Application of Energy Storage on the AEP Distribution System Presented by: John Mark Neal WV IEEE Section Meeting February 2, 2010 Presentation Outline • AEP/APCo –

Download Report

Transcript Application of Energy Storage on the AEP Distribution System Presented by: John Mark Neal WV IEEE Section Meeting February 2, 2010 Presentation Outline • AEP/APCo –

Slide 1

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 2

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 3

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 4

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 5

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 6

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 7

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 8

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 9

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 10

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 11

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 12

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 13

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 14

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 15

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 16

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 17

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 18

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 19

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 20

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 21

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 22

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 23

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 24

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 25

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 26

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 27

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 28

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29


Slide 29

Application of Energy Storage
on the AEP Distribution System
Presented by: John Mark Neal
WV IEEE Section Meeting
February 2, 2010

Presentation Outline

• AEP/APCo – Who we are
• Evaluating Energy Storage Opportunities
• Applying Energy Storage on the Distribution Grid
• Moving Forward
• Q&A

2

AEP Overview
• 5.2 Million customers
• 11 States
• 39,000 MW Generation
• 38,953 miles Transmission
• 212,781 miles Distribution
• 20,861 Employees

3

APCo Overview
• 1.05 Million customers
• 3 States
• 8,018 MW Generation
• 5,360 miles Transmission
• 47,981 miles Distribution
• 4,252 Employees

4

Utilities’ Interest in Energy Storage


Participation of utilities in Electricity Storage Association (ESA) , the most
widely recognized trade association on energy storage, has significantly
increased since 2000



EPRI has established an Energy Storage Program that has active
participation from member utilities



DOE ‘s Energy Storage program is paying more attention and participating
in large-scale utility application projects. Utilities are invited to participate
more in drafting and interpreting energy policy act



The dialogue between suppliers of energy storage devices and utilities
has significantly increased over the last five years



Over the last 12 months, there have been over 5 different energy storage
seminars and panel discussions with increased participation by utilities
(there used to be only one in 2000 with little utility participation)

5

Challenges to Deployment of Energy Storage in Utilities
Despite a clear increase in utilities’ interest in energy storage, deployment of
storage has been relatively slow due to several factors including:


High cost of new storage technologies discourages utilities to use storage
for improved service reliability and security for customers without some
incentives or assurance that its cost will be shared by customers



Storage benefits are very diverse impacting both customers and utilities.
Even within utilities, storage benefits are spread widely over different
businesses units from generation to distribution with independent budgetary
responsibilities



Separation of different utility businesses (distribution, transmission,
generation, energy trading, etc.) makes it hard for any one of these
businesses to justify the total cost of energy storage for only the partial
values that benefit that particular business unit.

6

Some Immediately Realizable Benefits of Energy Storage
A Quick solution to Reliability and Capital Deferral:
1. Provide contingency power to single-source loads
2. Maintain service during system repairs
3. Defer Investment

Maintenance

Future Line

Improved Service Reliability
7

Energy Storage Benefits

Benefits

Short -Term

Long -Term

Upgrade
Deferral

More Time for Service
Restoration

Improved Service
Reliability
Improved
System Control
Base Loading
Assets

Ancillary
Services

Enhance DG
Penetration

Displacing
Peak Energy Costs with
off-peak Costs

Improved Service Reliability is achievable both Short-Term and Long-Term
8

Other Benefits of Energy Storage

• Asset Optimization - Demand reduction on all utility assets in
Generation, Transmission and Distribution

• Renewables - Time Shift and Capacity Firming for renewable
energy sources like wind and solar

• Distributed Generation - Dispatchable Energy Buffer between utility
and customer-owned generation

Energy Storage Improves Reliability Today and Tomorrow
9

Storage Options for Utility Applications
• 1-10 MW, 4-8 hour storage systems for DG

• After reviewing all feasible technologies, AEP selected
Sodium Sulfur (NAS) battery for this application
• NAS strengths:
Commercial availability
Cost
Favorable field experience

Compactness
Modularity
Transportability

10

AEP Vision on Future Utilities

AEP Believes that Distributed Energy Storage will be a
Strategic Component in the Future Grid of the United States

Transmission
& Distribution

Transmission
Substation
Commercial

Residential

Distribution
Substation

Gensets
Gensets,, Solar, FC, LM
Industrial

Gensets
, Solar,
Fuel
Cells
(FC),
Gensets, Solar,
Fuel
Cells
(FC),
Load Management (LM)
Gensets
Gensets,, FC, LM

11

What is a NAS Battery?

–Nominal AC capacity: 50kW, 360 or 430kWh (320 or 384 cells)
–L x W x H = 2.3 x 1.7 x 0.7 = 2.9 m3

290-360 ºC

–3500 kg;

NAS has liquid electrodes and solid electrolyte
12

Is NAS Safe?

Module Firing Test

Module Crush Test

Module Drop Test

15 Years – No Accidents
Cell Burning Test

Designed and packaged to be safe
13

NaS Battery Installation – Environmental Issues


These batteries contain no CERCLA Hazardous Substances or EPCRA Extremely
Hazardous Substances (with the exception of sodium, which if released, has an
RQ of 10 pounds)



These batteries meet the OSHA "article" exemption, therefore an MSDS is not
required (however, we have created one that is very useful)



Since an OSHA MSDS is not required for the battery, they are not reportable under
SARA Tier II . However, since this is a groundbreaking activity, we will inform the
LEPC, SERC and local Fire Departments of their presence, even though it is not
"required".



The creation of a hazard communication plan would be a Best Management
Practice for us to follow. This hazard communication plan will include emergency
response information and emergency contact information and will always be
available to the operators.



There are no environmental operating permits required for the operation of these
installations



The only environmental regulations that are imposed upon these batteries are
those that are to be followed during transportation of the batteries and during the
disposal and / or recycling of the batteries.

14

Is it Safe to Deploy NAS in the Community ?
Japan’s 15 year experience

Integrated into
Residential
Neighborhood

Indoor
Applications
15

AEP’s First Commercial Energy Storage System






Charleston, WV
1.2 MW, 7.2 MWh
Operational since June 26th 2006
Deferring building a new substation

46 kV
bus
46kV/12kV
Transformer
12/16/20
MVA

12 kV Tyler Mountain Feeder
bus North Charleston Feeder
Voltage
Regulator

West Washington Feeder

16

Load Leveling – Summer 2007

17

AEP Substation-Scale Storages – 11MW, 75MWh
1 MW, 7.2 MWh installed in 2006

• Deferred substation upgrades
3 x2MW,14.4 MWH installed in 2008

• Demonstrated “Islanding”
4MW, 25MWh substation will be on-line in 2010

The New “Islanding” feature is Partially Funded by DOE/Sandia
18

One-Line
Milton Station

138kV

Approx. 4 miles

Target Site Area

19

Dynamic Islanding – Backup Power
This First Community-Scale Backup Power with NAS Battery is Partially Funded by DOE/Sandia

20

Live Islanding Test Information








Test Site :
Test Date:
Island Size:
Time to island customers:
Power Outage Duration:
Time to Exit Island:
Average Island Load:

Balls Gap, Milton, WV
July 8, 2009
700 customers
0.5 to 2 min.
28 min.
6 sec. (not Synchronized)
0.8 MW

21

Islanding Data – Battery Load & Energy
Battery
Load
(kW)

Islanding period = 28 min

SOC= 100%
Stored
Energy
MWh
SOC= 97%

22

Islanding Opportunities


September 8, 2009
Breaker interruption at Milton Station
No island established by system
Exposed flaw in design – required addition of a new device



December 19, 2009
Multiple faults and interruptions on Balls Gap feeder
Partial island established by system
25 customers served by DESS for two days



December 25, 2009
Single Phase hydraulic recloser interrupted on Balls Gap feeder
No island established by system
Battery unavailability may be reason – data still being analyzed
Learning operational nuances that each new event brings

23

Community Energy Storage (CES)
CES is a small distributed energy storage unit connected to
the secondary of transformers serving a few houses or
small commercial loads

• Uses New or Used PHEV- EV batteries
• Offers All Values of Substation
Batteries when aggregated,

• Offers Backup Power to customers
• Buffers Customer Renewable
Generation

• Makes PHEV Charging Time a less
critical issue
24

CES – A Virtual Substation Battery
CES is Operated as a Fleet offering a Multi-MW, Multi-hour Storage

Grid Benefits:

Local Benefits:

4) Load Leveling at substation level
5) Power Factor Correction
6) Ancillary services

1) Backup power
2) Voltage correction
3) Renewable Integration
Integration
Platform

Utility Dispatch
Center /SCADA

CES Control Hub

Communication &
Control Layout for
CES

Substation

CES

CES

CES

CES

Power Lines
Communication and Control Links

25

Advantages of CES to Substation Batteries
While CES is, Functionally, a Multi-MW, Multi-hour
Substation Battery, It has some Inherent Advantages:
1.

More reliable Backup Power to customers (closer)

2.

More Effective in providing Voltage Support (distributed)

3.

More likely to be a standardized commodity (low cost)

4.

More Efficient in buffering customer renewable sources

5.

More synergy with Electric Vehicle batteries (competition)

6.

Easier installation and maintenance (240 V)

7.

Unit outage is less critical to the grid (smaller)

8.

Lower resistive loss in wires (closer to customer)

9.

A better fit into the Smart Grids & MicroGrids

26

Migratory Path of Utility Energy Storage

– in AEP

Graphics adapted from an EPRI Presentation by Joe Hughes

Large Central Units
Substation Batteries

This Migration Trend is Driven by
Popularity of Customer-Owned Distributed Resources
and Customers’ demand for higher service quality

Storage at Grid Edge

27

AEP’s View of Energy Storage Value

765 kV

345 kV

138 kV

69 kV

4 to 34 kV

NAS
Pumped Hydro

(Substation)

(Central)

480 V

120/240 V

CES
(Community)

Storage
Value

Devaluators:
 Limited Value to Customer
 High Security Risk
 Less effective in removing Grid Congestions

Central Units

Devaluators:
 Aesthetics

Distributed Units
28

Wrap Up

Questions?

29