Telugu Ganga Project

Download Report

Transcript Telugu Ganga Project

TELUGU GANGA PROJECT – NANDYAL CIRCLE
1
PROJECT PROFILE : Lining of TGP Canal from KM 0.000 to KM 96.130 (Up to Kurnool –
Kadapa Border) etc.
2
No. of Packages
:
6 (2 EPC + 4 Old Packages)
3
Agreement value of packages
:
Rs. 188.304 Crs. (EPC Rs. 139.837
Crs.)
4
Expenditure
2004-05
:
Rs. 3.37 Crs.
2005-06
:
Rs. 54.19 Crs.
TOTAL EXP. :
Rs. 57.56 Crs.
5
Land Acquisition
6
Mob. Advance.
:
Paid
Recovered
2004-05 :
Rs. 3.37 Crs.
--
2005-06 :
Rs. 9.34 Crs.
Rs. 7.89 Crs
Rs. 12.71 Crs.
Rs. 7.89 Crs.
Total :
7
Target Date
Nil
:
7/2007
TELUGU GANGA PROJECT – NANDYAL CIRCLE
Package No.50 / Cat-II :
Contractor Name
: M/s E.C.C.I. & M.R.K.R.(J.V.)
i.
Agreement Amt.
: Rs. 72.45 Crs.
Agreement Date
: 25-7-2005
Period of Completion
: 24 Months
Lining to main canal from Km. 0.000 to Km.7.830
i.e. upto Velugodu Balancing Reservoir.
ii. Lining of main canal from Km. 0.000 to
Km.42.566.
Target date of Completion: 7/2007
iii. Construction of high level D.L.B. at Km.9.905
across Nippulavagu near Velpanur.
Investigation
:
Expenditure
:
2005-06
Completed
:
Rs. 4.70 Crores (Inc. Mob. Adv. Rs. 3.62
Present Status
:
Work in good progress
Target date of completion
: 7/2007
Crs)
TELUGU GANGA PROJECT – NANDYAL CIRCLE
Package No.51 / Cat-II :
Name of the Contractor
: M/s SVEC Construction
i.
Lining to Main canal from Km. 42.566 to
Agreement Amount
: Rs. 67.387 Crs.
Km. 96.130 i.e., upto Kurnool-Kadapa
Agreement Date
: 5-3-2005
Border excluding where lining is already
Period of Completion
: 24 Months
completed
Target date of Completion
: 3/2007

Investigation
: Completed

Design
: Approved

Execution (Canal)
: 17 Km lining completed against 53.564 Kms

Qty. of C.C. Lining
: 83350 Sq.m against 1220468 Sq.m

Qty. of RR Masonry
: 9440 cum done against 72600 cum

Qty. of grouting done
: 46,200 Sq. mt against 59056 Sq. Mt.

Expenditure
67.387 Crs.
: Rs. 36.75 Crs. (inc. Mob. adv. Rs.6.66 Crs.) against Rs.

 2004-05
: Rs. 3.37 Crores (mob. Adv.)
 2005-06
: Rs. 33.38 Crores (including mob. adv. Rs.3.29 Crs.)
Mob. Adv. Recovered
: Rs.6.01 Crores.
TELUGU GANGA PROJECT – KADAPA CIRCLE
1
PROJECT PROFILE : Construction of SPVBR left canal, right canal and
Chennamukkapalli Canal, etc.
2
No. of Packages (EPC)
:
2 Nos.
3
Agreement value of packages
:
Rs. 432.72 Crs.
4
Budget Provision (2006-07)
:
Rs. 465 Crs.
5
Expenditure of the Project
2004-05
:
Rs. 24.93 Crs.
2005-06
:
Rs. 136.62 Crs.
Total Exp.
:
Rs. 161.55 Crs.
6
Utilisaiton
:
29 TMC
7
Ayacut
:
2.75 Lakh acres
Kurnool – 1.08 Lakh Acres
Kadapa – 1.67 Lakh Acres
8
Mob. Advance.
Paid
Recovered
2004-05 :
Rs. 21.63 Crs.
--
2005-06 :
Rs. 12.38 Crs.
Rs. 26.17 Crs
TOTAL :
Rs. 34.01 Crs.
Rs. 26.17 Crs.
TELUGU GANGA PROJECT – KADAPA CIRCLE
Package No. 2
Name of the Contractor
Hyd. Agreement Amount
: IVRCL,SEW&PRASAD (JV),
: Rs. 210.42 Crs.
ii. Construction of Irrigation canal taking off from
SR-II and its distributory system.
Agreement Date
: 22-10-2004
Period of Completion
: 24 Months
iii. Construction of Chennamukkapalli Canal and
lining vulnerable reaches of main canal in
Kadapa District.
Target date of Completion
: 10/2006
i.
Construction of SPVBR Left Canal upto
Porumamilla tank and the distributory system.

Investigation (canal)
: Completed

Designs
: Approved

Execution
(Canal)
: 152 Km in progress against total length of 434 Km
Structures
: 45 Nos. against 48.

No. of Machinery deployed
: 118 Nos (Poclains-15, Tippers-70, Dozers-6, SFR-3, VRR-4,
Water Tankers-20)

Qty. of earth work done
: 50.47 Lakh cum against 109.33 Lakh cum

Qty. of concrete work done
: 1.15,5 Lakh cum against 3.54 Lakh cum

Expenditure
: Rs. 78.65Crs. (inc. mob. adv. Rs.14.27 Crs) against Rs. 210.42
Crs.

 Exp. 2004-05
: Rs.12.17 Crores (including Mob. Adv. of Rs.10.52 Crores)
 Exp. 2005-06
: Rs.66.48 Crores (including Mob. Adv. of Rs. 3.75 Crores)
 Mob. Adv. Recovered
: Rs.14.25 Crores.
Land Acquisition
: Required- 2392 Ac., Requisition – 1387 Ac., Acquired:
TELUGU GANGA PROJECT – KADAPA CIRCLE
Package No.3 / Cat - I
i.
SPVBR Left Canal beyond Porumamilla
tank and SPVBR right canal.

Investigation
: Completed

Designs (Canal)
: Approved
(Structures)
Name of the Contractor
Hyd.
: IVRCL,SEW&PRASAD (JV),
Agreement Amount
: Rs. 222.30 Crs.
Agreement Date
: 22-10-2004
Period of Completion
: 24 Months
Target date of Completion
: 10/2006
: 66 Nos. against 314 Nos.

Execution
: 60 Km in progress against total length of 120 Km

No. of Machinery deployed
: 174 Nos (Excavators-35, Dumpers-100, Dozers-8,
Crusher-1, Batching Plant-2 & Mixer Machines-20 etc)

Qty. of earth work done
: 20 Lakh cum against 54 Lakh cum

Qty. of concrete work done
: 22,500 cum against 5,11,750 cum

Expenditure
: Rs. 82.90 Crs. (inc. mob. Adv. Rs.19.74 Crs.) against Rs. 222.30 Crs.

 Exp. 2004-05
: Rs. 12.76 Crores (inc. Mob. Adv. Rs. 11.11 Crores)
 Exp. 2005-06
: Rs.70.14 Crores (inc. Mob. Adv. Rs. 8.63 Crores)
 Mob. Advance recovered
: Rs. 11.92 Crores.
Land Acquisition
: Required - 3100 Ac;
Acquired - 180 Ac.