Commissioning

Download Report

Transcript Commissioning

Commissioning
Missy Ogan, P.E.
[email protected]
June 25, 2002
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Commissioning (CX)
 Topics






Drivers
ORNL’s Historical Way
Advantages & Disadvantages of CX
CX Resources
ORNL CX Projects
ORNL Lessons Learned
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Drivers
 DOE 413.3 - Program & Project Mgmt for
acquisitions of Capital Assets.
 Test and Evaluation
 Sustainable Designs
 LEED prerequisite but LEED is NOT mandated.
 EO 13123 - Greening the Gov through
Efficient Energy Mgmt
 ENERGY STARR Buildings “strive to meet ..”
 Best Management Practice
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL’s Historical Way
 Managing & Operating Contractor
 Establishes design basis & performance
requirements
 Reviews AE Title I & II docs
 Performs Title III w/AE home office support
 Performs construction inspection
 Provides oversight of Start up and Testing
 Actually starts up certain systems
 Power & Instrumentation
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Advantages of CX Agent
 Independent
 Established CX Process and Tools




Design Check lists
CX Specifications
Test Procedures
Test Equipment
 Up to date on latest technologies
 Staff augmentation
 Not just Test and Balancing OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
Disadvantages of CX Agent
 Unfamiliar with Site processes, standards
and procedures - learning curve
 Lack of ownership
 Another contract to manage
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
CX Resources
 ASHRAE Guideline 1-1996- HVAC Commissioning
Process, 1996
 SMACNA - HVAC Systems Commissioning
Manual, 1994
 Portland Energy Conservation, Inc. (PECI) - Model
Commission Plan & Guide Spec, Version 2.05
 DOE Building Commissioning Guide, Version 2.2
 Building Commissioning Association
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
CX Resources
 PECI
 www.peci.org/cx/index.html
 Model Commissioning Plan




Part I - CX reqmts in Design team phase
Part II - CX Plan in Design phase
Part III - CX Guide Specs (Divs 1, 15, 16, 17)
Part IV - CX Plan in Construction Phase
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
CX Resources
 Building Commissioning Association
 http://www.bcxa.org
 Currently NO certification program available
but in the works
 Member List available
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL CX Projects & Phase
 Laboratory for Comparative & Functional
Genomics (Mouse House) (6/17/02 Construction
start)
 UT-Battelle Development Corp (in Construction)
 Joint Institute for Computer Science (design CFC)
 Advanced Materials Characterization Lab (design
CFC)
 Research Support Center (Title I complete)
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL Lessons Learned
 2 Projects required CX in accordance with
PECI but AE to hold contract
 CX was brought in late in design phase on
both projects. AE trying to manage costs..
 After one CX meeting - cancelled CX contract
and are soliciting for another. Changing to
Company held contract.
 Mostly EITs
 Past performance as LEED consultant poor
 Second project CX deliverables were excellent.
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY
ORNL Lessons Learned Summary




No local area commissioning agents
RFP for CX must be clear & concise
CX contract should be with M&O
CX should be brought on board at
project’s design kick off.
 Funding to support for duration of project.
OAK RIDGE NATIONAL LABORATORY
U. S. DEPARTMENT OF ENERGY