WisDOT Implementation
of
3D Technology & Methods
in
Design & Construction
2009 Contractor/Engineer Conference
WTBA & WisDOT
January 21-22
Jerry H. Zogg, P.E. , WisDOT
3D Implementation
WisDOT has worked on a number of 3D
initiatives for several years:
Some were recognized as being directly
related to 3D technology
Others were not
Hasn’t been much of a coordinated effort
3D Implementation
Recent prominent initiatives:
3D Design process including selection
of Civil 3D as design software
– State-of-the-art 3D dynamic modeling
capabilities
GPS machine guidance for grading
– statewide option for 2009
3D Implementation
Recently realized need for a more
comprehensive/coordinated effort
– A number of related & supporting initiatives
– Implementing 3D technologies is a national
trend
Many engineering & construction benefits
A number of challenges & issues
Have a project underway to develop an
overall implementation plan
3D Implementation
Project Participants:
Principle Investigator:
– Alan Vonderohe,CMSC
Advisory Group:
– WisDOT
– WTBA
– ACEC
Workshop Attendees
3D Implementation
Conducting Project in 2 Phases:
Phase 1:
Preliminary Study
(April – Oct 2008)
Phase 2:
Develop Prioritized Plan
(Nov – April 2009)
3D Implementation
Activities in each Phase:
Develop Vision & Objectives
Perform Research
Prepare Interim Report
Conduct Workshop
Complete Final Report
Phase 1 - Preliminary Study
Title: Implementing Digital Terrain Models (DTM) for
Construction Plans & Determining Earthwork Quantities
Vision: Adoption of 3D methods and seamless data flows
throughout initial survey, design, contracting, construction,
as-built survey, and payment processes.
Objectives:
– Identify institutional issues, relevant design and
construction work processes, consequences, and legal
issues associated with realizing the vision.
– Suggest strategies for addressing the issues.
Stakeholder Workshop
September 18, 2008
Workshop Objective:
– Provide a forum for participation by the stakeholder
community in achieving study objectives.
Breakout sessions:
–
–
–
–
3D model content, format, and security.
DTM data collection and data quality.
Impacts, training, and communication.
Implementation planning.
Where We Are And Where We Want
To Be
Current
The Vision Goes Even Further
Future
Oct. 22 Adv Group Meeting
Agenda & Outcome
Agenda
Review Workshop outcomes from Each
Breakout Session
Develop recommendations for the final
report and determine the path forward.
Outcome
Expand the vision statement
Develop a high-level implementation plan
Phase 2 - Implementation Plan
3D Technologies & Methods for
Design & Construction
Advisory Group Meetings
November 17, 2008
December 17, 2008
January 20, 2009
3D Imp Plan - Phase 2
Vision and Scope
Vision:
– Adoption of 3D methods and seamless data
flows throughout initial survey, design,
contracting, construction, as-built survey,
payment, and other applications included
within the infrastructure lifecycle.
Scope:
– Design and construction along with
identification of links to operations,
maintenance, and planning.
3D Imp Plan - Phase 2
Objectives
Develop a prioritized implementation plan to
move WisDOT toward the vision
Focus plan on 3D initiatives within WisDOT
Link Sept Workshop Issues & Outcomes to those
initiatives
3D Imp Plan - Phase 2
Adv Group Activities
To accomplish Phase 2 Objectives, Adv Group
working to initially:
Identify 3D initiatives
– Currently underway
– New
Determine topics to be addressed with each
initiative
Develop other implementation
recommendations
3D Imp Plan – Phase 2
Six Initiatives:
3D Design Process
Automated Machine Guidance
Height Modernization Project (HMP) &
Continuously-Operating Reference
Stations (CORS)
Original Ground DTM
Inspection & Final Quantities
Post Construction Uses of 3D As-Builts
3D Design
Process
GPS Machine Guidance
Height Modernization
Project
(HMP)
Continuously Operating
Reference Stations
(CORS)
3D Imp Plan – Phase 2
Six Initiatives:
3D Design Process
Automated Machine Guidance
Height Modernization Project (HMP) &
Continuously-Operating Reference
Stations (CORS)
Original Ground DTM
Inspection & Final Quantities
Post Construction Uses of 3D As-Builts
Implementation Plan
Topics to be addressed for each 3D
initiative:
Status
Issues
Timeline & Expectations
Level of Effort
Benefits
Relationships with other Initiatives
Recommendations
Short & Long Term Goals
Stakeholders & Responsibilities
Priority
3D Imp Plan – Phase 2
Recommend creation of Mgmt Task
Force to:
Monitor Initiatives & coordinate if necessary
Create reporting structure
Keep upper mgmt informed
Advocate for overall effort
Develop outreach mechanisms for internal &
external stakeholders
Stakeholder Workshop
February 17, 2009
Objectives:
Obtain feedback on Draft Imp Plan from
wide variety of stakeholders
Conduct breakout session on postconstruction activities:
– Operations
– Maintenance
– Planning
3D Imp Plan - Phase 2
Completion
March 18 - Advisory Group Meeting
– Review outcomes of 2/17 Workshop
– Finalize content of Implementation Plan
March 31 – Complete Final Report
– Combine findings:
Phase 1 - Preliminary Study
Phase 2 - Implementation Planning Effort
April - Begin Reporting Out to DTSD Mgmt
Provide Your Input !
2/17 Workshop Invitees: Please attend
Others: Please contact Advisory Group
– Alan Vonderohe,CMSC
– Jessica Lewis, ACEC
– Chris Goss, WTBA
– Jerry Zogg, BPD
– Don Greuel, BPD
– Rick Larson, BPD
– Brad Hollister, BPD
– Kim Schauder, BITS
– Cindy McCallum, BITS
– Drew Kottke, BITS
– Dennis Keyser, NE
– Bruce Enke, NE
– Allen Gilbertson, SE
– Amy Coughlin, SW