VHF Digital Link Mode 2 and Areonautical

Download Report

Transcript VHF Digital Link Mode 2 and Areonautical

GLOBAL ink
ARINC
PETAL IIe
VDL Mode 2, ATN
…and beyond
Prepared for:
ATN2001
18 September 01
Sarah MacLellan ([email protected])
ARINC proprietary
ARINC’s Goals for PETAL IIe
Demonstrate viability/suitability of CPDLC
over VDLM2/ATN
Work out many technical and ops issues
for CPDLC over VDLM2/ATN in a trials
environment
Forcing function to keep forward
momentum for CPDLC
First step toward full operations: USbased CPDLC program, and Link 2000+
ARINC proprietary
2
ARINC’s PETAL Role
Test partner with Rockwell Collins on
VDL M2
US mini-network to support AAL
certification
European network, coverage for
Maastricht UAC airspace
ARINC proprietary
3
ARINC-Rockwell Collins
VDL M2 Testing
Testing 3/00 through 4/01
• AVLC
- Also took advantage of concurrent AOA work
• v8208
• Integration of ATN
• End-to-end RC-ARINC-EUROCONTROL
Experimental Centre (EEC) testing 2-4/01
ARINC Ground Test Station (AGTS) in
Cedar Rapids
• Production hardware
• Production software
• Test/instrumentation code
ARINC proprietary
4
US Certification Mini-Network
AGTSs at TUL and DFW
Routers and network management in
Annapolis
Connection to EEC and Maastricht (via
EEC)
Installed early Apr 01
Test flights late Apr - end of May
• Certification flight 29 May
ARINC proprietary
5
ARINC AAL Cert VDLM2/ATN
Architecture
Tulsa
VGS
X.25 switch
Maastricht
UAC
GBIS1
ARINC
Regional
ATN
AGR1
GBIS
ATN ES - P2GWMADAP
GBIS2
AGR2
Dallas
VGS
EEC/Bretigny
NetMgt
ANP
STNA
ARINC proprietary
7
29 May Certification Flight
Final Track
2152z
ARINC European Network
PETAL IIe (VDLM2/ATN) network
• 6 VDL Ground Stations (VGSs)
• 2 Air/Ground Router/Regional Managers
(AGRMs)
• 2 Ground Boundary Intermediate Systems
(GBISs)
Installation May - June 01
ARINC proprietary
9
ARINC Petal IIe VDLM2/ATN
Architecture
Frankfurt
VGS
Berlin
VGS
Hamburg
VGS
ARINC
Regional
ATN
AGR
Frankfurt
X.25 switch
Maastricht
UAC
GBIS
Frankfurt
GBIS
ATN ES - P2GWMADAP
GBIS
London
AGR
London
London
Gatwick
VGS
EEC/Bretigny
Paris
VGS
Amsterdam
VGS
NetMgt
ANP
STNA
Expected PETAL-IIe VDLM2 Coverage
25k Feet MSL
Technical Lessons Reaffirmed
Complex interaction among air and
ground components
Lab testing only takes it so far
Flight operations necessary to identify
operational issues
ARINC proprietary
12
VDL M2 Technical Items
AEEC
• Timer values at v8208 and TP4 layers
• Timer implementation inconsistency in
specifications
• Signal Quality Parameter (SQP) calculations/
air-initiated handoff scenarios
- RF Signal in Space strength variable due to
combination of antenna location, aircraft attitude,
ground antenna pattern, and structural or
geographic influences
PETAL team completing identification,
investigation, and recommendation on all
anomalous behavior seen during the trials
ARINC proprietary
13
Programmatic
Lessons Reaffirmed
Strong central lead is imperative
• Committee and congeniality takes you only so
far - every once in a while you need a boss
Integration Team concept works
• Stakeholders committed to success
• Frequent interchange of status
ARINC proprietary
14
PETAL IIe a Success
Demonstrated viability/suitability of
CPDLC over VDLM2/ATN
Worked out many technical and ops
issues for CPDLC over VDLM2/ATN in a
trials environment
Forcing function/kept forward momentum
for CPDLC
First step for full operations: US-based
CPDLC program, and Link 2000+
ARINC proprietary
15
So where does ARINC
VDLM2/ATN go from here?
ARINC proprietary
16
VDL in Europe
PETAL network status in review
• Customer base, location
AOA coverage starts late 2001 for Airbus
• 3 VGSs (Toulouse, Lyon, Nice)
2002 and beyond: expand coverage
• AOC equipage expected to precede ATM
• Specific station/coverage schedules planned
with customers
• AOC coverage expansion ~ ACARS, as
customers equip
• Work with airlines, ATS Providers to plan
support required for Link 2000+
ARINC proprietary
17
Long Term
Planned VDL Coverage ~ ACARS
ARINC proprietary
18
CPDLC Build 1
9 Station network with redundant routers,
connections to FAA
PETAL+ functionality (network
management, PETAL II identified
modifications)
Network install 4Q01
Operational testing with FAA and AAL
through to 6/02
6/02 Initial Daily Use (IDU)
CPDLC Build 1A will drive network
expansion beginning 12/03
ARINC proprietary
19
CPDLC Build I Coverage Map
ARINC proprietary
20
US VDL Deployment
Four additional AGRMs deployed
• Annapolis (2); Chicago (2); Livermore (1);
New York City (1)
Ground stations/VDL kits installation @
3/week
• sites selected, surveyed, and installs
scheduled
Planning for 50 sites deployed by year
end 2001, remainder in 2002
ARINC proprietary
21
VDL Coverage Phases - CY 2002 Plan
175 Sites
Phase 3 fill in)
Phase 2 fill in
ARINC proprietary
22
Thank You
EUROCONTROL and
American Airlines
for PETAL IIe/ATN!
PETAL IIe single-handedly has influenced
the course of data link implementation in
Europe and US
•
•
•
•
Demonstration
Validation
Risk Reduction
First Step (breaking the chicken/egg
challenge)
ARINC proprietary
23