First Results from Tracker 1 Cryostat Commissioning AFE/VLSB Firmware and Readout Cosmic Ray Setup Tracker Readout Software Trigger Timing Scan Alignment
Download
Report
Transcript First Results from Tracker 1 Cryostat Commissioning AFE/VLSB Firmware and Readout Cosmic Ray Setup Tracker Readout Software Trigger Timing Scan Alignment
First Results from Tracker 1
Cryostat Commissioning
AFE/VLSB Firmware and
Readout
Cosmic Ray Setup
Tracker Readout
Software
Trigger Timing Scan
Alignment
Light Yield
Next Steps
M.Ellis - VC113 - 17th July 2008
1
Cryostat Commissioning
Both cryostats cooled down very well and
reached a temperature that allows all 4
cassettes to operate at 9.0 Kelvin.
The lid heater alarms and VESDA smoke
detection system have been hooked up to a
relay that will kill the AFE power if any of
the three alarm.
An auto-dialler will call an expert (or the
MOM) if any of the above alarms occur, or
if either of the insulating vacua start to
degrade.
M.Ellis - VC113 - 17th July 2008
2
AFE / VLSB Firmware
New AFE and VLSB firmware
from Fermilab is being used
for the readout.
An additional VLSB is providing
an encoded clock signal that is
fanned out to all 8 AFE
boards.
The readout is operating
asynchronously, with the
trigger coincidence signal being
vetoed by the master VLSB to
only allow a trigger to be
produced in the correct live
M.Ellis - VC113 - 17th July 2008
windows.
3
Cosmic Ray Setup
The 25 waveguides were connected
and the cassettes made light tight.
At the moment there is a 2 inch
layer of lead under the tracker to
act as a momentum filter.
The coincidence of two trigger
scintillators (one above the tracker,
one underneath the tracker and a
layer of lead) provides the external
trigger (which is a bit noisy).
Some new trigger scintillators are
being prepared at Fermilab which
should increase the trigger rate and
the trigger efficiency.
M.Ellis - VC113 - 17th July 2008
4
Tracker Readout
At the moment we are using the
Excel/Visual Basic DAQ developed at
Fermilab.
Hideyuki is working on a Linux based
AFE initialisation code.
Once that is working, we will check
that the data taken looks the same
and start to move to a Linux based
AFE initialisation and DATE DAQ for
readout. M.Ellis - VC113 - 17th July 2008
5
Software
The decoding and calibration files have been
committed to G4MICE and the necessary
unpacking code for the current data format.
A new application – “R8CosmicTest” has been
added which reconstructs the data and
creates ROOT histograms and event display
files for viewing using HepRApp.
All plots in this talk can be reproduced by
checking out the most recent version.
M.Ellis - VC113 - 17th July 2008
6
Trigger Timing Scan
Need to get the delay between cosmic ray passage
and AFE trigger signal correct at the level of 1020 ns.
Scan over a range of delays, take data for a day
and find delay with maximum light yield.
M.Ellis - VC113 - 17th July 2008
7
Trigger Timing Scan - Results
Light Yield for each Station
Average Light Yield for All 5 Stations
Delay chosen: 862 ns
Filled square – station 1
Triangle up – station 2
Triangle down – station 3
Open circle – station 4
Open square – station 5
M.Ellis - VC113 - 17th July 2008
8
Alignment
The alignment started with the nominal
values from the tracker design for the
station spacing, central fibres, etc.
These were fed into G4MICE and
triplet residuals and tracking residuals
used to spot any misalignments or
inconsistencies.
M.Ellis - VC113 - 17th July 2008
9
Triplet Internal Residuals
Stations 1 – 4 have residuals centred
near 0 with no need for any alignment
M.Ellis - VC113 - 17th July 2008
10
Triplet Residuals – Station 5
Station 5 before adjusting the nominal values
Station 5 after adjusting plane X
M.Ellis - VC113 - 17th July 2008
11
Station Alignment
Will check station spacing with Coordinate
Measuring Machine (CMM) data, but for
now assume the spacing is exactly as
designed.
At high momentum (i.e. no MCS), expect
residuals to have an RMS of ~ 430 mm in
X and ~ 497 mm in Y.
M.Ellis - VC113 - 17th July 2008
12
Track Residuals
X – expect 430 mm, see 466 mm RMS
Y – expect ,497 mm, see 549 mm RMS
Implies misalignments of order 100 mm
TRD Spec for Tracker alignment: 70 mm
M.Ellis - VC113 - 17th July 2008
13
Light Yield
Light yield determined by plotting the
distribution for each plane and each station
(integrating over planes in a station) for
clusters that were included in a good track.
Some features (narrow peaks) in the plots
for individual planes/stations are due to
overflow of the ADC.
Due to variations in the gain of the
cassettes, these peaks move around as a
function of plane/station.
M.Ellis - VC113 - 17th July 2008
14
Light Yield – All Stations
Light Yield: ~ 11 PE
M.Ellis - VC113 - 17th July 2008
15
Next Steps
Add another layer of lead and continue
data taking at the optimum trigger
delay.
Use CMM data to update station
spacing and possibly transverse
positions.
Study light yield and efficiency for
each station and each plane, and if
sufficient statistics, as a function of
position on the plane.
M.Ellis - VC113 - 17th July 2008
16
Finally – 100 Events with 5 point Tracks:
M.Ellis - VC113 - 17th July 2008
17