Scheduled FY07 Dredging Work in Baltimore District

Hopper Dredge Maintenance Dredging Atlantic Coast of Maryland, MD & DE Award Apr 13, 06 Baltimore Harbor & Channels, VA - Cape Henry/York Spit FY06 SEP OCT NOV 850 KCY Sea Turtles DEC JAN FEB FY07 MAR APR MAY JUN 400 KCY JUL AUG SEP Tourism FY08 OCT Sea Turtles - Screens and Observers Page 1 of 1

PROJECT: Atlantic Coast of MD TYPE WORK: Renourishment QUANTITY: 800,000 cy TYPE OF MATERIAL: Sand BORROW AREA: 9 NOURISHMENT AREAS: 33 rd Street and north of 60 th Street DISTANCE FROM BORROW TO BEACH: 3-7 Miles TYPE OF EQUIPMENT: Hopper SMALL BUSINESS SET ASIDE: No LAST NOURISHED: 2002 ENVIRONMENTAL WINDOW: Sep 7 – Jun 30 REASON FOR WINDOW: Tourism ADVERTISING: Feb 28, 2006 BID OPENING: Mar 31, 2006 AWARD: Apr 13, 2006 CONTRACT: $6,674,769.25

CONTRACTOR: Weeks Marine

Ocean City, Maryland, Looking North from Ocean City Inlet

Ocean City, Maryland, Looking North

Erosion at 70

th

– 79

th

Street

Atlantic Coast of Maryland Renourishment

PROJECT: Baltimore Harbor & Channels, VA - Cape Henry & York Spit Channels TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 1,000 and 800 Feet LENGTH: 3 and 18 Miles QUANTITY: 400,000 cy TYPE OF MATERIAL: Sand PLACEMENT AREAS: Dam Neck Ocean and Wolf Trap Alternate DIST. TO PLACE. AREA: 7 Mi TYPE OF EQUIPMENT: Hopper SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2006/2004 ENVIRONMENTAL WINDOW: Dec 1 – Mar 31 REASON FOR WINDOW: Sea Turtles FY 07 FUNDING: $1,500,000 ADVERTISING DATE: Dec 06 BID OPENING DATE: Jan 07 AWARD DATE: Jan 07

Scheduled FY07 Dredging Work in Baltimore District

Hydraulic Pipeline Dredge Maintenance Dredging Wicomico River, MD Awarded July 25, 2006 Knapps Narrows, MD Awarded Sep 29, 2006 FY06 SEP OCT Oysters Oysters NOV DEC 99 KCY 43 KCY JAN FEB Oysters FY07 MAR APR MAY Anadromous Fish JUN Tilghman Island Harbor, MD Awarded Sep 29, 2006 Oysters 11 KCY Oysters Poplar Island, MD 900 KCY JUL AUG SEP FY08 OCT Oysters Oysters Oysters Page 1 of 1

PROJECT: Wicomico River, MD TYPE WORK: Maintenance DEPTH: 14 Ft.

WIDTH: 150 Ft.

LENGTH: 10 miles.

QUANTITY: 99,000 c.y.

TYPE OF MATERIAL: Silt/Clay PLACEMENT AREA: Upland DISTANCE TO PLACEMENT AREA: 1-2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 2005, 2000, 1998 ENVIRONMENTAL WINDOW: June 16 – February 14 REASON FOR WINDOW: Anadromous fish spawning FY 07 FUNDING: $800,000 ADVERTISING DATE: May 5, 2006 BID OPENING DATE: June 13, 2006 AWARD DATE: July 25, 2006 CONTRACT: $368,750 (Base only) $1,444,271 (Options) CONTRACTOR: Cottrell Contracting Corp.

PROJECT: Knapps Narrows, MD TYPE WORK: Maintenance DEPTH: 9 Ft.

WIDTH: 75 Ft.

LENGTH: 9,000 Ft.

QUANTITY: 43,000 c.y.

TYPE OF MATERIAL: Sand/Silt/Clay PLACEMENT AREA: Wetland Creation, Shoreline Stabilization DISTANCE TO PLACEMENT AREA: 1-2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 2000 ENVIRONMENTAL WINDOW: October1 December 15, March 15 - June 1 REASON FOR WINDOW: Oysters REQUEST FOR PROPOSAL: Sep 7, 2006 PROPOSAL DUE: Sep 20, 2006 AWARD: Sep 29, 2006 CONTRACT: $850,000 CONTRACTOR: Coleman Construction

Placement Site Knapps Narrows

2000 Shoreline Placement Site Knapps Narrows West End

PROJECT: Tilghman Island Harbor, MD TYPE WORK: Maintenance DEPTH: 6 Ft.

WIDTH: 60 Ft., Basin 500 x 200 Ft.

LENGTH: 2,080 Ft.

QUANTITY: 11,000 c.y.

TYPE OF MATERIAL: Silts/clay/sand PLACEMENT AREA: Wetland Creation, Shoreline Stabilization DISTANCE TO PLACEMENT AREA: 2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: Yes LAST DREDGED: 1996 ENVIRONMENTAL WINDOW: October 1 - June 1 REASON FOR WINDOW: Oysters FY 07 FUNDING: $0 REQUEST FOR PROPOSAL: Sep 7, 2006 PROPOSAL DUE: Sep 20, 2006 AWARD: Sep 29, 2006 CONTRACT: $500,000 CONTRACTOR: Coleman Construction

Placement Site Tilghman Island Harbor

Poplar Island Environmental Restoration Project

PROJECT: Poplar Island Environmental Restoration, Cell 6 Closure, MD TYPE WORK: New Work/Construction DEPTH: 25 Ft.

WIDTH: 400 Ft. .

LENGTH: 4,300 Ft QUANTITY: 900,000 c.y.

TYPE OF MATERIAL: Sand STOCKPILE AREA: Cell 4 DISTANCE TO STOCKPILE AREA: 1-2 miles TYPE OF EQUIPMENT: Hydraulic cutterhead pipeline SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2006 to 15-20 Ft ENVIRONMENTAL WINDOW: January 1 – December 31 REASON FOR WINDOW: N/A FY 07 FUNDING: $6,000,000 ADVERTISING DATE: Dec 06 BID OPENING DATE: Jan 07 AWARD DATE: Feb 07

Scheduled FY07 Dredging Work in Baltimore District

Mechanical Dredge Maintenance Dredging Baltimore Harbor & Channels (Awarded August 23, 2006) FY06 SEP OCT NOV DEC JAN FEB 2.0 MCY FY07 MAR APR MAY JUN JUL AUG SEP FY08 OCT Drying at Poplar Island Baltimore Harbor & Channels Drying at Poplar & Hart-Miller 2.5 MCY State of Maryland New Work Seagirt Marine Terminal Masonville DMCF 3.0 MCY 1.5 MCY Page 1 of 1

PROJECT: Baltimore Harbor & Channels, MD TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 400 - 800 Feet LENGTH: 10 – 15 Miles QUANTITY: 2,000,000 cy TYPE OF MATERIAL: Silt and clay PLACEMENT AREAS: Poplar Island Environmental Restoration Project DIST. TO PLACE. AREA: 20 -30 Miles TYPE OF EQUIPMENT: Clamshell SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2000 - 2005 ENVIRONMENTAL WINDOW: Dec 1 – July 31, Sep 1 – Mar 31 REASON FOR WINDOW: Sturgeon, Dredged Material Drying FY 07 FUNDING: $18,500,000 ADVERTISING DATE: Jun 30, 2006 BID OPENING DATE: Aug 1, 2006 AWARD DATE: Aug 23, 2006 CONTRACT AMOUNT: $18,834,200 CONTRACTOR: Great Lakes Dredge & Dock Co.

PROJECT: Baltimore Harbor & Channels, MD TYPE WORK: Maintenance DEPTH: 50 Feet WIDTH: 400 - 800 Feet LENGTH: 10 – 15 Miles QUANTITY: 2,500,000 cy TYPE OF MATERIAL: Silt and clay PLACEMENT AREAS: Poplar Island and Hart-Miller Island DIST. TO PLACE. AREA: 20 -30 Miles TYPE OF EQUIPMENT: Clamshell SMALL BUSINESS SET ASIDE: No LAST DREDGED: 2000 - 2006 ENVIRONMENTAL WINDOW: Dec 1 – July 31, Sep 1 – Mar 31 REASON FOR WINDOW: Sturgeon, Dredged Material Drying FY 07 FUNDING: $300,000 ADVERTISING DATE: May 2007 BID OPENING DATE: Jun 2007 AWARD DATE: Jun 2007

Existing Dredged Material Placement Sites

HART-MILLER ISLAND CONTAINMENT FACILITY

Poplar Island Environmental Restoration Project

Proposed Masonville DMCF Seagirt Marine Terminal

Port of Baltimore

Seagirt Marine Terminal

Masonville Dredged Material Containment Facility

Corps Dredge Currituck Assateague Island

Scheduled FY06 Dredging Work in Baltimore District

FY06 SEP OCT NOV DEC JAN 90 KCY FEB FY07 MAR APR 90 KCY MAY JUN JUL AUG SEP FY08 OCT 90 KCY Page 1 of 1

Assateague Island Restoration

Ocean City Inlet Looking West

Assateague Island, Looking North

USACE Dredge CURRITUCK Depositing Sand in Surf Zone Off Assateague Island

Maryland Port Administration’s Seagirt Marine Terminal