U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Society of American Military
Engineers (SAME)
Fort Leonard Wood Chapter
Military Construction Briefing & Site Tour
Hosted by:
Fort Leonard Wood Resident Office,
Kansas City District, USACE
June 11, 2008
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
MCA Tour Timeline
Time:
Event:
11:30 – 11:45
Gather at Tech Park
11:45 - 12:00
Welcome Guests; Pick-up Box Lunches
12:00 – 12:25
MILCON Briefing
12:25 – 12:30
Safety Briefing, Issue Hard Hats
12:30-12:35
Walk to Permanent Party Barracks Site
12:35-12:55
Walk through Permanent Party Barracks
12:55-13:00
Walk Back to Tech Park and Release
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Permanent Party
Barracks Phase I
Permanent Party
Barracks Phase II
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Agenda
•
•
•
•
•
Overview of USACE
Overview of Current Challenges
What is Important at FLW
Current Project Summary at FLW
Questions
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of USACE
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Northwest Division
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of KC District
Kansas City District
-2 Area Offices
-7 Resident Offices
-18 Lakes
-2 Hydro Power Dams
-350 Structures on Mo
River (Revetments, Wing
Dikes, Levees)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of FLW Resident Office
Northwest Division – COL Miles
Engineering & Construction Division (E&C)
Kansas City District – COL Wilson
-Engineering & Construction Division (E&C)
-PM Division
Kansas Area Office
MO Area Office (5 Personnel)
-Area Engineer / ACO w/ $500K
Warrant
-Mechanical Engineer
-Electrical Engineer
-Office Manager & Secretary
WAFB Resident Office (9 Personnel)
KC Resident Office (8 Personnel)
FLW Resident Office (22 Personnel)
-Resident Eng. / ACO w/ $500K Warrant
-Deputy Resident Engineer
-Submittals Technician
-3 Office Engineers
-4 –Quality Assurance Teams
-1 – QA Rep at GLWACH
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current Challenges
• Army moving into the most comprehensive
restructuring since WWII
– USACE is planning to execute $40 Billion of MILCON Construction
from 2006 – 2011
– At FLW alone, our construction placement will increase from about
$40 Million a year to over $200 Million a year through FY 08 and FY
09
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current Challenges
• The army is transforming and has immediate needs that
must be met to support BRAC and the GTA Programs as
well as re-stationing initiatives:
– The recently released Army Stationing Plan, for example, will add
approximately 74K new Soldiers to the Army over the next 2-4 years
– This plan will also add 6 new BCTs and 8 new MEBs which will be disbursed
at various posts across the country
– This plan also re-stations units formerly stationed overseas to CONUS
military bases
– FLW for example is receiving approximately 3,000 plus additional trainees
this summer through the TRAPS program and is also receiving a FORSCOM
MEB in October
• Creates Need for additional Barracks Bed Space, family housing, dining
facilities, etc…)
• Creates Need for additional infrastructure (sewage, water, phone lines,
roads, training ranges, parking, etc… to support influx of personnel)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current Challenges
• The GWOT has created several unique demands:
– USACE oversees massive construction programs supporting OIF and
OEF through the GRD and AED
– On the home front, the army is also involved in improving living
conditions and programs for soldiers and families to take care of them
and improve retention rates (Examples: improving housing, post
facilities, Warrior in Transition Units, etc…)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Overview of Current Challenges
• To support these and many other programs, the army has
a need for USACE to deliver projects faster and cheaper
with more sustainable designs and without diminishing
quality
• In order to stay relevant in meeting the Army’s needs,
USACE is itself transforming and thinking outside of the
box and changing its systems and ways of doing
business
– MILCON Transformation
– At the local level, we are also doing a lot to stay relevant and
meet our immediate customer’s needs and expectations
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
What is Important at FLW?
• IET Soldier Bed Space (TRAPS Relocatables,
TBUP, and Starship Barracks)
• Facilities for Future Combat Support Brigade
• Upgrading Post Infrastructure to support the large
increase in facility demands (ie…sewer, roads,
phones, etc…)
• Upgrading Ranges to support training for TRADOC
and FORSCOM Units
• Supporting the installation’s Master Plan
development and implementation
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
BT / OSUT & AIT
Long Term Transition Plans
Renovating through TBUP Program over
next 4-8 years
TRAPS Relocatables
Rolling Pin Barracks –
(Built 1950s to 1960s)
Starship Barracks
Complex
• Over the next 10-25
years, the installation
wants to replace rolling
pin barracks and
Specker barracks with
over 15 phases of
Starship Complexes
• Provide immediate
bed space for BT and
AIT Soldiers to meet
Summer Surge /
TRAPS Requirements
Recently Renovated by CENWK-EC-MD
Specker Barracks (Built in 1970s)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Long Term
Master Plan for
FLW
• Segregate BCT, AIT,
Permanent Party, and
FORSCOM Zones of FLW
• ADPs are being developed in
these areas by KC District
• Phases of implementation:
• Move non-applicable
facilities out of zoned areas
• Renovate existing facilities
while implementing long
term plans to build new
facilities
N
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Project Summary - FLW
MILCON Projects: ($101.2M)
Project Name:
Contract Completion Date:
Permanent Party Barracks - Phase I (The First of Five
Phases Awarded)
21-Dec-07
Permanent Party Barracks - Phase II
25 Sep-08
Basic Combat Training Barracks Complex
31 Jan 10
Child Development Center
30 Jun 10
Photos of Permanent Party Barracks Phases I & II to Follow
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – Permanent Party
Barracks Phase I
Permanent
Part Barracks
– Phase I
Completed
Photographs
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – Permanent Party
Barracks Phase II
• 19 Additional Buildings
currently under construction
• A third GTF Phase is to be
awarded this spring to construct
27 additional barracks
• Phases IV and V are also
being considered as potential
supplementals in the Murtha Bill
for FY 08
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Project Summary - FLW
O&M Projects: ($95.1M)
Project Name:
Contract Completion Date:
Specker Barracks Renovation - Phase II
Training Barracks Upgrade Program
30-Mar-08
828 & 829 due 6 Jun 08
TRAPS Relocatables 07
07 Apr 08
TRAPS Relocatables 08
15 Jun 08
Photos of Specker Barracks, TBUP, and TRAPS 07 Sites to Follow
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – Specker Barracks
Renovation
Specker Complex
Interior Work Improved Appearance & Provided Adequate Airflow
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – TBUP Phase I
BKJ adding Bump out
portion of Bldg 829
Bldgs 828 & 829 Must be turned
back to FLW by 6 Jun 08
QA, George Edgington, conducts Initial Inspection of Block Shear Wall Construction
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – TBUP Phase I (Continued)
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Current Projects – TRAPS 07
Major Setbacks in a 120 Day Contract include 1) Design Development & Review,
2) Permits, 3) Ordering and Delivering Trailer Units, 4) Obtaining Transformers
Interior Finishes of TRAPS 07 Barracks
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Upcoming Projects - FLW
Projected FY08 Projects
Project Name:
Acquisition
Strategy:
Funding
Type:
New Double Dining Facility – GTF
D-B
MCA
Range 7 & 8
D-B-B
MMCA
Combat Pistol Range
D-B
GTF
Multiple Purp. Machine Gun RNG
D-B
GTF
TBUP Renovation – Phase II
D-B
O&M
Permanent Party Barracks - GTF
D-B
GTF
Sewage Treatment Plant
D-B
Unit Operations Facility
D-B
MCA
Chapel
D-B
MCA
Sapper Leader Course Design Directive
D-B
MCA
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Upcoming Projects - FLW
Projected FY08 Projects
Project Name:
Acquisition
Strategy:
Funding
Type:
Permanent Party Barracks – Ph. I
D-B
MCA
Permanent Party Barracks – Ph. IV
D-B
MCA
Consolidated TMC
D-B
MCA
94th EN BN HQ Complex
D-B
MCA
Company HQ Bldgs (times 2)
D-B
MCA
Vehicle Maintenance Shop
D-B
MCA
* Note: There are about $87M in potential supplemental contracts. It is not looking at this point as though the
Murtha Bill will include these supplementals, but this office is preparing to staff them in the event they are awarded.
U.S. ARMY CORPS OF ENGINEERS KANSAS CITY DISTRICT
MISSOURI AREA OFFICE OVERVIEW
Questions