Transcript Front-End of Project X at FNAL
MuCool Test Area RF Workshop
Derun Li Center for Beam Physics Lawrence Berkeley National Laboratory November 15, 2010
MAP RF Goals
Develop a workable solution for high gradient NCRF operating in B fields between approximately 3 and 6 T.
Support sub-assembly prototyping for the 6D cooling bench test.
1. Guggenheim 2. FOFO Snake 3. HCC MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 2
Workshop Goals
• • •
Review the status of the MTA RF programs Review proposed future RF programs Discuss RF R&D strategy to respond to the comments and recommendations from the MAP Review in August 2010
–
Scope of the work of MAP RF proposal
–
Resources
–
Schedule and milestones
–
Concerns/Risks MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 3
Current RF Programs
•
Targeted R&D programs to understand the RF breakdown problems in magnetic fields
a workable solution
— Physics models and numerical simulations, — Experimental programs and new techniques at 805 and
201 MHz
The 805-MHz with RF buttons
High pressure cavity
ALD to eliminate field emission
Be wall cavity
Box cavity to study E x B effects
Magnetic field insulated cavity
Physics model to understand RF breakdown in magnetic fields MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 4
Future RF Programs
• • • • • • •
Magnetically insulated box cavity Beam test of HPRF cavity The 805-MHz RF button tests (Be) Update design of 805-MHz cavity Dielectric loaded cavity Design and fabrication of Be-wall cavity ALD processed buttons in pillbox cavity
• •
201-MHz cavity test with coupling coil magnet at MTA Complete MICE 201-MHz cavity
•
Single cavity vessel MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 5
Comments from the MAP Review
More cavities and tests International RF Workshop
MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 6
Comments from the MAP Review
Concerns on beryllium
MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 7
RF Recommendations from MAP Review
MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 8
In respond to the MAP Review
• •
Update RF proposal
–
Revisit previous plans + this WS
–
Schedules and milestones
–
Exploring more RF tests in magnetic fields
•
Design and build more cavities + RF tests
•
SLAC group: 2-T SC magnet and tests at s- or x-band frequencies
–
International workshop on high-gradient RF cavities Wish we have a productive workshop MTA RF Workshop, D. Li, Lawrence Berkeley National Lab, November 15, 2010 9