priority list The whole collection has several hundred entries. 11/7/2015 WBS Structure derived from partial list 11/7/2015 Summary & Next Steps • Scope of R&D program well described and understood • CERN team transfers to Data Base and generates a variety of Reports • We will make our information available to funding distribution reviews on request • We will add time line information and study schedule linkage • The data must be upgraded and tracked fairly often, including changes in plans • We should have a more finished product in about three months. 11/7/2015