UV14_STANAG4559_25 apr 2013_.ppt

Download Report

Transcript UV14_STANAG4559_25 apr 2013_.ppt

STANAG 4559
CST #29 Meeting
16 April 2013
Custodian: Laura Moore
Intelligence – Surveillance - Reconnaissance
4559 UV14 Test Plan Outline
(proposed)

Custodian Requirement

AEDP-2, Vol 2 (NIIA):
 Custodian: manage validation & compliance testing
 Custodian: validate STANAG is complete and understandable
 Custodian: identify deficiencies and requirements and update STANAG
accordingly
 UV14 4559 Objectives
Compliance testing; goal is 4559 compliance certification prior to UV14 execution
 Interoperability testing
 Inform STANAG 4559 future development

 Test Concept

Test Environment(s)
 Phased testing to integrate lessons from “de-risking events”
 Define, then mature the 4559 Test Suite to support UV14
 Conduct evals; collect and record data
 Write test report
Incorporate identified requirements into future STANAG 4559
Intelligence – Surveillance - Reconnaissance
4559 Test Objectives
for UV14

Evaluate National 4559 implementations for STANAG 4559 compliance

Evaluate interoperability between STANAG 4559 implementations

Evaluate backward compatibility between STANAG 4559
implementations

Evaluate ability to ingest, store and retrieve new data sources:





STANAG 4676 ISR track data
HUMINT data
CBRN data (CAN initiative)
GMLJP2 (proposed)
Identify and document new change proposals for STANAG 4559
Work required: evaluation criteria/test scripts: work with NCIA;
MAJIIC2/SOWG; inputs from Nations/CIAV
Intelligence – Surveillance - Reconnaissance
Proposed STANAG 4559 UV14
Test Structure
Op CSD
Op CSD
SOWG
Experimental
CSD
Op CSD
Operational
CSD Environment
Baseline (IDD 2.4/DM 2/2)
Experimental
CSD
Experimental
CSD
Experimental
CSD Environment
- 4559 compliance
- interoperability
Experimental
- SOA
- new data sources
Intelligence – Surveillance - Reconnaissance
4559 UV14 Test Flow

Phase I: Pre-MAJEX13




Phase II: Pre-UV14




Develop test plan:

Determine test baseline configuration

Define test suite

Develop test thread(s)
Conduct pre-EC13 compliance testing using CDTE
Conduct initial interoperability testing with compliant systems in EC-13 (if EC13 is available)
Refine test plan:

Update baseline configuration

Per lessons from Phase I testing

Per added sensor types in 4559 (4676, HUMINT, other)
Refine test suite
Conduct pre-UV14 compliance testing on CDTE
Phase III: UV14 execution

Finalize and execute test plan:

Final baseline test configuration (pre-certified CSDs participating)

Final test suite
Intelligence – Surveillance - Reconnaissance