Framework Guidelines
on System Operation
Process
Uroš Gabrijel (ACER)
Presentation Workshop, Ljubljana, 24 August 2011

Content
..
..
.
Introduction
Process description
State of play
Details on public consultation
Next steps
2

Introduction (1)
.
.
During the “interim period”, ERGEG assumed the role
assigned to ACER by the 3rd package and worked on
“pilot” Framework Guidelines (FG)
ERGEG has been working on three FG:
»
»
»
Electricity Grid Connection
Capacity Allocation and Congestion Management
System Operation
3

Introduction (2)
.
.
Work on drafting the FG on System Operation was
concluded under ACER
ACER was invited to submit to the Commission, by 31
December 2011, a framework guideline on electricity
system operation
4

.
Process description (1)
General timeline as set out in Reg. (EC) 714/2009
Agency prepares
Framework
Guidelines
EC
requests
Agency to
submit
framework
guidelines
EC defines
priorities
for
network
codes
12 Months
ENTSO prepares
network codes
EC requests
ENTSO to
submit
network code
ENTSO
submits
network code
to Agency
3 Months
Agency
reviews
network
codes
COMITOLOGY
6 Months
Agency
submits
network code
to EC when
satisfied,
recommending
approval via
Comitology
5

Process description (2)
..
Annual priority list − Commission
.
..
..
Consultation with ACER, ENTSO-E, other relevant
stakeholders
Areas for the development of FG/NC
Initial Impact assessment − ACER
To support the development of the FG
Expert group representing wide industry perspective
Identification of problems / objectives / policy options
6

Process description (3)
..
Framework Guidelines (FG) − ACER
..
..
..
Invitation from the Commission to draft FG
Public consultation
Adoption of the FG / Submission to the Commission (6
months)
Network Codes (NC) − ENTSO-E
Commission request
ENTSO-E prepare the NC in line with the FG (12 months)
ACER reasoned opinion on NC (3 months)
7

State of play
..
ACER deliverables on FG (2011 Work Programme)
..
.
Electricity Grid Connection (finished)
Capacity Allocation and Congestion Management (finished)
System Operation (on-going)
Balancing (to be delivered in mid 2012)
8

Details on public consultation (1)
.
.
Public consultation on Draft Framework Guidelines on
System Operation
.
»
Run from 15 July to 15 September 2011
Email-based consultation
»
Submission of comments to:
[email protected]
»
Personal details should be enclosed
Constructive and comprehensive responses
»
Large companies invited to coordinate their answers
internally
9

Details on public consultation (2)
.
.
Questionnaire to steer the structure of responses
» 8 general issues, 4 specific issues
Transparency
»
»
Responses will be published on the ACER
website
Comments marked confidential will be considered
but not disclosed
10

Next steps
.
.
.
Public consultation
» On-going
» Ending on 15 September 2011
Evaluation of responses
» Within approximately two months
Finalization of the FG
» Submission to EC by 31 December 2011