Transcript TITLE
Non-regulated Interconnectors NECA Seminar Tuesday 8 December 1998 Opening Remarks Stephen Kelly NECA Introduction • Code provisions • programme • key issues 3 Obligations on promoter • • • • establish connection agreements with NSPs register as market participant provide an access undertaking to ACCC apply to NECA 4 Obligations on NECA • establish rules for market participation • within two years of market launch, develop provisions to address financial risk to promoter as a result of need for augmentation 5 Change in status • provision to switch from non-regulated to regulated link, subject to conditions • meets Code criteria and technical standards • passes “net public benefit” test 6 Programme • • • • • • • • a role for entrepreneurial interconnectors? a proponent’s perspective introduction to working group proposals market participation structural and competition issues extensions and alternatives overall assessment conclusions and next steps 7 Key issues • generator competitors or TNSP companions? • regulated and non-regulated links: can they coexist? • hermaphrodite links: a freak of nature? • access, market power: how light-handed can we be? • safe harbour provisions: smothering at birth? 8 WHY NON-REGULATED INTERCONNECTORS ? An advocacy statement .. Stephen Orr Hazelwood Power A REGIONAL MARKET DESIGN • NEM is regionalised - conscious choice • Simplified version of full nodal pricing • few intra-regional constraints (in real regions) • mechanism to redefine if constraints occur • Inter-regional constraints create heavy risks for participants; market awakening 25 Nov 97 10 NEMMCO IRH PROCESS • Settlement Residue Auction (SRA) process developed as interim access to SR to underwrite inter-regional hedges and mitigate IR risk • Also developed view of the future, issues being: • network performance drivers and standards • firm inter-regional access - leading to IRHs • regulatory risk for investing participant hence non-regulated interconnectors 11 ISSUES FOR PARTICIPANTS • Particularly generators, but others too • Interconnectors look like wires, but … ... • They perform like competitors, ie • They introduce remote generation as new entrants into a region • Conversely they add remote load to a region • They also potentially redefine the region 12 INVESTMENT RISK • Investment criteria for regulated interconnectors don’t match market criteria, eg: • n-1 transmission reliability standard • Demand with 10% probability of exceedance • ACCC reviewing criteria for NEMMCO to approve regulated status for interconnectors 13 INVESTMENT RISK contd • Regulated interconnectors see little investment risk - if transmission planner sees the need, customers pay until next optimisation • Even if investment rules become marketcommercial, regulated interconnector not at risk of failure • Hence, some propose higher discount rates for regulated interconnector assessments 14 REASONABLE INVESTMENT CERTAINTY • Regulated interconnectors threaten the price signals which underpin local generation and demand-side investment = regulatory risk • Generation/demand investor confidence up if interconnector faces equivalent market risk • “If you think it’s a good deal, you build it!” “If you don’t, don’t ask the market to underwrite your errors ……… 15 NON-REGULATED INTERCONNECTORS • Are competitively neutral • Reduce the need for central intervention • Require a change in thinking away from conventional interconnector perspectives • Can be free-flowing and open like normal transmission lines, or alternatively … … • Can be actively traded in the market through price-differential/volume offers 16 NON-REGULATED INTERCONNECTORS • Potentially remove the need for regulated interconnectors at all, ie • if regulated rules changed to achieve competitive neutrality, no for regulated • if commercial hurdles not met, governments and others can build NRIs, and take the risk 17 TODAY’S SESSION • Reflects the initial results of efforts of a diverse industry group to define the nature and operation of non-regulated interconnectors • The group has diverse views on some key issues, but sufficient consensus on the fundamentals to encourage others to join the debate 18 A Proponent’s Perspective Tony Cook TransÉnergie Australia Outline • Code requirements • DirectLink • Transmission in a competitive market 20 National Electricity Code Obligations of Proponents • Clause 5.6.6 (f) requires a connection applicant, in relation to a non-regulated interconnector, to: – apply to NECA in accordance with clause 3.10 to determine the rules that will apply in terms of the connection applicant’s participation in the market as a market participant in relation to that interconnector. • TransEnergie Australia and NorthPower made 21 application to NECA on 1 October 1998. National Electricity Code Obligations of NECA • Clause 5.6.6 (g) provides that, if an application is made to NECA under clause 5.6.6 (f) (4), NECA must determine those rules within a reasonable time after receipt of the application. 22 DirectLink Features • • • • 180 MVA capacity between Qld and NSW. DC technology. 1 January 2000 commissioning date. Non-regulated interconnector – Recoup costs through trading in financial instruments tied to the interconnector capacity. 23 Geographic Location Darwin NT QLD WA Brisbane SA DirectLink region NSW Perth Adelaide Sydney Canberra VIC Melbourne TAS Hobart 24 Transmission in Competitive Markets • Objective: – Provide sufficient transmission capacity to ensure a competitive energy market, while fairly and efficiently pricing the use of that capacity. • Outcomes: – Facilitate competition in: • generation, • transmission (as an alternative to local generation). 25 Transmission in Competitive Markets • Commercial framework for transmission expansion: – “Top Down” projects for reliability and competition - determined by NEMMCO – “Bottom Up” projects in response to energy price differentials - proposed by developers. 26 Transmission in Competitive Markets • Top Down Projects – Competitive tendering e.g. Victoria • Bottom Up Projects – Entrepreneurial interconnectors. 27 Benefits to Consumers and Generators • Effective competition in generation. • Lower transmission costs. 28 Introduction to the Working Group’s Proposals John Howarth VPX WG’s Terms of Reference • One of the group’s terms of reference is – “recommend rules to govern the participation of entrepreneurial interconnectors in the national electricity market and advise on implications for other aspects of the market design such as network augmentation criteria.” – this is a problem - how can you write rules for an unregulated interconnector? – need to define the boundary of acceptable behaviour 23/02/98 without being prescriptive 30 WG’s Terms of Reference • Addressed in three stages: – identify “safe harbour” provisions – define the degree of discretion used in other approvals – define scope for future extensions and variations to the “safe harbour” provisions • This workshop is a result of the first stage and some progress has been made on the other stages • The work presented today is new and requires a change in thinking - there are still many challenges – inter-regional hedging 23/02/98 – completion of other stages etc 31 • Other Terms of Reference Remaining Tasks – “if possible recommend a practical and effective implementation path for introducing firm link-based inter-regional hedges, i.e. inter-regional hedges that are underwritten by settlements residues and are as firm as practicable against residual risks such as those associated with network availability.” – “advise on the scope and appropriateness of aligning the inter-regional and intra-regional hedging provisions with frameworks such as the transmission congestion contract concept and others. This should include 32 23/02/98 identifying the implications for other aspects of the What are “Safe Harbour” Provisions • Safe harbour provisions. 23/02/98 – A set of provisions conformance to which would ensure an application’s approval. There is no implication that non-conforming applications would necessarily be rejected, although they would not be assured of receiving approval. – not code requirements but a set of criteria to judge automatic acceptability. – because we are naturally risk adverse the provisions are conservative. 33 • What are “Safe Harbour” Obligations Provisions – Configuration limits – Must be scheduled – Must have controllable flow – Pay network service charges – Enter into connection agreements – Exposure to costs and benefits of interconnector – NEMMCO to have power to direct – Subject to competition – Sunset clause – Subject to market power provisions – Ring-fencing provisions 23/02/98 – Must make an access undertaking 34 What are “Safe Harbour” Provisions • Rights – Entitled to the spot market revenue – Can enter into Reserve Trader contracts – Option to convert to regulated status • Having fulfilled the obligations, the entrepreneurial interconnector has access to spot market revenue 23/02/98 35 Status of Working Group Paper • The WG has not endorsed all the provisions • There are still differing views • However the WG has agreed that it is time for wider consultation and exposure of the proposal • WG may need to review provisions in the light of feedback from this workshop 23/02/98 36 Post - implementation Review • WG recommends post - implementation review – > one application but, – < 3 years • Needed due to keep pace with innovation! • Needed because the concepts are new and quite different from other approaches therefore need to consider developments 23/02/98 37 Definitions • Interconnector. A network element that connects networks located in different regions of the National Electricity Market (NEM). • Entrepreneurial interconnector. An interconnector for which there is an entitlement to derive income through its participation in the spot market. • Non-regulated interconnector. An entrepreneurial interconnector for which there is no entitlement to recover any revenue through regulated network 23/02/98 38 service charges. Definitions cont’d • Regulated interconnector. An interconnector for which there is an entitlement to recover a determined level of revenue through the imposition of regulated network service charges. There is no entitlement to retain any additional revenues arising from the operation of the interconnector in the spot market. 23/02/98 39 • Definitions cont’d Hybrid interconnector. An entrepreneurial interconnector for which there is an entitlement to recover some revenue through the imposition of regulated network service charges. As with other entrepreneurial interconnectors, income may also be obtained through participation in the spot market. • A mix of regulated and non-regulated has been identified but further work required. This and general areas where the safe harbour provisions can be extended in the future will be the subject of 23/02/98 40 Rod Ward and Dave Roberts talk at 2:15pm NECA WORSHOP ON ENTREPRENEURIAL INTERCONNECTORS Introduction - End User Perspectives Roman Domanski Executive Director Energy Users Group 23/02/98 Sydney Airport Sheraton 8 December 1998 41 Entrepreneurial Interconnectors • Supportive of Concept • Why? – ‘virtual’ generator & competition for generators – competition for TNSPs - ‘right’ to provide – adds depth to NEM by strengthening links between regions – can help augmentation become more competitive – consistent with reform 23/02/98 42 Safe Harbours Simple, just park it in this ‘safe harbour’ 23/02/98 How do I stop my entrepreneurial interconnector getting torpedoed? 43 ‘Safe Harbors’ Concept • Could go without rules, but • Rules provide some certainty for a new concept – certainty for investors, owners & customers – may improve chances of getting proposals up • Rules should not hinder proposals • Need to be flexible enough to foster change – but firm enough not to stop investment 23/02/98 44 Need for Debate As rules are new and innovative, important to expose to broader debate and get feedback. Need to be prepared to modify SHP to take account of informed comment. Need to also consider links between this work and ACCC review of regulated interconnectors 23/02/98 45 Competition Issues • Market Power – considerable discussion about threshold market shares • • • • Access Ring Fencing Hybrids Conversion 23/02/98 These issues need broader input 46 The Future • Monitor and review • Adapt to practical experience & NEM/reform goals:e.g. – review requirement that flow must be independently controllable – perhaps move to calculating the price difference with and without interconnector • Should all future links be entrepreneurial – intra- & inter-regional? 23/02/98 47 Market Participation Stephen Wallace Snowy Mountains Hydro-Electric Authority Michael Green Transend Networks Pty Ltd Overview • Market issues – – – – bidding, dispatch and pricing spot market revenues system security contracting • Network issues – configuration and controllability – connection agreements and network pricing 49 Spot Market Participation • Networks characterised by – economies of scale – short run marginal costs are insufficient to cover costs of optimally sized interconnector • Three models for interconnector operation – passive participation – bids capacity – bids price differential (above marginal losses) 50 Interconnector Market Model • Passive participation - due to economies of scale is likely to encourage undersized links • Bids capacity - subset of price differential model – a capacity bid is equivalent to bidding two prices, $0 and VoLL, with the MWs bid at 0 the same as capacity offered • Bids price differential - best model 51 Bidding & Rebidding Price Differentials • Similar to generators or customers • 10 prices for each direction (monotonically increasing) • For each price MWs of capacity offered for each half hour • Total capacity offered each half hour is equal to link capacity • Obliged to follow dispatch instructions and provide PASA information 52 Dispatch & Pricing (SPD) • Bidding model can be incorporated easily into SPD framework • Objective function is maximise value of supply (demand bids dispatched) - cost of supply (gen offers dispatched) - cost of interconnector (link offers dispatched) - cost of ancillary services 53 Dispatch & Pricing (Ctd) • Link energy balance export = import + link losses (this brings in dynamic marginal losses for flows over link) • SPD essentially the same as now but current interconnector violation penalties approach is extended to transport capacity bids 54 Spot Revenue (energy) • Similar to other participants • Metering at each terminal • Prices at each terminal determined much the same as for other participants • Since flows may change direction or be highly variable there is an issue concerning choice of marginal loss factors 55 Spot Revenue (energy) export • Buys F1 energy in region 1 at spot price adjusted for marginal losses, SP1 x MLF1 import • Sells F2 energy in region 2 at spot price adjusted for marginal losses, SP2 x MLF2 revenue = import - export • Rev = F2 x SP2 x MLF2 - F1 x SP1 x MLF1 Note: There are problems with flows and prices on 5 minute dispatch interval vs half hour averages 56 Marginal Loss Factors (Prices for Energy at Connection Points) • Many possible models for marginal loss factors (MLFs) – – – – – fixed variable with time of day/day of week/season etc variable with direction of flow and 1 or 2 above dynamic nodal pricing of connection point (dynamic + intra regional constraints) 57 Ancillary services • Co-optimisation approach allocates interconnector capacity between energy and ancillary services • Interconnector receives spot market and ancillary services income like other participants • Interconnector pays for ancillary services • If optimal SPD will schedule ancillary services to enhance flow 58 System Security • Same as for generators & other participants • NEMMCO has power to direct for system security reasons • When directed interconnector is compensated in the same way as for other participants (fair market value -ACCC) • May be involved in Reserve Trader contracts 59 Contracting • Actively operates in contract market • Offers inter-regional hedges (IRHs) • May have firm access compensation arrangements • Basically like any other participant 60 Conclusion • Market operation is much like a generator – bidding – requirement to be scheduled and provide information – spot market revenue – ancillary service income and charges – subject to direction etc • What about network connection, TUOS etc? – Mike Green will reveal all 61 62 TRANSEND NETWORKS PTY LTD MICHAEL GREEN CONFIGURATION NO. 1 Existing Interconnection Region 2 Region 1 Proposed Interconnector 64 CONFIGURATION NO. 2 Two Terminal Between Regions Regional Definitions Network Service Charges Bidding & Scheduling 65 CONFIGURATION NO. 3 30MVA Minimum Capability In Line with Scheduled Generator, Clause 2.2.2 Cross Zonal Boundary Windfalls Regulator Shopping 66 NEED FOR CONTROLLABILITY Follow Dispatch Instructions Avoid Adverse Impacts on other Network Elements Forms a Clear Basis for Settlements 67 FREE FLOWING Interconnector Actual Flows Depend Upon: Generator Dispatch Customer Demands Network Characteristics 68 ISSUES IF NOT CONTROLLABLE Safe Harbour Does NOT Preclude This Option Need to Develop Basis of Settlements Need to Develop Basis of Compensation 69 CONNECTION AGREEMENTS Service Levels Connection Fees Arrangements Subject to Negotiation 70 CONNECTION AGREEMENTS CONNECTION FEES Dedicated Entry/Exit Assets - Payable by Proponent Attributable Agreed Deep Augmentation - Payable by Proponent Transmission Use of System - Matter for Resolution 71 CONNECTION AGREEMENTS ISSUES NO. 1 Is there a need for a level playing field between regulated & non-regulated interconnectors? Regulated Face Stringent Regulatory Tests Non-regulated Face Connection Fees? Must Provide for Efficient Investment Interface with NECA Incidence & Allocation Review 72 CONNECTION AGREEMENTS ISSUES NO. 2 See Appropriate Forward Looking Costs See Appropriate Forward Looking Benefits Difficulty With Identifying : Magnitudes of Costs/Benefits Duration of Costs/Benefits Funding of Benefit Rebates 73 CONNECTION AGREEMENTS ISSUES NO. 3 Should non-regulated interconnectors result in financial transfers between Network Service Providers? Many Factors Drive Financial Transfers. 74 SUMMARY MARKET ISSUES Spot Market Revenue Ancillary Services Revenue Required To Be Scheduled Able To Offer Into Market Subject To NEMMCO Direction 75 SUMMARY NETWORK ISSUES Configuration Controllable Flow Must Enter Into Connection Agreements Subject to Efficient Network Connection Fees 76 STRUCTURAL AND COMPETITION ISSUES Conversion to Regulated Status, Sunset Clause, Market Power Issues Stephen Orr Hazelwood Power CONVERSION TO REGULATED STATUS • Safe harbour should allow interconnector owner to apply for conversion to regulated status at any time • Revenue entitlement assessed at the time • Recognises uncertainty regarding nonregulated design at present - hence may encourage investment 78 CONVERSION TO REGULATED STATUS • Also supports utilising economies of scale, eg hybrid converts to fully regulated when justified • Proponent must not be shielded from commercial risks, eg mis-assessment of demand or price • Hence apply rules at the time • No scope for strategic alternation 79 CONVERSION TO REGULATED STATUS • Note • If rules for regulated interconnector investment change to match commercial conditions, • Then why would the non-regulated interconnector owner want the change to regulated status? 80 SUNSET CLAUSE • Conversion to regulated status offers protection to the non-regulated interconnector investor • The sunset clause approach protects the market as a whole from unexpected outcomes • Suggest 15 years minimum reasonable approval for long life, high cost interconnectors • ACCC Code authorisation may limit approval period to 2010 81 MARKET POWER ISSUES • Active trading models create potential for exercise of market power • Economies of scale, easements etc may limit scope for competitive interconnectors • Cross ownership potential • Hence we have considered control to maximum of 35% of either interconnected areas as limit for safe harbour 82 MARKET POWER ISSUES • Concentration of control could be limited by divesting rights to the revenue stream, if operational control ring-fenced • Cross-ownership with regulated interconnector should be OK, provided ring-fencing in place 83 MARKET POWER ISSUES • However ……… this proposal is arbitrary • It excludes, for example, Delta and Macgen immediately • There is a serious question whether the market rules should endeavour to anticipate and constrain market power • Perhaps safe harbour provisions should not be specific - let ACCC decide case-by-case? 84 EXPOSURE TO COMPETITION • No restriction on entry of competing regulated and non-regulated interconnectors • Providing they meet the criteria at the time • This assumes level playing field through the rules governing approval of regulated interconnectors 85 Entrepreneurial Interconnectors Hugh Gleeson (United Energy) & Ken Brunette (Integral Energy) 23/02/98 86 Exposure to competition • No restrictions on the entry of competing interconnectors (regulated or unregulated) • Aim to achieve a ‘level playing field’ to ensure comfort of consistency in regulation • Various views – (Generators) desire to force regulated augmentations to be based on the same investment criteria as unregulated. – (Retailers) preference to see a ‘stable playing field’, not restrict regulated decision making. – (Customers) desire to see most efficient (lowest cost) generation used first irrespective of geographic location87in 23/02/98 clause • Initial approvalSunset to operate as a non-regulated interconnector and actively participate in the market may be limited to a specific interval – safeguard against undesirable unforeseen outcomes. – proposed right to apply to convert to regulated status and receive regulated revenue assessed on the deprival value upon reaching the ‘sunset date’. – fifteen year minimum approval proposed (by some of group) as ‘appropriate’ to match level of investment. – May in practice be shorter horizon as the ACCC Code authorisation expires in 2010. – No protection from effect of Code changes intended by 23/02/98 this clause 88 Ring fencing • Isolation from the operations of any co-owned regulated network business – Ensure the operation is not influenced by consequential profit or loss from the nonregulated business. – Concern regarding potential to influence timing of outages (by related regulated network business) for unreasonable financial advantage. 23/02/98 89 Submission of an access undertaking • Access undertaking to be in the form specified in the Code – Must be available in accordance with the Code. – Applicable Code provisions will likely differ from standard (as exist for regulated assets). • Right to trade (as determined) in the spot market • No right to receive regulated revenues (Chapter 6) 23/02/98 – ACCC acceptance of access undertaking to protect the asset from declaration under the Trade Practices Act. 90 Beyond the Safe-Harbour Rod Ward - Delta Electricity Beyond the Safe Harbour Overview • • • • Purpose of Safe Harbour Provisions Key Limitations of the Safe Harbour Provisions? Trading non-controlled interconnectors The Way Forward? 92 Purpose of Safe Harbour • Conformance to ‘safe harbour’ provisions should guarantee approval. • There is no implication that non-conforming applications would necessarily be rejected 93 Beyond the Safe Harbour • Further work required to: – explore the scope for further extensions and variations – define the degree of discretion for other applications (within and beyond safe harbour) 94 Key Limitations of the Safe Harbour Provisions - case examples The provisions do not cover: • intra-regional interconnectors • non-transmission interconnector capacity upgrade • free flowing AC links - loop and parallel flows • participant or an interconnector controlling more than 35% of the capacity in either of the supply regions • hybrid of regulated and non regulated interconnection 95 Key Limitations of the Safe Harbour Provisions - case examples The provisions do not cover: • intra-regional interconnectors • non-transmission interconnector capacity upgrade • free flowing AC links - loop and parallel flows • participant or an interconnector controlling more than 35% of the capacity in either of the supply regions • hybrid of regulated and non regulated interconnection definition of capacity and access to the market (if controllable or switchable could be considered) 96 Key Limitations of the Safe Harbour Provisions - case examples The provisions do not cover: • intra-regional interconnectors • non-transmission interconnector capacity upgrade • free flowing AC links - loop and parallel flows • participant or an interconnector controlling more than 35% of the capacity in either of the supply regions • hybrid of regulated and non regulated interconnection Impact on the capacity of incumbents and competitive trading solutions 97 Interconnector Trading • energy supplied to a region does not have to be delivered by that interconnector - “inter-regional capacity can be shared” • an interconnector flow does not have to be controlled “inter-regional transfers is controlled by generator loading in merit order” 98 Concept of “Notional Capacity” • Parallel interconnectors treated as a single notional interconnector • revenues are split according to relative capabilities and bids (notional dispatch) • However, complexities arise when the capacity of an incumbent is affected or loop flows occur. 99 Concept of “Notional Capacity” Bidding • Similar to generators • 10 prices for each direction (monotonically increasing) • for each price MW’s of capacity offered in each half hour (total capacity equal to the link) • Any regulated capacity bid at zero • dispatch algorithm will dispatch lowest merit order bids up to the “notional capacity” of all interconnection capacity • However, residual capacity could be “constrained off ” 100 Concept of “Notional Capacity” Case Study - Capacity rights affected Examples: • New interconnector impacts the capacity of another remote interconnector e.g the capacity of SA/NSW interconnector is limited by flows on the NSW/VIC interconnector. • Total capacity of two parallel interconnectors less than sum of individual capacity. Issues: • Prior capacity rights - incremental capacity only recognised? • No prior capacity rights - full competitive bidding and residual capacity effectively constrained off ? • Technical prerequisites? 101 • Firm access to network? Loop Flows Example: • Additional complexity on parallel interconnectors where a connection to a region at two remote points create loop flows. Issues: • current regional model inadequate - more regions or progression to nodal model approach# • prior rights to capacity become increasing complex • complexities of notional capacity allocations would have to be modelled, continuous assessed and resolved in dispatch # loop flows could resolve to parallel flows 102 Key Limitations of the Safe Harbour Provisions - case examples The provisions do not cover: • intra-regional interconnectors • non-transmission interconnector capacity upgrade • free flowing AC links - loop and parallel flows • participant or an interconnector controlling more than 35% of the capacity in either of the supply regions • hybrid of regulated and non regulated interconnection anti-competitive conduct, control, timing of problem 103 Market Power • • • • Why is an interconnector different to generation? When is it likely to be material? Is it ownership, control or cross-subsidy between competitive businesses? Does it safe harbour anti-competitive behaviour of a substantial interconnector - ACCC issue Possible Solutions: • provisions of the TPA appropriate to apply to all owners of interconnectors • Transition requirement: – assets ring-fenced with separate reporting requirements – defined reasonable level of capacity contracts in the market • Alternative - safe harbour applies to small interconnectors only, regardless of ownership 104 The Way Forward • Determine the principles to define capacity and the market trading mechanisms for non-controlled interconnectors • Understand the application and merit of capacity rights and develop firm access where one interconnector affects the operation of another • Better appreciate the market power implications of interconnectors without unnecessarily restricting their development 105 Key Limitations of the Safe Harbour Provisions - case examples The provisions do not cover: • intra-regional interconnectors • non-transmission interconnector capacity upgrade • free flowing AC links - loop and parallel flows • participant or an interconnector controlling more than 35% of the capacity in either of the supply regions • hybrid of regulated and non regulated interconnection David Roberts Presentation to follow 106 Hybrid Interconnectors David Roberts Basslink Development Board Purpose • Endorsement for the Concept • Highlight Issues to be Resolved • Commitment to Progress 108 Outline • • • • • • • Reasons for Hybrid Interconnectors Relevant Situations Examples Principles Issues to Resolve The Way Forward Summary 109 Reasons for • Economies of Scale • Increase in Load Demand does not Automatically Increase Value • Beneficiaries not Necessarily Obvious • Approval of Regulated • Transition between Non Regulated and Regulated 110 Relevant Situations • • • • • Initial Trading may be Limited Most Trading is One Way No Market History to Support Non Regulated Regulated Asset Owner unwilling to Develop Non Regulated applies to become Regulated 111 Examples • • • • X% Regulated Y% Non Regulated Enhancement to Existing Interconnectors Regulated One Way Non Regulated the Other Regulated at Certain Times Non Regulated at Others • Combinations 112 Principles • Regulated Portion of an Interconnector can be Defined • Regulated Portion Subject to Rules for Regulated Interconnectors (Including Approval, Availability, Dispatch, Network Pricing & Revenues, Settlements Residues & IRHs etc) • Remainder Subject to Rules for Non Regulated 113 Issues to Resolve Who Defines Regulated Portion and How Which takes Precedence • Partial Outage • Dispatch at Zero Price Ring Fencing • Required for Network Businesses • Some Complexity with Hedge Contracts 114 Issues to Resolve Non Linear Allocations • Adjustment of Settlements Residue for Allocation of Losses • Required if Regulated and Non Regulated contracts treated differently Network Charges/Revenues • Regulated Portion • Non Regulated Portion 115 Issues to Resolve Approval Criteria • Look Ahead or Based on Market Results • Who bears the Market Risk Review of Regulated Portion • Discretion for Adjusting up or Down 116 The Way Forward • Depends on Arrangements for Regulated Interconnectors (Approval, Settlements Residue and Hedging) • Also Dependent on the Rules for Non Regulated Interconnectors • Common Factors Needed 117 Summary • Hybrid Interconnectors needed as a Bridge between Regulated and Non Regulated Interconnectors • Simple Arrangements should be Possible which could be Adapted to Different Situations • Commitment to Progress Arrangements 118 Next Steps Stephen Kelly NECA Next steps • working group supplementary comments • transmission and distribution pricing review 120 Review timetable • publication of draft report • consultation with key stakeholders • publication of final report Jan / Feb 1999 Feb/March 1999 end-March 1999 121