Project Management Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–1

Download Report

Transcript Project Management Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall. 2–1

2

Project Management

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 1

Work Breakdown Structure

Relocation of St. John’s Hospital Organizing and Site Preparation Level 0 Physical Facilities and Infrastructure Level 1 Select administration staff Purchase and deliver equipment Site selection and survey Select medical equipment Construct hospital Develop information system Level 2 Prepare final construction plans Bring utilities to site Interview applicants for nursing and support staff

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

Install medical equipment Train nurses and support staff Figure 2.1

2 – 2

Diagramming the Network AON approach (Activity On Node)

S AON T U Activity Relationships S precedes T, which precedes U.

S T U S and T must be completed before U can be started. Figure 2.2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 3

Diagramming the Network

S T S AON T U U V Figure 2.2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

Activity Relationships T and U cannot begin until S has been completed.

U and V can’t begin until both S and T have been completed. 2 – 4

Diagramming the Network

AON S T U V S T U Figure 2.2

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

V Activity Relationships U cannot begin until both S and T have been completed; V cannot begin until T has been completed.

T and U cannot begin until S has been completed and V cannot begin until both T and U have been completed.

2 – 5

Network Diagram

S = 36 A 0 12 S = 2 S = 41 S = 0 Start S = 2 S = 2 S = 0 S = 0 S = 0 S = 0 Figure 2.4

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

S = 26 Finish 2 – 6

Project Schedule

The earliest start time (ES) for an activity is the latest earliest finish time of any preceding activities

The earliest finish time (EF) is the earliest start time plus its estimated duration

The latest finish time (LF) for an activity is the latest start time of any preceding activities

The latest start time (LS) is the latest finish time minus its estimated duration

For simplicity, all projects start at time zero.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 7

Activity Slack

Activity slack is the maximum length of time an activity can be delayed without delaying the entire project

Activities on the critical path have zero slack

Activity slack can be calculated in two ways S = LS – ES or S = LF – EF

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 8

Calculation of Slack Time

Slack Time = LF – EF EF = summing Expected Time from left to right

If two or more activities precede an activity, choose the largest EF of these activities LF = summing Expected Time from right to left

 

Set LF equals to EF for the last activity If two or more activities precede an activity, choose the smallest LF of these activities

Refers to the time in which an activity can be completed without delaying the project

 

Tasks on the critical path has Slack Time = 0 LS = LF - t; ES = EF - t 2 – 9

Gantt Chart

Figure 2.5

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 10

Comparison of Gantt Charts and Network Diagrams

 Gantt Charts  Visually shows duration of tasks  Visually shows time overlap between tasks  Visually shows slack time  Network Diagrams  Visually shows dependencies between tasks  Visually shows which tasks can be done in parallel  Shows slack time by data in rectangles

2 – 11

Cost-Time Relationships

8000 — 7000 — 6000 — 5200 5000 — 4000 — Crash cost (CC) Linear cost assumption Estimated costs for a 2-week reduction, from 10 weeks to 8 weeks 3000 — Normal cost (NC) 0 — | 5 | 6 | 7 8 | 9 | 10 | 11 (Crash time) (Normal time) Time (weeks) Figure 2.6

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 12

Statistical Analysis

Area under curve between a and b is 99.74%

a m

Mean Time Beta distribution

b

Figure 2.7

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

a

3 σ 3 σ

m

Mean Time Normal distribution

b

2 – 13

Statistical Analysis

The mean of the beta distribution can be estimated by

t e

= a + 4m + b 6

The variance of the beta distribution for each activity is 2 σ 2 =

b

a 6

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 14

Analyzing Probabilities:

Because the central limit theorem can be applied, the mean of the distribution is the earliest expected finish time for the project

T E

Expected activity times = = Mean of normal distribution

Because the activity times are independent σ 2 =

(Variances of activities on the critical path)

Using the z-transformation z =

T

T

E

σ 2 where T = due date for the project

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall.

2 – 15