MPERC Comments on CERC Paper on Terms and Conditions of …

Download Report

Transcript MPERC Comments on CERC Paper on Terms and Conditions of …

Terms and Conditions
of Tariff
MPERC Comments on CERC Discussion Paper
Madhya Pradesh Electricity Regulatory Commission
In this presentation
Market Development
– Transmission and wheeling charges for Transmission Lines
– Transmission and wheeling charges for Inter-regional Lines
Tariff Setting
– Rate of return methodology
– Depreciation
– Development Surcharge
– Rate base
– Interest on working capital
– Operational norms
Other Discussion Points
2
Madhya Pradesh Electricity Regulatory Commission
Market Development
Madhya Pradesh Electricity Regulatory Commission
Market Development
Transmission and Wheeling Charges
Pan Caking (2.3.3.2)
 Definition: Term used to describe stacking up
of charges in a transmission system due to
repeated application of charges for different
regions
 Implications
– Increase in the landed cost of power
– Discouragement to inter regional
exchange of power
 Comments
– Open Access mechanism of Regional
Incremental Postage Stamp
4
 Mechanism of charging
– Original Beneficiaries cover full cost
– Reimbursed by income from Open
Access Charges and from Traded Power
 Comments
– Expansion of network should be done on
the basis of a Long-Term Transmission
Capacity Demand Forecast (Example: 7Year Plan in UK)
– Commission must regulate the level of
investment by CTU / STU and ensure
that it is at a certain margin above strictly
required.
Madhya Pradesh Electricity Regulatory Commission
Market Development
Transmission and Wheeling Charges for Inter-Regional Lines
Charging of Fixed Costs
 Present system of sharing of costs of Interregional assets is 50:50 between Regions.
 Method of charging should be changed to
allocated usage basis.
– Provisional fixed costs may be charged
based on Allocation of Capacity in
Agreement between CTU and
Beneficiaries
– Adjustments to be made at the month-end
based on actual allocation. These
adjustments may be billed in next months
bill
5
Sharing of Income from Open Access /
Traded Power
 Should be adjusted on a monthly basis
 Should be returned to Firm Users in the
proportion of costs paid in that month
Madhya Pradesh Electricity Regulatory Commission
Tariff Setting
Madhya Pradesh Electricity Regulatory Commission
Tariff Setting
Rate of Return
Existing methodology
ROCE, ROE and Return on Debt
 Cost-plus approach
 ROE:
– Interest rates have reduced
– Escrows and LC’s are established
– Suggestion: Government Bond Return + 5% =
say 11%
Options
 ROE
– Return to equity investment is measured
 ROCE (= ROI)
– Return on total investment is measured
– Measured against WACC
– Incentive for optimization by financial
engineering / refinancing – incentive to
investors
– No FERV
– Beneficial to consumers
 ROCE may be adopted
7
 Margin to cover:
– Risk premium
– Investment incentive
 Return on Debt @ PLR
 Normative Debt Equity Ratio: 80:20
 ROCE = 11*80/100 + 11*20/100 = 11%
 Annual revision, retrospective-forward
compensation or through VCA
Madhya Pradesh Electricity Regulatory Commission
Tariff Setting
Depreciation, Development Surcharge
Depreciation
Development Surcharge
 Purpose of depreciation
– Wear and tear
– Repayment of loan
 There should not be any such surcharge on the
beneficiaries for the purpose of creation of corpus
for investment in generation
 Comments
– Allow to explicitly charge loan repayment
– After full loan repayment, balance
depreciation may be charged on SLM till
useful life of the plant
– Develop norms for loan repayment
 Reasonable return is being provided
– Rate = PLR
– Term of loan = Moratorium +
Minimum 10 years
8
– Buyers must be protected by ensuring term of
PPA is for the fair life of the plant. If such an
assurance is not given, then depreciate at the
current rates
 Instead, a Developmental Charge may be levied
for a "Universal Service Obligation" Fund
 USO Fund can be used for improving access to
all
– Rural electrification programs
– Promotion to non-conventional sources
– Off-grid generation
Madhya Pradesh Electricity Regulatory Commission
Tariff Setting
Rate Base, Interest on Working Capital
Rate Base
Interest on Working Capital
 Asset-side NFA approach
 Allow interest portion as pass-through on net
Normative Working Capital
Initial Capital Expenditure
 Initial Capex:
– In case a prior order exists: As per the order
– In case prior order does not exist: Should be
determined by competitive bidding.
 Net of working capital may be derived after
deduction of fuel costs
 Norms must be developed by the CERC / CEA for
setting up of projects for quality of equipment,
costs, gestation, competitive bidding processes for
EPC etc
 Additional Capex:
– Allow subject to prior approval by the CERC
– Or, norms may be developed for this
9
Madhya Pradesh Electricity Regulatory Commission
Tariff Setting
Operating Norms
Operating Norms
Generation – Gross Calorific Value
 Define operational norms; this should consider
technology in place, inflation, age of the plant /
equipment
 Price of coal is notified based on UHV and coal
consumed is determined based on GCV
Operation and Maintenance Expenses
 There is a need of fixing norms for linking UHV with
GCV.
 Pass-through on actuals subject to a limit as a
percentage of capital costs
 Norms for stacking and transit losses should also be
fixed based on transport mode and distance
 Allow a portion of the savings to be retained
Generation – Specific Oil Consumption
Generation – SHR
 Norms should be reduced to 2 ml/kwh from the
current 3.5 ml/kwh if the target PLF is above
normative
 Should be linked with guaranteed heat rate. A
reasonable margin should be provided above this
which should keep in view the age of the plant
10
 At low PLF Specific Oil Consumption is higher to
keep the furnace stable. Higher Sp.oil consumption
can be allowed at low targeted PLF
Madhya Pradesh Electricity Regulatory Commission
Other Issues
Madhya Pradesh Electricity Regulatory Commission
Other Issues
Tariff Period
Peak and Off-peak Tariff for Hydel
 MPERC suggestion
– 5-year period, which is a business planning
cycle
– May be reviewed before in case of drastic
change
 MPERC suggestion
– Apply to depreciated hydel plants for peak
period
– Off-peak tariff need not be changed
– Surplus income may be paid into a "Universal
Service Obligation" fund for to provide access
to all
Declared Capacity
 Current Definition / Analysis
– One MWh ex-bus capacity
– Scheduling is on MW basis
 MPERC suggestion
– Change definition to MW basis
12
Single Regional Tariff
 MPERC’s views
– Promotes generation from lower cost stations,
since they now earn more, but an expensive
generator will not generate
– Not recommended
– Individual tariff setting is preferable
Madhya Pradesh Electricity Regulatory Commission
Other Issues
Auxiliary Consumption
 Current
AxC =
[Σ KWH Generator terminal –
Σ KWH delivered at station switchyard]
[Σ Gross generator terminal]
 Proposed
AxC =
[Σ KWH Generator terminal –
NET Σ KWH exported ex-bus]
[Σ Gross generator terminal]
 MPERC suggestion
– Do not adopt the proposed change. A change
will result in beneficiaries bearing the cost of
losses between switchyard and bus
13
Madhya Pradesh Electricity Regulatory Commission
MPERC
Madhya Pradesh Electricity Regulatory Commission
Pan caking
TC = 10
Rourkela
WC = 12.5
212.5
200
Exportin
g Region
Raipur
ER
TC = 10
Chandrapur
TC = 10
WC = 12.5
Ramagundam
TNEB
SR
242.5
255
Selling price = 200 P/U
Landed cost = 255 P/U
Thus, pan caking is a major disincentive to inter regional sale
Numbers are purely for the purpose of illustrating the concept and may not be correct
15
Madhya Pradesh Electricity Regulatory Commission
Transmission / OA Charges
Inter-Regional Lines
Units
Monthly Charge
Crores 100
Allocated usage
MU
Ratio
Charge
Crores
Open Access Income Crores 20
Refund / Adjustment Crores
Net Cost
Crores
16
East-West Link
East Zone Users
E1
E2
E3
E4
800
8%
8.0
500
5%
5.0
700 1,000
7%
10%
7.0
10.0
1.6
6.4
1.0
4.0
1.4
5.6
2.0
8.0
West Zone Users
W1
W2
W3
W4
Total
1,200 1,600 2,400 1,800
12%
16%
24%
18%
12.0
16.0
24.0
18.0
10,000
100%
100
2.4
9.6
3.2
12.8
4.8
19.2
3.6
14.4
20
80
Madhya Pradesh Electricity Regulatory Commission
Tariff Setting
Operating Norms
Grade
A
17
UHV (Kcal/Kg) Ash + Moisture
Range
Range
> 6200
Upto 19.6
GCV Kcal/Kg
@ 5% Moisture @ 7% Moisture
> 6450
> 6350
B
6200 – 5600
19.6 – 23.9
6049 – 6454
5940 – 6360
C
4950 – 5600
23.9 – 28.7
5597 – 6049
5490 – 5940
D
4200 – 4940
28.7 – 34.1
5089 – 5597
4990 – 5490
E
3360 – 4200
34.1 – 40.1
4524 – 5089
4400 – 4990
Madhya Pradesh Electricity Regulatory Commission