Virtual Hub NGIL - Ian Moss

Download Report

Transcript Virtual Hub NGIL - Ian Moss

Coordinated Market
Coupling for GB
2
Virtual Hub
 Service Provision specified to create a GB Hub with open access to :
 All GB connected ICs to coordinate XB Capacity
 All Regional PXs
 Extendible to new Interconnectors / PXs
Procurement Update:
•
•
•
•
•
NGIL initiated the procurement, and will seek to ensure
that the service is able to encompass all existing and
future GB interconnectors.
Contract Notice issued July 2011
Tenderer’s shortlisted
RfP to be issued early October
Tender selection November
4
Virtual Hub
 Pre-Coupling:
 Coordinate capacity information for submission into EU Coupling solution
 Post-Coupling
 Energy Transactions on PXs
 Cross Border Nominations to TSOs
•
•
Shipping: Energy Trades
The output of the coupling algorithm is ‘net position’ of each price
area, which equates to required energy transactions on each PX hub.
Example: flow from GB to France, Net position of GB is a PX Buy, and
a France PX Sell.
GB
Flow
FR
NPS
NPB
Sells
Buys
Sells
Buys
Shipper buys energy in GB, and then sells the energy in France
Shipping: Physical Transfers
•
To Balance PX traded position, nominations required to
TSOs in order to be balanced in each country.
GB
FR
FR Import
= PX Sell
PX Buy =
GB Export
NPB
NPS
Interconnector nominations to balance shipper position in each country
•
Intra-GB Shipping: Energy Trades
The GB ‘net position’ is a combination of the ‘net position’ of each GB
PX, therefore a ‘shipper’ is needed to undertake the energy
transactions between the two GB PXs.
NP1
Buys
Sells
PX1
GB
Sells
NP2
Buys
PX2
NP2
NPGB
NPGB
NP1
FR
How the Virtual Hub fits in with the
NWE Project
FI
EE
NO
SE
NL
GB1
DK
GB
VH
IE
PO
BE
DE
GB2
AT
FR
Infinite Capacity
NWE Update







PX / TSO joint project initiated.
CASC appointed by TSOs to undertake key
project roles
PCR including TSO requirements is the basis
for coordinated matching.
Re-use of existing systems / agreements where
possible.
Budgets being prepared.
TSOs agree to cover costs of design phase.
Cost recovery on future phases to be further
discussed.