Instrument Readiness Review Process

Download Report

Transcript Instrument Readiness Review Process

The Instrument Readiness Review
Process
John Arthur
LCLS Experimental Facilities Division
June 30, 2009
LCLS Transition to Science
DOE Status Review of the LUSI MIE Project
An IRR is…
Part of a layered approach for assuring safe, reliable,
and efficient operation of LCLS
Consistent with SLAC Guidelines for Operations
Chap. 23, Accelerator Safety Reviews and Unreviewed Safety
Issues
Described in XFD document 030-00200-000
Motivated by plans to add 6 major instruments for x-ray
experiments at LCLS over 3-year period
A way to assure that all USI associated with new LCLS
instruments have been identified and mitigated before
starting commissioning of the instrument
A tool that will also be used for reviewing major changes
to instruments after they are operational
IRR Process
NEH ARR – June 30, 2009
2
2
J. Arthur
[email protected]
An IRR is not…
A replacement for normal SLAC WPC
A replacement for the SLAC USI process
Appropriate for minor repairs or changes to LCLS
instruments
Appropriate for review of each LCLS experiment
IRR Process
NEH ARR – June 30, 2009
3
3
J. Arthur
[email protected]
IRR Process
What is reviewed
Documentation
Physical inspection of instrument
Qualifications of staff
Product of review
List of documents reviewed
Record of presentations, interviews
List of review participants
Pre-start and post-start findings of review
IRR Process
NEH ARR – June 30, 2009
4
4
J. Arthur
[email protected]
How IRR process is used
Coordinated by Instrument Scientist
Takes place when instrument is nearly complete, but
allows time to address pre-start issues
May require modification of SAD and/or ASE
Modified SAD must be approved by SLAC Director
Modified ASE must be approved by DOE SSO
After all IRR pre-start issues are closed, LCLS Director
authorizes start of commissioning
IRR Process
NEH ARR – June 30, 2009
5
5
J. Arthur
[email protected]
Who is involved in IRR
Instrument Scientist coordinates
Radiation Physics group reviews shielding, beam
containment issues
SLAC safety committees review issues in their areas
IRR committee has formal meeting to assess status of
reviews, identify pre-start and post-start issues
Committee composed of experts from SLAC and other DOE labs
Invited by LCLS Director
IRR Process
NEH ARR – June 30, 2009
6
6
J. Arthur
[email protected]
Tentative schedule for LCLS IRR’s
AMO instrument
SXR instrument
XPP instrument
CXI instrument
XCS instrument
MEC instrument
mid-July, 2009
March, 2010
July 2010
January 2011
May 2011
2012
IRR for early test phase of instrument may occur earlier
IRR Process
NEH ARR – June 30, 2009
7
7
J. Arthur
[email protected]
IRR for the AMO instrument
NEH lower level
X-ray hutches and control rooms
AMO instrument
Hutch 1
Hutch 2
Hutch 3
10m
hard x-ray line
IRR Process
NEH ARR – June 30, 2009
8
8
J. Arthur
[email protected]
AMO instrument
Designed to focus LCLS x-ray beam, and study interactions
between intense x-ray pulses and atoms or small clusters
IRR Process
NEH ARR – June 30, 2009
9
9
J. Arthur
[email protected]
AMO IRR status
Installation nearly finished
Working with safety committees
Collecting memos from committee chairs
Tentative date for IRR: July 15
Choosing committee, organizing review
IRR Process
NEH ARR – June 30, 2009
10 10
J. Arthur
[email protected]
End of Presentation