Project Manager’s Report David Britton 4/July/2005 D. Britton Outline 1. Project Maps 2. Resources 3.

Download Report

Transcript Project Manager’s Report David Britton 4/July/2005 D. Britton Outline 1. Project Maps 2. Resources 3.

Project Manager’s Report
David Britton 4/July/2005
D. Britton
Outline
1. Project Maps
2. Resources
3. People and Roles
4. Tier-1 Hardware
4/July/2005
Project Manager’s Report
D. Britton
GridPP2 ProjectMap
GridPP2 Goal
To develop and deploy a large scale production quality grid in the UK for the use of the Particle Physics community

0.
Tier-A

Tier-1

1
LCG

Tier-2
1. 1


Design

1. 2
1. 3

2.1




2.2

Development
2.3


2.4


2.5


2.6
Network
4/July/2005
3.2
3.3
3.4


3.5

4.1


4.2

3.6



4.3
Grid Operations

5
Management


5.1
6
External

Planning

SAMGrid


5.2


4.4
6.1

Deployment

6.2
6.3

Engagement


6.4
Knowledge
Transfer

Navigate down
External link
Link to goals
LHC Deployment
Project Manager’s Report

Interoperability

UKQCD


Dissemination
Portal
PhenoGrid


BaBar
CMS
Information
& Monitoring


LHCb
Security

3.1
Experiment Support
4
Non-LHC Apps
Ganga
Workload
Management


ATLAS
Data & Storage
Management

Middleware Support
3
LHC Apps
Metadata
Service Challenges

Deployment
2
M/S/N

Production Grid
D. Britton




Metrics
84 are currently satisfied; the 14 below are not:
Shortage of Hardware (wrt planning): This reflects
0.104: Number of LCG/EGEE job slots published by the UK.
the slower than planned ramp-up of resources at the
0.105: Number of LCG/EGEE jobs slots used.
institutes. Tier-2 Report suggests this is recovering.
0.106: GridPP KSI2K available.
0.108: GridPP disk storage available:
Low usage of resources: Mitigates the above. Tier-1
0.111: GridPP tape storage made available to LCG/EGEE.
Report shows:
0.112: Fraction of available KSI2K used in quarter.
2004: 56% CPU; 48% Disk.
0.113: Fraction of available disk used in quarter.
2005: 42% CPU; 64% Disk.
0.114: Fraction of available Tape used in quarter.
0.131: Tier-1 service disaster recovery plans up to date.
0.143: Accumulated scheduled downtime in the last quarter.
3.6.3: LCG Deployment evaluation reports.
5.2.4. Tier-2 Hardware realization.
5.2.7 Quarterly reports received within 1 month of the end of the quarter.
6.2.11: Non-HEP applications tested on the GridPP Grid.
4/July/2005
Project Manager’s Report
D. Britton
Milestones
A total of 262 milestones defined; 54 (21%) have been completed in the first
20% of the project. There are 4 milestones shown as overdue:
0.37: Full Tier-1
Team in place.being prepared for last two posts.
Advertisements
Done at deployed
70% of sites
90%).
0.53: Accounting package
and(metric
R-GMA requires
configured
at GridPP sites.
2.4.1 Security: GridPP GACL parsing and policy.
In fact these are
done.
2.4.11 Security: Integration
of VOMS interface to GridSite lightweight groups.
4/July/2005
Project Manager’s Report
D. Britton
Change Forms
Five change forms have been enacted during this period as follows:
Ganga deliverable 3.2.1 and 3.2.2 have each been delayed by four months.
PhenoGrid deliverable 3.5.7 has been delayed by 6 months.
Interoperability milestones 6.2.1 and 6.2.2 have been delayed to Oct/05 and
Jan/06 respectively
4/July/2005
Project Manager’s Report
D. Britton
Risk Register
ID
R1
R2
R3
R4
R5
R6
R7
R8
R9
R10
R11
R12
R13
R14
R15
R16
R17
R18
R20
R22
R25
R26
R27
R28
R29
R30
R31
R32
R33
R35
R36
R37
R38
R39
R40
R41
R42
R43
R44
Alt-i-r
Name
Recruitment/retention difficulties
Sudden loss of key staff
Minimal Contingency
GridPP deliverables late
Sub-components not delivered to project
Non take-up of project results
Change in project scope
Bad publicity
External OS dependence
External middleware dependence
Lack of monitoring of staff
Withdrawal of an experiment
Lack of cooperation between Tier centres
Scalablity problems
Software maintainability problems
Technology shifts
Repitition of research
Lack of funding to meet LCG PH-1 goals
Conflicting software requirements
Hardware resources inadequate
Hardware procurement problems
LAN Bottlenecks
Tier-2 organisation fails
Experiment Requirements not met
SYSMAN effort inadequate
Firewalls interfere with Grid
Inablility to establish trust relationships
Security inadequate to operate Grid
Interoperability
Failure of international cooperation
e-Science and GridPP divergence
Institutes do not embrace Grid
Grid does not work as required
Delay of the LHC
Lack of future funding
Network backbone failure
Network backbone bottleneck
Network backbone upgrade delay
Inadequate User Support
4/July/2005
GridPP
Li Im Risk Li
2
1
3 2
6
2 2
3 1
2 3
3 2
4
3
6
2
2
1
1
3
1
1
2
1
2
1
LCG
MSN
Im Risk Li Im Risk
2
4
2 2
4
3
3
1 3
3
1 2
2
1 3
3
3
6
2 3
6
1
2
1 4
4
1
1
2 2
4
3
3
1 3
3
3
2
4
2
2
2
2
9
2
4
4
2
4
2
4 1
4
3 3
3 2
9
6
2
2
2
3
4
4
2 2
1 3
2 3
4
3
6
2 3
2 3
3 2
6
6
6
2 3
6
3 3
3 2
9
6
3 2
2 3
1 4
6
6
4
2 2
2 3
4
6
1 4
4
3
2 2
2 3
4
6
1 3
3 2
3 3
6
9
1
3
2
1
3
1
2
2
6
3 1
2
3
2
2
1 4
2 2
Apps
Pro. Grid
Li Im Risk Li Im Risk
2 2
4
2 2
4
1 3
3
1 4
4
4
6
4
6
3 2
3
3
3
3
2
4
3
3
3
9
6
3
6
4
6
6
3 3
2 3
9
6
1 3
3
0
2
1
1
1
4
4
4
Seven high risks identified:
R10-LCG and R10-Apps: External
middleware dependence.
R22-LCG, R22-Apps, R22-PRO:
Hardware resources inadequate.
R32-PRO: Security inadequate to
operate Grid.
3
6
2 3
6
3 3
9
4
2
4
4
R40-Apps: Lack of future
funding.
Project Manager’s Report
D. Britton
Outline
1. Project Maps
2. Resources
3. People and Roles
4. Tier-1 Hardware
4/July/2005
Project Manager’s Report
D. Britton
GridPP2 Financial Summary
Jun 2005
LCG-2
Travel
Mgr
Ops
£0.00
£0.49m
£171,911
Tier-1/A
Hardware
£0.81m
£0.95m
Total includes £273,988 carried
forward from GridPP1.
£2.89m
M/S/N
£2.76m
Tier-1/A
Operations
£2.49m
£2.87m
£2.92m
Applications
Tier-2
Operations
Category
Sub-Cat
LCG
Tier-1
Staff
Tier-1
Hardware
Tier-2
Staff
Tier-2
Hardware
Applications
Staff
N/M/S
Staff
Operations
Managers
Operations
Staff
Operations
Travel
Operations
Misc
GridPP2 Total
Total Available
Surplus (Deficit)
PPARC Agreed Profile
4/July/2005
Funds are fully allocated.
Posts iSY
13.5
38.2
19.0
48.6
19.0
14.5
3.4
2.0
49.9
42.9
9.9
4.9
71
194
FY04
FY05
FY06
FY07
£245,732 £908,052
£482,000 £216,000
£218,986 £779,854
£150,000
£49,000
£274,460 £1,034,946
£430,785 £903,401
£159,983 £318,666
£17,339 £138,621
£131,284 £272,000
£30,000
£40,000
£2,140,568 £4,660,540
£921,619
£801,000
£1,080,832
£27,000
£1,081,376
£963,025
£329,170
£150,823
£284,000
£40,000
£5,678,846
£410,135
£1,392,000
£611,653
£0
£483,221
£463,460
£141,085
£58,138
£119,000
£15,000
£3,693,692
£2,647,000 £4,712,000
£5,666,000
£2,977,000
Project Manager’s Report
Total Cost
£0
£2,485,538
£2,891,000
£2,691,325
£226,000
£2,874,003
£2,760,671
£948,904
£364,920
£806,284
£125,000
£16,173,646
£16,173,988
£343
D. Britton
- £0.2m
+ £0.5m
- £0.1m
GridPP2 Post Summary
Work Area
Application Interfaces
Middleware/Security/Networking
Tier-2
Tier-1
EGEE Infrastructure Support
Project Management Board
Operations
TOTAL
FTE
18.5
14.5
15
13.5
4
3.4
2.5
71.4
GridPP2 Funding
Total Posts
Unfilled
20
0
18
0
20
3
13.5
2
4
0
6
0
3
0
84.5
5
Note-1: Only short ½ FTE of effort at present.
Note-2: Advertisements under preparation.
4/July/2005
Project Manager’s Report
D. Britton
Note-1
Note-2
GridPP2 Effort Summary
Applications
MSN
Tier-1
Tier-2
TOTAL
Cumulative to end of
GridPP
EU
Other
104%
#DIV/0!
36%
93%
96%
35%
69%
#DIV/0!
55%
43%
96%
113%
86%
96%
53%
Of planned
4/July/2005
Project Manager’s Report
Of actual
GridPP and
EU effort.
05Q1
Total
137%
127%
106%
138%
135%
Of planned
GridPP and
EU effort.
D. Britton
Outline
1. Project Maps
2. Resources
3. People and Roles
4. Tier-1 Hardware
4/July/2005
Project Manager’s Report
D. Britton
People and Roles
DataBase is contained in the "All People" worksheet.
Click on the catagories below to view sub-lists.
Organisational
Applications
Middleware
Infrastructure
All People
ALICE
InfoMon
Tier-1
Birmingham
Bristol
GridPP Post Holders
ATLAS
Metadata
Tier-2
Brunel
CERN
CB - members
CMS
Networking
London Tier 2
Cambridge
CCLRC
PMB - members
LHCb
Security
NorthGrid
Durham
Edinburgh
DB - members
BaBar
Storage
ScotGrid
Glasgow
Imperial
UB - members
CDF
WLMS
SouthGrid
Lancaster
Liverpool
OC - members
D0
T2 Hardware Support
Manchester
Oxford
Tier-1 Board Members
Other Applications
T2 Middleware Support
PPARC
QMUL
Tier-2 Board Members
PhenoGrid
RHUL
Sheffield
Deployment Team
UKQCD
Sussex
Swansea
EGEE
Portal
Warwick
UCL
Dissemination
Institutions
If DataBase has been edited, click this button to update all lists:
4/July/2005
Project Manager’s Report
D. Britton
Outline
1. Project Maps
2. Resources
3. People and Roles
4. Tier-1 Hardware
4/July/2005
Project Manager’s Report
D. Britton
Tier-1 Hardware
Some work needs to be done updating v26b described at GridPP12:
•
Provisional 20% increase in Hardware budget needs to be added
•
ADS planning is currently being re-done with better input.
•
Delay of 2005 hardware purchase needs to be included.
4/July/2005
Project Manager’s Report
D. Britton
Conclusions
• GridPP2 is 20% complete.
• Need to limit our ambition and focus on what is
essential (as oppose to what would be nice).
“What happens when you
overload your ass… “
“… or “When neither a
carrot or a stick will work“
4/July/2005
Project Manager’s Report
D. Britton