E-2D Advanced Hawkeye Lessons Learned from Integrated Test (IT) Rick Quade Navy T&E 10 March 2010
Download ReportTranscript E-2D Advanced Hawkeye Lessons Learned from Integrated Test (IT) Rick Quade Navy T&E 10 March 2010
E-2D Advanced Hawkeye Lessons Learned from Integrated Test (IT) Rick Quade Navy T&E 10 March 2010 1 Agenda • • • • • Program Overview IT Challenges Implementation of IT IT Self Assessment Keys to Success 2 E-2D Advanced Hawkeye Program ACAT: ID M/S: MS B June 03, MS C May 09, IOT&E FY12, IOC FY15 Contractors: Northrop-Grumman as Total Weapon System Prime Lockheed-Martin as Radar Principal Subcontractor Flight Test Program Phases • SDD – 2 SDD Aircraft, ~2000 Flt Hrs • Apr 2007 • Pilot Production Verification – 3 Aircraft, ~800 Flt Hrs • June 2010 • IOT&E – 4 Aircraft, ~1000 Flt Hrs • FY12 E-2D Integrated Test Team (ITT) • 100+ engineers and project officers 3 E-2D Test Organization ISEET/VX-20 Integrated Test Team (ITT) Operational Test Coordinator AHE T&E IPT PMA-231, NGC COTF LEGEND Use of Test Site Specific Facilities or Services Operational Test Director VX-1 CFTD/GFTD Test Director Aircraft Coordinators A/C Maintenance & Quality Control SAMC, VX-20 LTE Aircrew (Pilots) Logistics/ Supply Safety Dept. DCMA, VX-20 Flight Operations SAMC,VX20 Air Vehicle Test Engineering* Mission System Test Engineering* Aircrew (WSOs & NFOs) Data Reduction/ Management Test Facilities Instrumentation Engineers & Techs Reliability & Maintainability Engineering Safety Officer * Including Aircrew Performing Test Planning and Data Reduction and Analysis Functions FCRA 4 Test Environmental Factors • E-2D complex weapon system with extensive amount of flight testing – Mission Systems - ~225 successful flights (SDD) – Air Vehicle - ~125 successful flights (SDD) – 25+ Test Plans (SDD) • Many moving parts (Staff, HW/SW, DRs, Management) • Large and diverse test team comprised of NAVAIR (5.1.1, 5.1.2, 5.1.6, VX-20, 5.2, 5.4, CSS), Northrop Grumman, Lockheed Martin, VX-1, COTF and others • Typical program and flight test challenges 5 E-2D IT Challenges • • • • • • • • DT, OT and Program Organizational Barriers “I’ve got a secret” Expectations Management Staffing/Turnover Spec Compliance vs Suitability Legacy vs Program of Record Weapon System Maturity Leveraging/Integrating DT/OT efforts IT touches all aspects of program execution. 6 E-2D IT Implementation • PMA embraced T&E role in program execution – Multiple 5.0 T&E Deep Dives of test program – Conducted an Independent T&E Review to identify test risks – Program unilaterally added an Operational Assessment (OA) • Focused on improving internal/external communications – Monthly meetings with VX-1 (OTA) – Weekly reports and metrics to stakeholders & leadership • Embraced early and robust OT participation – OA Report mitigation plans pre-coordinated – OT concerns included in update to CDD – OT part of program management team • E-2D ITT CONOPS implemented to document roles, responsibilities and procedures – Signed by NGC, PMA, DT (VX-20), OT(VX-1) and DCMA 7 E-2D IT Implementation (Continued) • Early and continuous participation by all stakeholders (DT, Cont and OT) on test DT planning and execution – Test planning working groups – Discrepancy reporting/NTAB Yellow Sheet Reviews – Technical Reviews • Integrated Test Planning & Execution – DT/OT Test Point Matrix for Pilot Production/IOT&E testing – OT Test Planning – coordinate with program, risk reduction – Integrated flight schedule w/OT crews • Efficient use T&E Infrastructure/Capability – Telemetry Trailer, targets, labs – Data/data analysis personnel used by DT and OT • Northrop-Grumman Support – Embraced early OT involvement and feedback – Willing to discuss and mitigate relevant OT issues 8 E-2D IT – Self Assessment • Contractor data augmenting IOT&E data – OA Report leveraged significant amount of data collected during DT • DT and OT personnel recognize each other in airport • OT personnel influence DT scenarios – OT part of planning process, common goal of leveraging “DT” flights to meet OT objectives • DT system operated by OT users – Monthly flt hr goals for OT team, DR verification • DT and OT sharing data in common format • OT confirms DT results – OA Report did not identify any new issues 9 E-2D Awards and Recognitions • CY2007 – NAWCAD Commander's Award for 2007 – VX-20 Test Team Award 2007 • CY2008 – NAWCAD Commander's Award for 2008 for Individual Effort for Mr. Pat Svatek – Society of Flight Test Engineers' International Flight Test Team of the Year 2008 (James S McDonnell Award) – Daedalian Weapons Systems Award: Colonel Franklin C. Wolfe Memorial Trophy – VX-20 Test Team Award 2008 • CY2009 – NAWCAD Commander's Award 2009 – Society of Flight Test Engineers’ 40th International Symposium Best of Symposium Award for E-2D ACAWS Team – European Flight Test Safety Award for 2009 – E-2/C-2 Shore Pilot of the Year – LT Greg Machi – E-2/C-2 Shore NFO of the Year – LCDR Matthew Tharp 10 E-2D IT Keys to Success • Set Expectations – Known roles & responsibilities, big picture awareness • Open Communication – Create forums for discussion, education and decision making – No secrets or surprises, transparency expedites issues resolution • Common Goals & Objectives – Deliver weapon system to war fighter with known performance • Robust Conflict Resolution Process – No one has to agree, resolve conflicts at lowest level possible • Demand Constructive-Tension/ Positive-Friction – Disagreements are expected, know when to move on • Embrace value of robust T&E program – Program leadership values T&E and solicits input – T&E’s job is to inform the PM and decision makers 11