Transcript Slide 1
Infrastrutture: Qualità sotto controllo Il Valore delle Verifiche Indipendenti Copenhagen Cityringen Metro Project Ing. Matteo Buzzetti Copenhagen Metro Team CMT Design Coordinator 31-01-2013 Agenda 1. Introduction to Cityringen Project 2. Design Process – Check, Validation & Approval 3. Design Structure 4. Conteco Review Process 5. Special Stations 6. Optimized Construction Sequence 1. Introduction to Cityringen Project Contract - Copenhagen Cityringen Project Civil Works (signed on 10 January 2011) - Design & Build Contract - Value: approx. 1.500 mln Euro Joint Venture: - Salini S.p.A. - Tecnimont Civil Construction S.p.A. - Seli Client: Metroselskabet I/S Metroselskabet I/S is owned by: • Municipality of Copenhagen (approx. 50%) • Danish State (approx. 42%) • Municipality of Frederiksberg (approx. 8%) Cityringen shall operate 24 hours/7 days a week with a planned operational headway of approximately 100 sec. during rush hours, in the first years of operation Cityringen is expected to serve up to 240.000 passengers per day or 72 million passengers per year Description of the works • Two single track tunnels each approximately 16 km in length • 17 underground Stations • 3 Construction and Ventilation Shafts • 1 Ramp and Cut & Cover structure for TBM launch and access to the Control and Maintenance Center • M&E Installations The tunnel construction will be done by means of three methods: • Approximately 7.6 km of twin tunnel using TBM (tunnel boring machines) EPB type (Earth Pressure Balance) Type Diameter 5.78 m to ensure an internal minimum diameter of 4.9 m. • Variable diameter twin tunnel and caverns using sprayed concrete lining and steel ribs temporary supports (SCL) • Cut and Cover Tunnel The TBM construction shall be primarily through the Copenhagen limestone. The tunnel depth varies from approximately 15 m to 35 m 2. Process – Check, Validation & Approval PARTIES INVOLVED IN DESIGN & APPROVAL PROCESS Metroselskabet (Employer), ISA (Independent Safety Assessor) and SRA (Safety Regulatory Authority) Copenhagen Metro Team (CMT) - Contractor Tecnimont Civil Construction / EKJ (TCC/EKJ) - Designers Conteco – Independent Verification Body Design Team Organization Phase RESPONSIBILITY TECHNICAL DIRECTOR DESIGN COORDINATOR FLOW CHART Definition of WBS for design and design package Design Quality Plan Design schedule List of documents Assessment of laws and regulations List of Laws and Regulations DESIGN PLANNING DESIGN MANAGER PROJECT LEADERS CMT CONTECO DESIGN TEAM Design package Kick-off meeting Start up meeting Working Site Layout Construction Sequences Constructability Risk Assessment Interface Main Issues (ICDD to be opened and followed up) Preliminary GIR & Groundwater Conditions Existing Building / Monitoring Specific Environmental Issues Phase RESPONSIBILITY FIRST DESIGN ASSESSMENT AND INPUT TO CONTECO DESIGN TEAM FLOW CHART Preliminary Reports Sketches First Design Assessment Input to Conteco for Alternative Calculation DESIGN MANAGER CONTECO INDIPENDENT BODY - Geotechnical Parameters Formwork Drawings M&E input Conteco Calculations DESIGN DEVELOPMENT AND CHECK DESIGN TEAM Design package development DESIGN MANAGER DESIGN TEAM VC1 INTERNAL VERIFICATION Periodical design review Documents and reports Document and reports update if necessary Phase RESPONSIBILITY FLOW CHART Distribution to CMT for review DESIGN INTERNAL REVIEW DESIGNER DOCUMENT CONTROL TECHNICAL DIRECTOR DESIGN COORDINATOR INTERFACES ASSESSMENT CMT CHECK SAFETY ASSESSMENT RISK ASSESSMENT CONTECO INDIPENDENT BODY DESIGN COORDINATOR CONSTRUCTABILITY ASSESSMENT VC2/VC3 CHECK Comments Transmission to Designers Review Sheets Check and Homogenization Phase RESPONSIBILITY DESIGNER DOCUMENT CONTROL DESIGN UPDATE AFTER CMT/CONTECO COMMENTS DESIGN TEAM FLOW CHART Distribution to Design Leaders DESIGN UPDATE V1 CHECK DESIGN MANAGER DESIGN MANAGER DESIGNERS DOCUMENT CONTROL ANSWERS TO CMT/CONTECO COMMENTS Design Document Package Approval Submission to CMT for issue Design Certificates Phase RESPONSIBILITY FLOW CHART DESIGN CHECK AND ISSUE TO MS CMT/CONTECO FINAL CHECK VC2/VC3 INDIPENDENT BODY CHECK OF UPDATED DOCUMENT AND ANSWERS TO COMMENTS DESIGN COORDINATOR CHECK OF UPDATED DOCUMENT AND ANSWERS TO COMMENTS TECHNICAL DIRECTOR VC2/VC3 INDIPENDENT BODY Design Document Package Approval Check Certificate by Conteco DESIGN ISSUE TO MS EXTRENAL REVIEW CMT DOCUMENT CONTROL MS REVIEW ISA/SRA REVIEW METROSELSKABET MEASURING BUILDING PERMIT DESIGN COORDINATOR TECHNICAL DIRECTOR Monitoring status of design documents Monthly report 3. Design Structure Design Packages Station/Shafts - Preliminary Design 21 Packages - Detailed Design 192 Packages (Civil Works only) Tunnel Stretches - Preliminary Design 21 Packages - Detailed Design 21 Packages Total Number of Design Packages 272 - Average number of revisions considering all the involved actors 4 - Total Number of Design Packages considering 4 Revision 936 Approximate Design Duration ≈ 3 years ≈ 780 working days Design Packages to be managed per day 1.2 Design Packages to be managed per week 6 4. Conteco Review Process Verification Scope of Works as per Main Contract Requirements 4. Conteco Review Process 1st Phase – Revision on Internal Submission (Rev. 0.1) 2nd Phase – Documents Update (Rev. 1.0) and Answers to Conteco Remarks by Designers 3rd Phase – Conteco Final Check of Revision 1.0 If the Documents have been correctly updated and the answers to remarks are satisfactory Conteco issues the Final Verification Report and the Check Certificates 5. Special Stations Gammel Strand Marmorkirken Marmorkirken Station – Tender Design • During the Tendering phase of the Project, CMT proposed a concept design of the station which was modelled on the recently constructed Station Piazza Bologna of Rome Line 3 Metro. The conceptual design of the station consisted of a narrow station box, providing the space for a concourse area as well as escalators with a stacked platform solution requiring the tunnels to run one above the other. Marmorkirken Station – Design Optimization proposed by CMT during the Tender • The concept of the stacked solution required a deepening of the station box but limited all works from course level downwards to be contained within the diaphragm wall retaining structure thus avoiding the necessity of cavern works or additional ground treatment such as freezing Marmorkirken Station – Design Optimization proposed by CMT during the Tender Additional Mitigation Measures to avoid Volume Loss under the Church and the Ancient Buildings Gammel Strand Station – Tender Design • The station is a special station located at Gammel Strand partly below Slotsholmskanalen. • Gammel Strand station is classed as a “special” station due to its unique location and layout. • All station elements at street level, including the emergency exit stair and ventilation openings are located close to and along the quay wall. Also the lift is located close to the quay wall behind the main stair. • Due to the station being located partly below the Slotsholmskanalen the station box has been lowered so that the roof of the technical level, which is equivalent to the normal station roof level, is below the bottom of the canal. Gammel Strand Station – Construction Sequences Temporary Works – Phase 1 Diversion of navigation within canal / Installation of navigation buoys / Installation of silt curtain Gammel Strand Station – Construction Sequences Temporary Works – Phase 2 Mobilization of pontoon / Placing of drill rigs on pontoon / Installation of micro- piles for temporary bridge deck Gammel Strand Station – Construction Sequences Temporary Works – Phase 3 Installation of precast bridge decking / Concreting of bridge decking /Installation of micro- piles for tie back of bridge Gammel Strand Station – Construction Sequences Temporary Works – Phase 4 Installation of sheet pile wall / Installation of gabions / Backfilling to create job site area Gammel Strand Station – Construction Sequences Permanent Works – Stage 1 Permanent Works – Stage 2 Construction of Guide Walls and DW Construction of Top Slab Installation of Strut on DW Head Excavation within station with the installation of struts at specific levels Start of Archaeological Excavations Installation of water proofing membrane and Concreting of Bottom Slab Gammel Strand Station – Construction Sequences Permanent Works – Stage 3 Construction of Inner Lining & Intermediate Slabs Completion of Waterproofing Removal of Backfill within canal and demolishing of DW above top slab Reinstatement of quay wall 6. Optimized Construction Sequence Optimised Construction Sequence - Typical Station - Phase 1 Top Slab Top Slab Secant Piles Secant Piles King Post Piles Optimised Construction Sequence - Typical Station - Phase 2 Excavation Excavation 1st level of strut Demolition of King Post piles Optimised Construction Sequence - Typical Station - Phase 3 Connection to King Post Piles Installation of waterproofing and connection to retaining wall Installation of 2nd Strut level Intermediate Slab Construction Excavation Resumes Excavation Resumes Optimised Construction Sequence - Typical Station - Phase 4 2nd Strut Level 3rd Strut Level Excavation Resumes Excavation Resumes with King Post Piles Intact Optimised Construction Sequence - Typical Station - Phase 5 Construction of Slab. Subsequent placing of metallic King Post Construction of Slab in presence of King Post Piles Optimised Construction Sequence - Typical Station – Advantages/Disadvantages ADVANTAGES OF OPTIMISED CONSTRUCTION SEQUENCES Excavation methodology remains unchanged from start to end. No requirement to excavated under intermediate slab with alternative equipment and lower rates of production No execution of King Post Piles No pre-installation and of waterproofing membrane at intermediate slab level No predisposition of connection of intermediate slab to retaining wall and king post piles to permit excavation to resume below intermediate slab Concreting of structure performed in a traditional bottom up method without complications for waterproofing membrane and coupler connections Reduced risk for delays in construction due to simplified construction sequences No secondary concreting of bottom slab at location of king post locations with complications in sealing of waterproofing membrane DISADVANTAGES OF OPTIMISED CONSTRUCTION SEQUENCES Additional installation of 1 level of struts Installation of scaffolding for the construction of intermediate slab Thank you for your attention Special Thanks to Sergio Notarianni – CMT Technical Director All CMT Technical Office