Balancing the production line at
Southern California Door
Company
Virginia Marques-Arbogast
Simulation Modeling & Analysis
Project Objectives
Model the present facility layout and
flow.
Find the current bottlenecks.
Make suggestions to increase
production.
Description
Southern California Door company
produces solid. wooden doors
Model Assumptions
Time distributions have been estimated
based on available data
No downtimes have been considered
No breaks or shifts for operators
Raw material always available
Output Analysis
Avg
Std Var.
Doors
Now
Altern.1
Altern.2
40
47.2
78.2
0
0.83666
0.447214
Recommendations
Invest in two Forklift machines
Redesign facility layout