Standard Missile 6 Cooperative Earned Value Program Management Kirk Johnson (IWS 3A SM PM) Tim Lardy (RMS SM6 PM) 1 June 2009 Copyright © 2009 Raytheon Company.
Download ReportTranscript Standard Missile 6 Cooperative Earned Value Program Management Kirk Johnson (IWS 3A SM PM) Tim Lardy (RMS SM6 PM) 1 June 2009 Copyright © 2009 Raytheon Company.
Standard Missile 6 Cooperative Earned Value Program Management Kirk Johnson (IWS 3A SM PM) Tim Lardy (RMS SM6 PM) 1 June 2009 Copyright © 2009 Raytheon Company. All rights reserved. Customer Success Is Our Mission is a registered trademark of Raytheon Company. SM-6 Program Summary Design Program Plan • Milestone B completed 15 Jun ‘04 Guidance Section Elements AMRAAM Electronics Stack Transmitter Battery/ECU Power STANDARD Interface Computer Stable Platform Plate 3A Two Way Data Link GPS / IMU Growth Allocation New SM Size Antenna, Mission Computer Modify FRU For Semi-active • Contract Award 03 Sep ‘04 • SRR/SFR Dec ‘04 – SFR Completed 2 Months Early • IBR Feb 05 • PDR/Gate 7: Jun ‘05 – Completed 2 Months Early Common Common Factory Factory For For AMRAAM -6 SM AMRAAM & & SMSM-6 Guidance Guidance Sections Sections • DRR/Gate 8: Mar ‘06 – Completed 4 Months Early • WSMR Testing: ‘07-’09 – Direct Hit on first 2 guided flights • DT/OT FY10 STANDARD Missile Propulsion Stack, Airframe, Warhead/TDD, Radome • IOC planned in FY10 Capability • Provides Area Defense • Capable of Over-The-Horizon Engagements • Enabler for Integrated Fire Control • Capable against Overland Cruise Missile Non-technical data per ITAR 120.10(5) Overview – May ‘08 • • • • 80% Complete ITD CPI: .98, ITD SPI: 0.99 GTV 1 June 08 – Direct Hit GTV 2 Sept 08 – Direct Hit CTV 29 Jan 09 – Did not launch Retest Aug 09 • GTV 3 scheduled for Nov 09 • First DT/OT missile hardware in work for delivery this fall 11/6/2015 Page 2 Acquisition/Cultural Changes Its Not All Rocket Science LEGACY ACQUISITION MODEL Detailed Statement of Work Many Specifications Separate Seeker Developments Subjective Award Fee Separate Factories Customer/Contractor Relationship STREAMLINED ACQUISITION MODEL 5 Page Statement of Objectives Single Msl Performance Specification Common Active Seeker Family Results-Oriented Objective Award Fee Common Factories, Volume Production ToPP- Total Performance Partnering Acquisition Philosophy Must Be As Innovative As Technical Solution Non-technical data per ITAR 120.10(5) 11/6/2015 Page 3 Acquisition/Cultural Changes Its Not All Rocket Science Culture / Communication – High Priority From the Beginning – Develop a Consistent Focused Team Intent on Mission of Delivering Capability – Small, Engaged, Informed Govt Teaming inside Contractor IPTs – Counterparts Identified and Maintained throughout phase – Web Based Information Sharing System (WISDM) – Combined Contractor/Government Reviews Business, technical, programmatic – Arbinger Training – Raytheon Six Sigma New Culture Requires Partnership Between Team Members Non-technical data per ITAR 120.10(5) 11/6/2015 Page 4 Cooperative Successes Government and contractor teams participated in Alpha contracting process to generate technical scope, schedule & cost baseline for the program – Required alignment of technical objectives, schedule and budget realities – Scope agreements hammered out early in the baselining process – Schedule development took into account the possibility of test failures and resulted in an executable program plan Successful IBR in Feb 2005 – Baseline is still in effect today (no re-baselines since contract start) RMS provides an EV “quick look” to USN cost team 10 days after month end to facilitate timely & objective analysis – Data provided in USN preferred WINSIGHT format Government (USN and DCMA) participates in RMS monthly Earned Value reviews – Diligent participation by execution team and management SM6 EVMS DCMA COE Audit Results – Kudos received from both DCMA audit teams on SM6 use of Earned Value – SM6 management team received an RMS excellence award for performance during 2006 EV audit Cooperation & Management Focus Drove Success Non-technical data per ITAR 120.10(5) 11/6/2015 Page 5 Program EVM “Early Warning”Benefits • Principle benefit of EVM during program execution phase is providing an early warning for future problems – Generated “Watch Account” metric to be able to track Control Account Performance to EAC CAM’s were spending to EAC but it was not clear if they were actually achieving the performance necessary to meet EAC New metric tracks actual performance to promised performance – Allocated MR to antenna supplier to build additional tooling to improve delivery schedule and mitigate risk #183 Antenna delivery schedule from supplier was predicted to drive build of POM GS’s Supplier indicated that additional tooling would improve cycle times and reduce schedule pressure Antennas are no longer the critical path for GS build – MBIT Performance metrics (cost/schedule variance, EAC, TCPI, etc.) were showing that the team was starting to struggle Program worked with functional department to bring in new resources and make surgical personnel changes Team is back on track, performance has improved & product will be delivered in time to support production Non-technical data per ITAR 120.10(5) 11/6/2015 Page 6 SM-6 Managing Using EV Daily Daily Standup Meetings Status of Pacing Items (Chaired by PM and CE) Weekly Schedule Updates Critical Path Reviews (Chaired by PM and Planner) Bi-Monthly Schedule/Critical Path Reviews (Chaired by PM and Planner) Monthly Mangement Reviews Risk/Opportunity Reviews (Chaired by PM) (Chaired by CE) Non-technical data per ITAR 120.10(5) 11/6/2015 Page 7 SM-6 Monthly Management Metrics Sampling Top Ten Cost/Schedule Drivers -256. 7 -335. 7 0.000 -335. 7 91. 13 C ohen Am y -112. 8 -252. 0 0.709 -252. 0 33. 16 22, 445. 3 21, 686. 1 MK 698 GMTS Upg R andall R obert H 146.6 -233. 1 5.964 -233. 1 82. 06 3,356.3 5 A2C3N MK 45 F ac t ory Graf f am Ray 10. 3 -186. 7 1.060 -186. 7 57. 01 A4A23M1 Spac e Stabilize Albrecht Ken 3,726.7 -500.04,289.4 6 10. 7 -138. 9 1.201 -138. 9 94. 09 1,158.2 1,164.8 7 A7A2A GTV1 I nt egrat io Adam s , Charlie 28. 4 -137. 4 1.453 -137. 4 23. 65 1,811.4 1,678.5 Antenna Prot ot y Albrecht Ken -67.4 -117. 6 0.801 -117. 6 84. 98 -400.02,897.9 2,487.0 Target Detec tio Abraham , Lisa -89.3 -103. 7 0.162 -103. 7 56. 78 3,428.3 3,742.2 10 A4A42M1 Sem i-Ac tiv e F RU Albrecht Ken -0. 8 -85.2 0.942 -85.2 62. 99 890.2 1,091.8 11 G1D 2 AU R BIT Test er R andall R obert H 100.8 -54.6 1.165 -54.6 58. 40 4,945.1 2,570.4 2,516.3 10. 02 2,556.5 2,409.6 84. 98 2,487.0 0.672 35. 48 7,989.6 -42.9 -42.9 1.05 1 6000 1.200 1.100 0.95 5000 0.9 Jan-06 Feb-06 Mar-06 Apr-06 May-06 Jun-06 Jul-06 Aug-06 Sep-06 Oct-06 EAC Watch Accounts 0.800 DD 45 Fa cto ry Sh ro ud ) DD e (T Pro to ty pe 20 3400 3337 3325 0.700 3000 0.600 10 2 3300 0 3 3268 3200 -10 0.500 2000 0.400 0.300 Simulation, Algorithms & Performance - C1F1 1000 0.200 3100 -20 -22 Now looking as tasks that did not meet their baseline dates. 3000 -30 -35 2900 -40 -42 -50 2800 -50 -49 ITD Actuals/ITD Forecast $1,400.0 9,000.0 $1,200.0 $1,000.0 $833.8 6,000.0 $800.0 $720.7 $680.4 $600.0 $558.6 3,000.0 Total LRE $14,806.7K Q109EAC $15,017.3K 3-Mth CPI = 2.70 TCPI 1Q09eac 1.08 0.0 CPI B/L Plan 1.08 1.09 1.09 May-09 Jun-09 1.08 1.03 1.01 .98 3738.8 3634.3 3461.3 Cum Actual Delta to Baseline Plan 9 09 ul- 22 -A ug -0 9 Future Completes 25 -J Late and Critical to GTV-3 Critical Paths 1-5 to CPLI (FCA): 1.12 Program Milestone - Flight Test (ADSAM4/CTV-1a) 4/25/09 2008 December 2009 January February March April May June July August September (14517) G/S - Build G/S (ADSAM4/CTV-1a) (14518) G/S - Deliver G/S to Integration (ADSAM4/CTV-1a) (14269) G/S - Integrate (ADSAM4/CTV-1a) (14519) G/S - Vibe/Skin/Leak/Fill/Weight CG (ADSAM4/CTV-1 (15424) SIT - AUR Kit Complete (G/S, TDD, PCT, IFTS, ET, (15425) SIT - Assemble Flight Round (ADSAM4/CTV-1a) (21651) SIT - Test Readiness Review (TRR) ADSAM4/CTV-1a) (15428) SIT - ADSAM4/CTV-1a Flight Round Test EAT - Tucso (21652) SIT - ADSAM4/CTV-1a Flight Round EAT Data Review (15430) SIT - Consent to Ship (Gate 9) from Tucson to WSM (15431) SIT - All ADSAM4/CTV-1a AUR Kit Items Received at (15432) SIT - Assemble ADSAM4/CTV-1a Flight Round with or (21653) SIT - TRR for ADSAM4/CTV-1a Flight Round I and T (15436) SIT - ADSAM4/CTV-1a Flight Round I and T (WSMR) (20142) SIT - ADSAM4/CTV-1a Dress Rehearsal and Flight Te (15438) SIT - MRR (ADSAM4/CTV-1a) (15372) SIT - CTV-1 Flight Test $200.0 Jul-09 1.10 3919.9 Forecast Finish -0 0.614 0.618 0.646 0.571 0.409 0.517 0.462 0.527 0.548 0.385 0.569 0.486 9 Monthly Hit Index un BEI -80 23 -M 5201 9 5129 9 5057 pr -0 4992 25 -A 4930 9 4837 -0 4759 ar -0 4672 28 -M 4579 eb 4474 21 -F 4392 9 4261 0.983 0.970 0.972 0.968 0.961 0.957 0.958 0.962 0.970 0.974 0.981 0.983 an -0 Cum Sched. to Complete by Status Date -70 2500 24 -J 5113 8 5032 -0 4927 ec 4841 27 -D 4744 8 4635 -0 4552 ov 4492 22 -N 4433 08 4347 ct- 4262 2600 $0.0 Jan-09 ITD Actuals Feb-09 ITD Actuals Mar-09 ITD Actuals Apr-09 ITD Actuals TCPI $400.0 4189 Cum Completed by Status Date 0.000 25 -O $1,600.0 11,489.9 Expected - Achieved Performance Delta $1,800.0 12,000.0 Dec May Nov 08 Jan 09 Feb 09 Mar 09 Apr 09 Jun 09 Jul 09 Aug 09 Sep 09 Oct 09 08 09 -60 The average number of tasks completed per month is 59 and 15 tasks were completed this month -64 0 BCWR 2700 27 -J 0.100 $2,000.0 ay -0 August '10 Completion 15,000.0 Delta to Baseline Plan/Future Completes 4000 Tasks Completed Dec-05 GTV-3 Tasks / All Teams 3500 0.8 Nov-05 Critical Path 1.000 0.900 Task Finishes 0.85 Material ITD CPI Labor ITD CPI Material ITD SPI Labor ITD SPI ev ic pm 2,897.9 7,755.6 A4 A2 3M Schedule EV Baseline Execution Indices (BEI) as of April 09 K 0.801 -117. 6 -64.3 A2 DT -67.4 -117. 6 A2 C3 R-M De ve lo F ritz Bill U 3,853.4 Albrecht Ken D 3,146.5 FR 94. 02 -40.2 on 0.198 -40.2 e -69.1 tiv i-A c 3,742.2 Sm it h Rex 1Se m 3,428.3 A4 A4 2M 56. 78 en t 0.0 686. 1 33. 16 22, 445. 3 21, 0.162 -103. 7 Pro to ty pe 0.709 -252. 0 -89.3 -103. 7 a rg et De te cti -112. 8 -252. 0 en t A4 B1 4-T Antenna Prot ot y BI T (N RE) 38. 00 -32.2 Te st De ve lo pm A4A21MN A4C21N -45.2 0.000 NAn te nn a 10 0.000 -32.2 C ohen Am y A4 A2 1M 9 Nov-06 Month -45.2 -119. 7 C ohen Am y Badillo I v eli se Abraham , Lisa Fa cto ry Miss ion C om pute -128. 9 1,699.7 Pro to ty pe A4A5AH 1,883.3-100.0 2,062.6 m 8 1,541.5 46. 17 Pla tfo r Target Detec tio 90. 82 -17.0 bil ize d C SCI D ev elopm en A4B14 0.0 0.108 Sta Miss ile Lev el E A4B11 7 0.000 -17.0 Ac ce pta nc e C SCI I nt egrat io A7A7 6 0.0 -137. 8 & A4B15 5 LRE -229. 9 Up gra de 4 45 TS Graf f am Ray K Parry , Jam es TDD SH ROU D 9,044.1 10, 480. 3 en t Aerody nam ic Ana A2D 91. 13 pm C 1F 2 3 0.000 -335. 7 ev e lo 2 4,909.1 -200.0 -256. 7 -335. 7 In te g ra tio n Oct -06 BAC 1 Sep-06 H unter Scot t % Comp A7 A2 A-G TV Aug-06 SW ES/C IL/ HI L De CvCur G M Jul-06 C 1G2 SpiCur SC ID Jun-06 1 CvCur K May-06 SvCurCvCur SvCur -300.0 1-M Apr-06 CAM $$ A4A21MN A4B14 Desc Oct-06 Sep-06 Aug-06 2,997.2 G 1D Mar-06 LRE -600.0 IL Jan-06 1.1 Feb-06 BAC 9,044.1 10, 480. 3 /H 0.88 % Comp IL 1.15 0.92 CvCur 8 WBS ITD LABOR and MATERIAL CPI/SPI SpiCur /C 0.96 CvCur 9 1 SPI SvCurCvCur SvCur A4 B1 1-C CPI H unter Scot t C SCI D ev elopm en G1D 1 W ES Actuals 1.04 SW ES/C IL/ HI L De A4B11 3 C1 G 2-S 1.08 CAM C 1G2 2 A2 C3 N-M WBS Top 10 CM Cost Drivers Desc 1 1Sp ac e CPI/SPI Trend 1.12 69 8 CPI/SPI Trend Data 8/20 Program Milestone - Flight Test (ADSAM4/CTV-1a) 8/28 ITD Actuals BCWP - (Actuals * TCPIeac) LRE * TCPIeac Achieved Perf ITD LRE 1st Qtr '09 EAC (12860) AUR - Assemble IFTS (ADSAM4/CTV-1a) (12861) AUR - IFTS Delivered (ADSAM4/CTV-1a) (11373) G/S - SE Integration - ADSAM4/CTV-1a (21654) SIT - ADSAM4/CTV-1a Flight Round I and T Data Rev (20143) SIT - ADSAM4/CTV-1a Permit to Ship (PTS) (15437) SIT - MCP (ADSAM4/CTV-1a) (20141) SIT - ADSAM4/CTV-1a WSMR DS/Range Intg. (IOM-2.2b Path 1 6d Non-technical data per ITAR 120.10(5) Path 2 7d Path 3 8d Path 4 8d Path 5 14 d 11/6/2015 Progress Risk Page 8 Summary Diligent application of management processes (EV) produce significant benefits to the war fighter – Stable technical baseline - no scope creep – Stable funding requirements – Predictable Performance – All major program milestones met on time – 2 guided flights, 2 direct hits On Time, On Budget Delivery of Warfighter Capability 11/6/2015 Non-technical data per ITAR 120.10(5) Page 9 Non-technical data per ITAR 120.10(5) 11/6/2015 Page 10 Non-technical data per ITAR 120.10(5) 11/6/2015 Page 11