Transcript Document
Thirty Years of Success in Implementing Desalination
By Roger K. Noack, P.E.
HDR Engineering, Inc.
MSSC 2011 Annual Salinity Summit February 17 – 18, 2011
Presentation Overview
History of Desalination in Florida In the Beginning Overtime there have been some speed bumps Where we are today Summary
In the Beginning
Rotunda West Utilities Placida, Florida 1971 Brackish RO Plant 0.3 MGD Design Capacity Groundwater source high TDS and chlorides Surface discharge for the concentrate
Permitting
Permit to Construct Permit to Operate Local permits – building, clearing, environmental, etc.
Permit to Discharge the Concentrate Started design before having the permit Application is a couple of pages Received approval in a couple of months • Minimal public input
As the world turns….
More desal plants constructed More information becomes available More public involvement More headaches More engineering work
As the World turns….
Mid 1980’s Most sources are groundwater Discharge to ocean Major-Seawater Ion Toxicity – Toxicity resulting solely as a result of a surplus or deficit of one or more of the major seawater ions or from the relative proportions of those ions.
As the World turns….
Tampa Bay Desalination Plant 1996 - West Coast Regional Water Supply Authority ordered to reduce groundwater use 23% by 2003 In October 1996, West Coast Regional Water Supply Authority issued RFP for commercial developer to design, build, operate, and own a desalination plant.
March 3 2010 plant finally hits goal of 25 MGD for 4 months and 20 MGD for 12 months
Where are we today
Over 140 desalination plants Capacity totaling over 500 MGD Ranging from 0.01 to 25 MGD Source Ocean – A couple Surface – 1 plant Groundwater – Overwhelming majority
Concentrate Disposal in Florida
25% 20% 15% 10% 5% 0% 45% 40% 35% 30% Surface Deep Well Injection Land Application Sewer Evap Pond Shallow Well Injection
Permitting Today
Permit to Construct Permit to Operate Local permits – building, clearing, etc.
Permit to Discharge Demineralization Concentrate Recommend getting Discharge Permit before proceeding with design
Permit to Discharge Demineralization Concentrate
10 pages of instructions 20 page form Discharge determines information required Surface Underground injection Land application Blending with reclaim water Blending at wastewater facility All information available to public
Summary
Florida has led the way in desalination The path has not been easy First DBOO – industry learned a lot from this experience More open process today than in the past Can get a permit for construction, operation and discharge, but it will take some time – 1 to 2 years
QUESTIONS
Contact:
813-282-5371
COMMENTS
MSSC 2011 Annual Salinity Summit February 17 – 18, 2011