GLAST LAT Project
LAT Mgr’s Meeting 2005
LAT Planning Meeting
Mechanical/Thermal Systems
March 17, 2005
Marc Campell
1
LAT Mgr’s Meeting 2005
GLAST LAT Project
Status Mar. 15, 2005
SLAC
• Grid is ready for sell to I&T
• Bonding of Grid Thermistors and fly away thermocouples
complete.
• Shipped to B25 for fit up with Grid Perimeter ring.
2
GLAST LAT Project
LAT Mgr’s Meeting 2005
Status Mar. 15, 2005 (cont)
Lockheed Martin
• New contract for environmental testing of Radiators and X-LAT
Plate is in process.
– Needs to be in place by Mar. 27 (end of existing contract)
• X-LAT plate assembly is 80% complete
– Heat pipes matched drilled to plate
– 4 of 6 bonded
– ECD 3/31
• +Y Radiator panels fabrication is complete less edge taping
and instrumentation installation.
– ECD 4/14
• -Y Radiator fabrication is 85% complete. Final machining,
bottom bracket bonding and instrumentation installation.
– ECD 4/30
3
LAT Mgr’s Meeting 2005
GLAST LAT Project
X-LAT Plate Assy Fit Check
Heat Pipes
Ground Cooling Tube
RIT interface flange
4
LAT Mgr’s Meeting 2005
GLAST LAT Project
-Y Radiator Panel
Reservoir
RIT
interface
flange
LAT
Mounting
Point
5
LAT Mgr’s Meeting 2005
GLAST LAT Project
MECH Milestones
6
LAT Mgr’s Meeting 2005
GLAST LAT Project
Threats to RFI
• LM X-LAT & Radiator delivery have no float.
• Radiator
– First time use of bonding/assembly tool & procedures.
There have been Discrepancies at each step along the way.
MFG schedule and marching army costs.
– Potential cost over runs in testing
• Vibration/Acoustic tests
– Fixture design
– Instrumentation requirements
• Final test plan for thermal vacuum.
– Investigating an alternative chamber.
• Timely resolution of test anomalies.
7