Buyout of the State Transportation Improvement Program (STIP)

Download Report

Transcript Buyout of the State Transportation Improvement Program (STIP)

Monterey Branch Line
Association of Environmental Professionals
and
American Planning Association
July 28, 2010
Monterey Peninsula:
Why do we need rapid transit?

Two-lane highways

Congestion; Buses
also stuck

Highway widening
opportunities limited

More future growth
along the corridor

Green alternative
•Goal: Reestablish
rail/rapid bus service on
Monterey Branch Line
•Purchased from Union
Pacific in 2003
•Many alternatives
studied since purchase
Light Rail
Benefits

High Capacity Vehicles


100 passengers
Ability to add train cars

Quiet

Low Emissions

Safe

Supports Transit Oriented
Development

Carries:



wheelchairs
Bicycles
MST Operates
Initial Phase
• Every 15 to 30 Minutes
• Transfer to Salinas
Characteristics:






Custom House Plaza
- Marina Green
10.15 miles fixed
guideway
Peak: 15 minutes
Off-peak: 30 minutes
6 vehicles
11 stations



Capital Cost: $145.0M
Operating Cost: $4.2M
Boardings (Daily): 3,725
Monterey Branch Line:
Transit-Oriented Development

Reservation Downtown

Dunes at Monterey
Bay

8th St. Art District

CSUMB

Seaside Broadway
Urban Village
Environmental Review

Environmental Documents


State
Federal





Conceptual Engineering



Noise/Vibration
Safety
Crime
Sea Level Rise
Station Development
Off-site Traffic Access Improvements
Federal Transit Administration Small Starts
Report Preparation
Funding

Capital

Secured


Spent
Unsecured
$ 145 M
$ 25.0 M
$ 12.4 M
$120.0 M
Federal Small Starts
 State Public Transportation Account
 Impact fees


Operations


Fares
Lease Revenues
$ 4.2 M /year
$ 1.1 M
$ 3.1 M
Short-Term Activities



Alternatives Analysis
Selection of Preferred Alternative –
Oct. 2009
Public Outreach




Visual Simulation
Public Hearings
Draft Environmental Document –
Dec. 2010
Final Environmental Document –
July 2011
Monterey Branch Line: Timeline
Monterey to Marina
 Environmental
Documents
 Engineering & Design
 Construction
 Start of Service
2009-11
2011-12
2013-14
2015
Questions?