Using MS Project

Download Report

Transcript Using MS Project

USING MS PROJECT 2010

M. J. Liberatore VSB 3008

• • • Project management software programs such as Microsoft Project 2010 can be used for developing the project schedule and budget, and tracking actual vs. planned progress We demonstrate the use of MS Project 2010 for a sample project • Complete model found in construction.mpp on class web page Begin by launching MS Project 2010

MS Project 2010 Setup

• Select

File, Options

, click on

Schedule” tab • For Calendar options for this project: “Select “All New Projects” • For Scheduling options for this project: select “All New Projects” • For New Tasks Created: select “Auto Scheduled” • For Duration is entered in: select “weeks” • For default task type: select “fixed duration” • make sure New tasks are effort driven is

NOT

checked • Click

OK

when finished

MS Project 2010 Setup

Creating a Project

• Click on

Project, Project Information

, select 10/3/11 as the Start date, click

OK

• Click on

Save as

, type in project name such as

Demo

, click

OK

• Your project is saved as Demo.mpp

Creating a Project

Example Project

4 5 6 7 8 9 10 1 2 3 Task, Duration, and Immediate Predecessor Information for Construction Project TASK DESCRIPTION IMMEDIATE PREDECESSORS DURATION (WEEKS) START Excavate and Pour Footers Pour Concrete Foundation - 1 2 0 3 1 11 12 13 14 Erect Rough Wall & Roof Install Siding Install Plumbing Install Electrical Install Wallboard Lay Flooring Do Interior Painting Install Interior Fixtures Do Grading & Landscaping FINISH 3 4 4 4 6,7 8 8 9,10 Install Gutters & Downspouts 5 12 11,13 4 6 3 4 5 6 3 3 2 3 0

Entering Task Information

• Default view,

Entry

table on left,

Gantt Chart

on right • You can delete the two left-most columns, “i” and “task mode” by highlighting these columns and pressing the “delete” key (not needed by us) • Task numbers now in left-most column • Enter task name and duration in their field • • The default is weeks or “w” “d” for days and “h” for hours can be used • Enter predecessor task number(s) in the “Predecessors” field • MS Project

automatically

gives start and finish dates based on critical path analysis

Entering Task Information

Task Information

Double-clicking on a task name opens the Task Information” screen

Project Charts

• The

Gantt Chart

view shows task linkages • Since START and FINISH are dummy activities with 0 duration, they are

milestones in MS Project

(black diamonds) Right-click on dates in the chart and then “zoom” as desired • Change view to

Network Diagram

Diagram” (zoom as desired) by clicking on “View” in the menu and then select “Network

Gantt Chart

Network Diagram

Critical Path Analysis

• MS Project 2010 automatically computes the critical path and the earliest and latest start and finish times and slack •

Project, Project Information, Statistics

shows the critical path is 26 weeks in our project

Project Critical Path Length

Critical Path Analysis

• Use the “Detail Gantt” to best display the critical path • Select “View”, “Other Views”, “More Views”, “Detail Gantt” then “Apply” • Use the “Schedule Table” to display all of the early and late start and finish information, along with total and free slack • Again from “View”, select “Table”, and then “Schedule”

Schedule Table & Detail Gantt

Critical Path Analysis

• • • Critical path tasks can be identified as those have zero

total slack (TS)

or

float

• • TS = LF – EF = LS – ES

The TS of only 1 task can be used if we want to be certain about not delaying the project

Free slack (FS) of a task is the difference between the smallest of the ES’s of the task’s immediate successors and the task’s EF.

• Using FS does not affect the start times of a task’s successors • • FS <= TS

FS of multiple tasks can be used without delaying the project FS is shown on the Detail Gantt

Critical Path Analysis

• Notice that tasks 12 and 13 both have 7 weeks of total slack • However, if task 12 uses this slack, it is not available to task 13, so its slack is not free • Tasks 12 and 13 are linked, so delaying the start of 12 delays the start of 13 by the same amount

Summary Tasks

Summary tasks

can be used to better organize a project (see constructionS.mpp) • We add three summary tasks: Structure, Interior, and Exterior • Structure includes current tasks 2 – 4, Interior includes 6 – 11, Exterior includes 5, 12, 13 • Example: highlight “Excavate and Pour Footers,” click on “Tasks”, click on” Summary,” enter “Structure” • Indent first three tasks under “Structure” by highlighting them and selecting “indent” (thick green arrow going to the right)

Creating a Summary Task