NITS Implementation
Clover Bubble
NITS Implementation
• FERC Order 676-H
• Phase I
– Non-NITS portion was completed on May 13, 2015
– Scheduling Across Multiple Transmission Systems (SAMTS).
This allows a transmission customer to submit requests on
multiple Transmission Providers OASIS that are dependent
upon each other.
• Phase II
– Currently under development at OATI
2
NITS Implementation (continued)
– Key Preliminary Dates
• 7/25/15: Transmission Providers to post Transition
Plan. Posted under “NITS on OASIS” Folder on OASIS
page.
• 10/25/15: Transmission Provider deadline to provide
to the existing NITS Transmission Customers the
specific information that they intend post on the
NITS on OASIS Templates representing the current
arrangements.
• 1/15/16: Deadline to have NITS customers and/or
Agent registered in EIR.
3
NITS Implementation (continued)
• FERC Order 676-H
– Key Dates
• 2/1/16: OATI to release NITS module to DEMO OASIS
• 2/1/16: OATI training begins and testing
• 3/1/16: OATI to release NITS module to PROD OASIS
• 3/25/16: Transmission Provider deadline to post
information documenting all existing Network Customer’s
arrangements on OASIS using the new OASIS templates.
• 4/25/16: Compliance date. Transmission Provider shall
implement and support all Eligible Customer’s and
Transmission Customer’s use of NITS on OASIS.
4
Clover Bubble
• PACE divided into 3 new
Points of Service
1.
2.
3.
•
PACES
CLOVER
NUT
To manage internal
scheduling constraints
1.
2.
Huntington/Sigurd
Wasatch Front South
• Implementation Date:
October 1, 2015
5
Questions?
6