Transcript Slide 1

Florida Public Service Commission
2007 Hurricane Preparedness Briefing
May 23, 2007
Kissimmee Utility Authority
Ken Davis
Vice President
Engineering & Operations
KUA System Data
• Serves approximately 64,000
customers in Osceola County
• Distribution
– 857 Miles of Distribution Lines
• 41 % Overhead
• 59 % Underground
– 9 Substations
– 47 Feeder Circuits
– 15,000+ Poles (majority wood)
KUA System Data
• Transmission
–72 Miles of Transmission Lines
–230 kV and 69 kV
–63% of Poles Concrete or Steel
–37% Wood (will reduce to 27% by
2008)
2004 Hurricane Experience
• Charley
–100 % Customers Lost Power
• Frances
–36 % of Customers Lost Power
• Jeanne
–59 % of Customers Lost Power
Lessons Learned
• Hired James Lee Witt, Associates to
Conduct Independent Assessment of
Preparation for and Recovery From
Storms
• Improve Communications with
Customers During Restoration
• Can’t Rely Solely on Media for
Communications
Lessons Learned
• Better Define Roles of All
Employees
• Closer Coordination with EOC for
Restoration Priorities
Hurricane Preparedness
Construction Standards
• Poles Designed to NESC
Extreme Wind Loading
–All New Construction
–Major Expansions or Relocation
Projects
–Targeted Critical Structures
Construction Standards
• 27% of Wooden Transmission
Poles to be Replaced with Steel
and Concrete
• Redundant Circuits to All
Hospitals with Automatic Transfer
Scheme
Construction Standards
• Selected Overhead to
Underground Conversions
• Underground Utilities Required in
All New Subdivisions
GIS/Outage Management
• All Transmission & Distribution
Facilities Tracked in GIS
• Links to Outage Management
System
• Tracks Outages Down to
Individual Customer Level
Vegetation Management
• Transmission Circuits
–Inspected/Trimmed Annually
• Distribution
–Three Year Trim Cycle
• Increased funding over 75%
Since 2004
Pole Inspection Program
• All Wood Transmission Poles
Inspected Every Two Years
• Wood Distribution Poles
Inspected on Eight Year Cycle
Facility Inspection Program
• Transmission System
–Annual Visual Inspections
–Annual Infrared Scanning
• Distribution System
–5 Year Cycle on Inspections
–Infrared Scans of All Circuits
Annually
Emergency Operations Plan
•
•
•
•
All Hazards Approach
Concentration on Hurricanes
Reviewed and Updated Annually
Follow National Incident
Management System (NIMS)
Emergency Operations Plan
• All Employees Have Pre-assigned
Roles
• Defined Set of Activities for Each
Phase of Storm Preparation,
Response and Recovery
• Pre-Defined List of Priority
Facilities
Emergency Operations Plan
• Pre-Assigned Damage
Assessment Teams
–Circuits Pre-Assigned
–Area Coordinators for Teams
• Developing Electronic Reporting
of Damage Assessment
Emergency Operations Plan
• Pre-Defined List of Restoration
Priorities
–Typical Top Priorities – Evacuation
Shelters, Emergency Operations
Centers, Hospitals, etc.
–Priorities Can be Changed by
Directive from EOC
Annual Mock Disaster Drill
• Full Scale Drill Practiced Annually
(April 12, 2007)
• All Employees Participate
• Evaluation Teams Rate Performance
• Post Drill Evaluation Conducted
• Action Items – Changes to
Processes, Facilities, Plan
Storm Response and Recovery
• Crews Assigned to Ride Out
Storm at Selected Fire Stations
–Assist First Responders with Wires
Down Situations
–Assist with Fire Calls for Power
Disconnects
Storm Response and Recovery
• Personnel Assigned to EOC at All
Times
• Regular Status Updates Given to
EOC
• Close Coordination with EOC for
Restoration Priorities
Storm Response and Recovery
• Mutual Aid Agreements
– Florida Municipal Electric Association
(Florida Municipal Utilities)
– American Public Power Associations
(National Municipal Electric Utilities)
– Florida Coordinating Group (Florida
Municipal, Investor Owned and
Cooperative Utilities)
Storm Response and Recovery
• Pre-Arranged Agreements
– Transmission and Distribution Line
Contractors
– Outside Engineering (damage
assessment and construction
management)
– Vegetation Management (Tree Clearing)
– Lodging, Catering, Laundry, etc.
Customer Communications
• Call Centers Fully Staffed 24/7
Throughout Recovery Process
• Provide Status Updates to Customers
– Emails
– Voice Mails or Text Messages
– Physically Place “Door Hangers”
QUESTIONS?
Kissimmee Utility Authority
Ken Davis
Vice President
Engineering & Operations
Phone: (407) 933-7777 Ext. 1210
Email: [email protected]