Transcript Slide 1

Aaron Nicholson
Beca
C/VM2 Design vs Non C/VM2
Performance Based Design
by
Aaron Nicholson
Outline
– Building Code changes
– One building - months apart
• Geometry
• C/VM2 vs PBD – what is different
• C/VM2 vs PBD – what is the same
– Risk and Responsibility Discussion points
September 2010
“Proposed changes to Building Code Requirements
and associated documents for protection from fire”
issued by the DBH for public comment.
September 2010
“Public consultation during the Building Code
review established that the level of fire safety
currently provided in the building code and the
associated Compliance Document is right…”
September 2010
“No change is proposed to the existing minimum
level of fire safety required under the Building
Code. As a result, there should be no additional
costs to the building sector arising from the
proposals in either design or construction”.
Building Code Changes
• April 2012 new C1 to C6 clauses replaced C1
to C4 clauses
• One aim was to make the building code more
specific and quantifiable in the level of
protection from fire which is required
• The changes were supported in part by the
introduction of a new Verification Method
C/VM2
Building Code Changes
• Important: The Building Code can still be met
in three ways:
• Full compliance with C/AS1-7 (as applicable)
• Full compliance with C/VM2
• Performance based design solution
Case Study: One building months apart
Ground floor
First floor
Second floor
C/VM2 vs PBD – what is the same?
• FEB process to agree approach, methodology,
inputs and tenability criteria
• Actual Tenability criteria
•
•
•
•
FED CO 0.3,
FED Thermal 0.3,
Visibility 10m,
Assessment height – 2m
• Fire and or Egress modelling required
• Peer review
C/VM2 vs PBD – what is different?
• Actual Inputs
• Prescribed rather than proposed and agreed
• Assessed tenability criteria
• Visibility not considered under C/VM2
PBD for this building:
• Visibility was the first of the tenability criteria
to fail (ASET) at 95 Seconds from ignition
• Extension of ASET achieved by smoke curtains
around voids and mechanical extract from
voids
• Extended ASET failed at 280 seconds which
was greater than RSET and therefore
complied.
CVM2 Design for this building :
• Visibility was not considered as the building is
sprinklered and less than 1000 occupants
• FED CO of 0.3 was not exceeded for in excess
of 600 Seconds from ignition
• If visibility were assessed? It failed at 95
Seconds from ignition
Differences in compliant designs:
PBD:
CVM2 design:
• Sprinklers throughout
• Smoke detection
throughout
• Smoke curtains
around voids
• Extract from voids –
required due to
modelling leakage
through curtains
• Sprinklers throughout
• Smoke detection
throughout
Questions raised:
• Were we overdesigning buildings pre building code change?
• Are we now potentially under designing buildings in certain
situations? How often does this situation arise?
• Have we therefore stepped outside of one of the original
“Statement of Proposals” which was that “No change is proposed
to the existing minimum level of fire safety required under the
Building Code”.
• As a Chartered Professional Engineer where do I sit ethically
knowing that visibility is not considered?
• Where do I sit legally – C/VM2 is deemed to satisfy so I’m safe right.
• What is the risk to the engineer professionally?
• What is the risk to the occupants of the building?
• Who is responsible?
Questions or comments?