RAJIV LIFT IRRIGATION SCHEME (BHIMA)
1
Project Profile
: Lifting of 20 tmc of water from
foreshore of PJP and Ookachettivagu
Project Pondage
2
Administrative Sanction
: G. O. Ms. No. 166, I & CAD, Dt: 30-102003 for Rs. 1426.30 Crores
3
No. of EPC Packages
: 13 Nos.
4
Agt. Value of 13 Pkgs
: Rs. 1417.92Crs.
5
Budget Provision for
2006-07
: Rs. 193.20 Crs.
6
Expenditure
2004-05 : Rs. 108.68 Crs. (Incl. Sangambanda BR)
2005-06 : Rs. 238.50 Crs.
TOTAL : Rs. 347.18 Crs.
7
Utilisation
8
Ayacut
: 20 TMC
New Ayacut
: 2,03,000 Acres
Stabilization
: 4,000 Acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
9
10
11
Lift-I
Lift Height
: 67 M
No. of Pumps
: 6 Nos.
Total pumps capacity
: 48 MW
Lift Height
: 61 M
No. of Pumps
: 6 Nos.
Total pumps capacity
: 48 MW
Lift-II
Total Power required
: 96 MW
RAJIV LIFT IRRIGATION SCHEME (BHIMA)
12
Land Acquisition
Required :
21,641 acres
Acquired :
8,278 acres
Requisitioned :
13,000 acres
13
Est. Cost for LA
:
Rs. 120 Crs.
14
Est. Cost for R & R
:
Rs. 40 Crores
15
Mobilisation Advance
: Paid
Recovered
2004-05 :
62.57 Crs
2005-06 :
22.10 Crs.
84.78 Crs.
Total : Rs.
Crs.
16
Target date for completion
: 9/2007
14.99 Crs.
Rs.14.99
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
PKG
No.
Description
Awarded
Bid Amount
Rs. in Crs.
13
Excavation of High level right main canal, distributary
system including construction of CM & CD works from
Sangambanda BR to feed ayacut of 18400 Acres.
M/s. R.M.M. & BRC
(JV)
57.97
14
Excavation of High level left main canal, distributary system
including construction of CM & CD works etc. to feed an
ayacut of 35,800 Ac. Under Sangambanda BR
M/s. VPR-Cromandal
(JV)
68.94
15
Investigation, design, estimation and excavation of canal
distributary system including construction of CM & CD works
from Yenukunta BR, Waddewata (V), Kottakota (M),
Mahabubnagar (D) to feed about 14,000 Acres upto
Rangasamudram BR.
M/s. Prathibha-Ch MR
(JV)
51.270
16
Excavation of canal distributary system – including
constrction of CM & CD works from Ranga Samudram to
feed an ayacut of 21,000 Acres
M/s. RNS-GSR & CO
(JV)
70.800
17
Investigation, design, estimation and execution for
converting the existing Rangasamudram tank, near Sri
Rangapuram (V) Pebbair (M), Mahabubnagar district as
balancing reservoir under Bhima Lift Irrigation Project (Lift-II)
M/s. ALS-KVR (JV)
41.540
18
Investigation, design, estimation and execution for
convesting the existing Shankarasamudram tank, near
Knaipally (V) Kothakota (M), Mahabubnagar district as
balancing reservoir under Bhima Lift Irrigation Project (Lift-II)
M/s. Sri Avanthi
Saivenkata (JV)
42.100
CATEGORY-II
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Pkg
No.
CATEGORY-II
Description
Awarded
Bid Amount
Rs. in Crs.
36.90
19
Shankara Samudram Balancing Reservoir Right Main canal.
M/s. G.H. Reddy &
Associate K.K.R & Co
(JV)
20
(i) Formation of Earth Dam with FRL +352m (ii) Construction of
spillway, (iii) Construction of Head Regulator to let out into left and
right main canals. Budpur Balancing Reservoir
M/s. KNR-SLEC (JV)
36.98
21
Investigation, Designs and excavation of left main canal,
distributary system including construction of CM & CD works from
budpur Balancing reservoir, Budpur (V), Atmakur (M),
Mahabubnagar (D) to feed about 32,000 Acres
M/s. S.V.E.C. Co.,
60.39
22
Investigation, Designs and excavation of right main canal, distributary system
including construction of CM & CD works from budpur Balancing reservoir,
Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres
M/s. S.V.E.C. Co.,
26.73
27
Investigation, Design, excavation of left main canal, distributary
system including construction of CM & CD works from
Sankarsamudam Balancing Reservoir .
M/s. KNR Const. Ltd.
& BPL (JV)
149.40
OC
LIFT-I : Design, manufacture, supplying & erection of pumps,
motors, electro mechanical works, including tunnel, cistern and
pump house etc.
M/s. Patel Engg. Ltd.
383.349
OC
Design and execution of Stage-I and stage-II pumping stations of
LIFT-II at Thirumalayapalli & Kothakota (M), Mahabubnagar (D)
on EPC basis.
M/s. NEC-NCCMAYTAS (JV)
391.55
TOTAL
1417.919
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 13/Cat-II : Excavation of High level
right
main canal,
distributary system including
construction of CM & CD works from Sangambanda
BR to feed ayacut of 18400 Acres.
Name of the Contractor : M/s R.M.M &BRC (JV)
Agreement Amount
: Rs. 57.97Crs.
Agreement Date
: 03-03-2005
Period of Completion
: 24 Months (8 milestones)
Date of completion
: 03-03-2007

Investigation completed
: Completed

Designs
: 9.2 KM approved against 24 KM

Execution (Main canal)
: 15 KM length in progress against total length of 24.00KM

Qty. of earth work done
: 6.00Lakh Cum against 37.32 Lakh Cum.

Qty. of concrete work done : 500 cum against 3500 cum

No. of Machinery
1No.)
: Deployed = 15Nos (Excavators =2 Nos.,Tipper-8Nos., T Roller-
2Nos., Dozers = 1 Nos., Water tank -1No.Crushing plant-

Land Acquisition
acres
: Required 1000 Acres, Requisition : 260 acres, Acquired – 81

Expenditure
: Rs. 14.90 Crs. against Rs. 57.97 Crs.,

Mob. Adv. Paid
: Rs. 2.90 Crs.

Mob. Adv. Recovered
: Rs. 2.90 Crs.
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Name of the Contractor : M/s VPR– Coromandal (JV)
Package No. 14/Cat-II : Excavation of High level
Agreement Amount
: Rs. 68.94Crs.
construction of CM & CD works etc. to feed an
Agreement Date
: 05-03-2005
ayacut of 35,800 Ac. Under Sangambanda BR,
Period of Completion
: 24 Months (8 milestones)
Date of completion
:24-02-2007
left main canal,
distributary system including

Investigation
: Completed (40.645 KM)

Designs
: Main canal completed (40.465 KM)

Execution (main canal)
: 28.75KM length in progress against total length of 40.645 KM

Qty. of earth work done
: 18 Lakh Cum against 26.20 Lakh Cum.

Qty. of concrete work done : 1500 cum

No. of Machinery
21Nos. etc)
: Deployed = 29Nos
(Excavators = 6 Nos., Dozers = 2 Nos, Tippers =

Expenditure
: Rs. 29.88 Crs. against Rs. 68.94 Crs.,

Mob. Adv. Paid
: Rs. 6.88 Crs.

Mob. Adv. Recovered
: Rs. 1.68 Crs.
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 15/Cat-II : Investigation, design, Name of the Contractor : M/s Prathibha – Ch MR- (JV)
estimation and excavation of canal distributary
Agreement Amount
system including construction of CM & CD works
from Yenukunta BR, Waddewata (V), Kottakota (M), Agreement Date
Mahabubnagar (D) to feed about 14,000 Acres upto Period of Completion
Rangasamudram BR.
Date of completion
: Rs. 51.27 Crs.
: 05-03-2005
: 24 Months (8 milestones)
: 05-03-2007

Investigation
: Completed (30.25 KM)

Design
: 26.75 KM approved against 30.25 KM

Execution (main canal) : 13 KM length in progress against total length of 30.25 KM

Qty. of earth work done : 5,70,000 Cum against 20,00,000 Cum

No. of Machinery
: Deployed = 28Ns (Excavators = 6 Nos., Tippers=20Nos, Leveller
=2No.)

Land Acquisition
218.71Acs.
: Required 943 Acres, Requisition :407Acs. Acquired –
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 16/Cat-II : Excavation of canal Name of the Contractor : M/s RNS-GSR & Co. (JV)
distributary system – including construction of CM
& CD works from Ranga Samudram to feed an
ayacut of 21,000 Acres.
Agreement Amount
: Rs. 70.80Crs
Agreement Date
: 02-03-2005
Period of Completion
: 24 Months (8 milestones)
Date of completion
: 02-03-2007

Investigation (HPs)
: Length 58Kms finalised against 81Kms

Execution
: Excavation in 1.5 KM length in progress against total length of
81.00 KM

Qty. of earth work done : 10,000 Cum against 16,00,000 Cum

No. of Machinery
S.Crushers-
: Deployed = 15 Nos (JCB-1No.Excavators = 4 Nos, Tippers-2Nos,
2Nos, Hard top jeep-4Nos)

Expenditure
: Rs. 3.54Crs. (Mob. Adv. Only) against Rs. 70.80 Crs.

Land Acquisition
: Required 1415 Acres, Requisition: 162.34Acres Acquired – Nil
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 17/Cat-II : Investigation, design,
estimation and execution for converting the existing
Rangasamudram tank, near Sri Rangapuram (V)
Pebbair
(M), Mahabubnagar district as balancing
reservoir under Bhima Lift Irrigation Project (Lift-II)
Name of the Contractor : M/s A L S-KVR(JV)
Agreement Amount
: Rs. 41.50 Crores
Agreement Date
: 07-03-2005
Period of Completion
: 24 Months (8 milestones)
Date of completion
: 07-03-2007

Investigation

Designs (Earth Bund & Weir) : 80% approved

Execution
: Started

Qty. of earth work done
: Cut off trench excavated for a length of 1.50 KM

Expenditure
: Rs. 2.08 Crs. (Mob. Adv. Only) against Rs. 41.50 Crs.

Land Acquisition
: Required 2452.30Acres, Requi.: 2526.11Acrs Acquired –
Nil
: Completed
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 18/Cat- : Investigation, design,
Name of the Contractor : M/s Sri Avanthika Saivenkata (JV)
estimation and execution for convesting the existing
Agreement Amount
: Rs. 42.10 Crores
Agreement Date
: 14-03-2005
Period of Completion
: 24 Months(8 Mile Stones)
Date of completion
: 14-03-2007
Shankarasamudram
tank,
near
Knaipally
(V)
Kothakota (M), Mahabubnagar district as balancing
reservoir under Bhima Lift Irrigation Project (Lift-II)

Investigation

Designs (Earth bund & Weir) : 80% of designs approved.

Execution
for
: Completed (3.69 KM)
: Yet to start (Water in the Tank & objections of Kanepally (V)
want of inclusion of village in R & R Package.

Expenditure
: Rs. 2.11 Crs. (Mob. Adv. only) against Rs. 42.10 Crs.

Land Acquisition
: Required 2220 Acres, Requisitioned: 1491Ac. Acquired –
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Name of the Contractor : M/s G. H. Reddy & Associate
K.K.R & Co. (JV),
Package No. 19/Cat-II : Shankara Samudram
Balancing Reservoir Right Main canal.
Agreement Amount
: Rs. 36.90 Crores
Agreement Date
: 19-02-2005
Period of Completion
: 24 Months (Milestones : 8)

Investigation
: Completed (39 KM)

Designs (HPs & Structures) : approved

Execution

Qty. of earth work done : 5.5 Lakh Cum against 6 Lakh Cum.

Qty. of concrete work done: 2500 cum against 30,000 cum

Structure
: 25 Nos. executed against 110 Nos.

Expenditure
: Rs. 16.68 Crs. against 36.79Crores

Mob. Adv. Paid
: Rs. 3.68 Crs.

Mob. Adv. Recovered
: Rs. 0.70 Crs.

Land Acquisition
: Required 800 Acres, Requisitioned 459 Acs Acquired – 236
: 34 KM length in progress against total length of 39 KM
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 20/Cat- : (i) Formation of Earth
Name of the Contractor : M/s KNR-SLEC (JV), Hyd.
Dam of Budpur with FRL +352m (ii)
Agreement Amount
: Rs. 36.98Crs
Agreement Date
: 07-03-2005
Period of Completion
: 24 Months (8 milestones)
Construction of spillway, (iii) Construction
of Head Regulator to let out into left and
right main canals.

Investigation
: Completed (6.10 KM)

Designs
: Approved

Execution
: Qty. of earth work 5.64 Lakh cum completed.

Expenditure
: Rs. 15.43 Crs. (Inc. Mob. Adv. Rs. 3.43 Crs.) against Rs. 36.98Crs.

Mob. Adv. Recovered
: Rs. 1.37 Crs.

Machinery deployed
: Excavator-1No., Tippers-5No., Dozer-1No., Other M/C-7Nos.

Land Acquisition
: Required 2073.11 Acres, Requisitioned- 2073.11 Acs Acquired –
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 21/Cat-II : Investigation, Designs
Name of the Contractor : M/s S.V.E.C Co., Hyd.
and excavation of left main canal, distributary
Agreement Amount
: Rs. 60.39 Crores
Agreement Date
: 25-02-2005
Period of Completion
: 24 Months (milestones)
system including construction of CM & CD
works from budpur Balancing reservoir,
Budpur (V), Atmakur (M), Mahabubnagar (D)
to feed about 32,000 Acres
 Investigation
: completed (32 KM)

Designs (HPs & Structures) : Length 28.65 Km approved against 37.825Kms.

Execution (Canal)
: 28.10 KM length in progress against total length of 37.825KM

Structures
: 13 Nos. executed against 79 Nos.

Machinery deployed
: 10Nos. (Tippers-4Nos, Poclains-4Nos, DRR-1No,Dozer-1No.)

Land Acquisition
: Required 1386 Acres, Requisitioned: 316Acs Acquired – 98
Acs.

Expenditure
Crs.
: Rs. 18.04 Crs. (inc. mob. Adv. Rs. 6.04 Crs.) against Rs. 60.39
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. 22/Cat- : Investigation, Designs
Name of the Contractor : M/s S.V.E.C Co., Hyd.
and
Agreement Amount
: Rs. 26.73 Crores
Agreement Date
: 25-02-2005
Period of Completion
: 24 Months (8 milestones)
excavation
of
right
main
canal,
distributary system including construction of
CM & CD works from budpur Balancing
reservoir,
Budpur
(V),
Atmakur
(M),
Mahabubnagar (D) to feed about 32,000 Acres
 Investigation
: Completed (15.025 KM)

Design (HPs)
: Approved

Execution (Canal)
: 14.50 KM length in progress against total length of 15.025KM

Qty. of earth work done : 2.86 Lakh cum against 2.95 Lakh cum

Qty. of concrete work done: 5200 cum

Structures
: 23 Nos. executed against 54 Nos.

Expenditure
Crs.
: Rs. 14.68 Crs. (Inc. Mob. Adv. Rs. 2.68 Crs.) against Rs. 26.73

Mod. Adv. Recovered
: Rs. 0.73 Crs.

Machinery deployed
: 13Nos. (Tippers-4Nos, Poclains-7Nos, DRR-1No,Dozer-1No.)

Land Acquisition
: Required 354 Acres, Requisitioned: 212Acres Acquired – 128
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. OC (Pkg. 27): Investigation, Name of the Contractor : M/s KNR Const. Ltd. &
Design,
excavation
of
left
main
canal,
distributary system including construction of
CM & CD works from Sankarsamudam
BPL (JV)
Agreement Amount
: Rs. 149.40Crs.
Agreement Date
: 9/2005
Balancing Reservoir .
AGREEMENT DATE :
9/2005
INVESTIGATION and DESIGNS are in PROGRESS
Financial – Rs. 7.47 Crores (Mob. Adv. Only) against Rs. 149.40
Crores
Land Acquisition:
 Required
: 3,000 Acs.
 Requisitioned
: 169.95 Acs.
 Acquired
: Nil
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. EPC / OC- : LIFT-I : Design,
Name of the Contractor : M/s Patel Engineering Ltd.
manufacture, supplying & erection of pumps,
Agreement Amount
: Rs. 383.349Crores
Agreement Date
: 07-03-2005
Period of Completion
: 30 Months (10 milestones)
motors, electro mechanical works, including
tunnel, cistern and pump house etc.

Investigation
:Completed (3.0725 KM)

Designs (Tunnel, Pump House, Surge pool, Cistern) : 2.70 KM approved against 3.0705

Execution
: Excavation in progress (approach channel, tunnel, surge pool & Pump
house)

Qty. of earth work done : 5.50 Lakh Cum against 7.82 Lakh Cum.

No. of Machinery
: Deployed = 8 Nos (Excavators = 6 Nos., Dozers = 2 Nos. etc)

Land Acquisition
: Required 250 Acres, Requisitioned 218Acs Acquired – 111
Acs.

Expenditure
19.58 Crs.)
: Rs. 52.16 Crs. against Rs. 383.34 Crs. (Mob. Adv paid – Rs.
RAJIV LIFT IRRIGATION SCHEME
(BHIMA PROJECT)
Package No. EPC / OC- : Design and
Name of the Contractor : M/s NEC – NCC – MAYTAS (JV
execution of Stage-I and stage-II pumping
Agreement Amount
: Rs. 391.55 Crores
Agreement Date
: 14-03-2005
Period of Completion
: 30 Months
stations of
lift-II at Thirumalayapalli &
Kothakota (M), Mahabubnagar (D) on EPC
basis.

Investigation
: Completed (3.132 Kms)

Designs (Tunnel, Pump House, Surge pool, Cistern) : Approved

Execution

Qty. of earth work done : 1,70,000 Cum against 5 Lakh Cum.

No. of Machinery
: Excavation 0.383Km in progress (approach channel, tunnel,
surge pool & Pump house)
: Deployed = 18 Nos (Excavators = 4 Nos., Dumpers = 12 Nos.,
Dozers = 2 Nos. etc)

Land Acquisition
: Required 135 Acres, Requisitioned 67 Acs. Acquired – Nil

Expenditure
: Rs. 71.58 Crs. against Rs. 391.55 Crs.

Mob. Adv. Paid
: Rs. 19.58 Crores.

Mob. Adv. Recovered
: Rs. 6.00 Crores.