Commissioning
Download
Report
Transcript Commissioning
Commissioning
Missy Ogan, P.E.
[email protected]
June 25, 2002
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Commissioning (CX)
Topics
Drivers
ORNL’s Historical Way
Advantages & Disadvantages of CX
CX Resources
ORNL CX Projects
ORNL Lessons Learned
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Drivers
DOE 413.3 - Program & Project Mgmt for
acquisitions of Capital Assets.
Test and Evaluation
Sustainable Designs
LEED prerequisite but LEED is NOT mandated.
EO 13123 - Greening the Gov through
Efficient Energy Mgmt
ENERGY STARR Buildings “strive to meet ..”
Best Management Practice
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL’s Historical Way
Managing & Operating Contractor
Establishes design basis & performance
requirements
Reviews AE Title I & II docs
Performs Title III w/AE home office support
Performs construction inspection
Provides oversight of Start up and Testing
Actually starts up certain systems
Power & Instrumentation
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Advantages of CX Agent
Independent
Established CX Process and Tools
Design Check lists
CX Specifications
Test Procedures
Test Equipment
Up to date on latest technologies
Staff augmentation
Not just Test and Balancing OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Disadvantages of CX Agent
Unfamiliar with Site processes, standards
and procedures - learning curve
Lack of ownership
Another contract to manage
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
CX Resources
ASHRAE Guideline 1-1996- HVAC Commissioning
Process, 1996
SMACNA - HVAC Systems Commissioning
Manual, 1994
Portland Energy Conservation, Inc. (PECI) - Model
Commission Plan & Guide Spec, Version 2.05
DOE Building Commissioning Guide, Version 2.2
Building Commissioning Association
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
CX Resources
PECI
www.peci.org/cx/index.html
Model Commissioning Plan
Part I - CX reqmts in Design team phase
Part II - CX Plan in Design phase
Part III - CX Guide Specs (Divs 1, 15, 16, 17)
Part IV - CX Plan in Construction Phase
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
CX Resources
Building Commissioning Association
http://www.bcxa.org
Currently NO certification program available
but in the works
Member List available
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL CX Projects & Phase
Laboratory for Comparative & Functional
Genomics (Mouse House) (6/17/02 Construction
start)
UT-Battelle Development Corp (in Construction)
Joint Institute for Computer Science (design CFC)
Advanced Materials Characterization Lab (design
CFC)
Research Support Center (Title I complete)
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL Lessons Learned
2 Projects required CX in accordance with
PECI but AE to hold contract
CX was brought in late in design phase on
both projects. AE trying to manage costs..
After one CX meeting - cancelled CX contract
and are soliciting for another. Changing to
Company held contract.
Mostly EITs
Past performance as LEED consultant poor
Second project CX deliverables were excellent.
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL Lessons Learned Summary
No local area commissioning agents
RFP for CX must be clear & concise
CX contract should be with M&O
CX should be brought on board at
project’s design kick off.
Funding to support for duration of project.
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY